India's first multi-modal terminal
PORTS & SHIPPING

India's first multi-modal terminal

India’s water transport is gaining a divergent new boost. The government is not only exploiting the country’s water potential optimally but upgrading existing waterways and creating new riverine pathways. With the aim to promote inland waterways as a cheaper and environment-friendly means of transportation, Prime Minister Narendra Modi recently inaugurated India’s first multi-modal terminal in Varanasi by receiving the country’s first container cargo transported on inland waterways from Kolkata.

With an estimated Rs 53.69 billion, equally shared between the Government of India and the World Bank, this is the first of four multi-modal terminals being constructed on the National Waterway-1 (River Ganga) as part of the Jal Vikas project of the Inland Waterways Authority of India.

The project involves the construction of three multi-modal terminals – in Varanasi, Sahibganj and Haldia – two inter-modal terminals and five roll-on-roll-off (Ro-Ro) terminal pairs. The contract for construction of Phase-I of the multi-modal terminal in Varanasi has been bagged by Afcons Infrastructure. Afcons is the leader in marine construction in India, and, is counted among the top 10 marine companies globally (as per the latest ENR survey).

While the terminal in Varanasi reportedly costs Rs 1.69 billion, the second terminal in Sahibhanj, Jharkhand, is expected to be built at Rs 2.80 billion and likely to be ready by June 2019. The third terminal in Haldia will reportedly cost Rs 5.17 billion and is expected to be ready by January 2020.

Immense potential

Banked on 1,320 km of National Waterway-1 from Haldia to Varanasi and spread over 43 hectare, the cargo handling capacity of the terminal is 1.26 mtpa. The cargo that will be handled at the terminal includes stone chips, cement, food grains, fertilisers, sugar, etc.

The potential of inland waterways to emerge as a viable alternative to road transport is immense in a country where barely 3.5 per cent of trade is done through this route. The country’s first terminal on the River Ganga not only promises to generate employment but save fuel and resources at large.

“Owing to the shift of low and medium value cargo to the inland waterways terminal, the project is a big relief to rail and road transport,” says Yoganand M, Project Manager, Afcons Infrastructure. “This way, the railways and roadways will be able to carry high volume and deliver items much faster, thus resulting in increased revenue.” The terminal facilitates a direct greenfield road connecting to NH-2, two mobile harbour cranes capable of lifting 50 tonne at 18-m reach, workers amenities with rest area, dedicated passenger pontoon jetty and terminal administration building. Besides, the project and proposed freight village in Varanasi are expected to generate 500 direct and over 2,000 indirect employment opportunities.

Scope of work

The berthing structure of 8,400 sq m has been constructed using new-generation hydraulic piling rigs and vibro-hammers, with the innovative construction method of using pre-fab mattress projecting inside the river for the construction of the pile foundation. With 72 supporting piles of a total length of 52 m, the piles were constructed in two phases – the first involved the construction of pile from the mattress level to the founding level, while the second phase involved the construction from the mattress level to the final top level. All elements of the superstructure like beams, slabs and fender blocks were precast and erected under floating conditions using modular pontoons and a hydraulic crane of 100-tonne capacity.

Elaborating upon the high-quality materials used in construction, Yoganand said, “The construction joints were provided with GI high rib mesh for best integrity of the structure, and the best quality of aggregates available at Dalla quarry, situated around 140 km from the terminal site, was procured. Also, high-quality corrosion resistant steel (CRS) and high-grade OPC 53 cement were used.”

A 200-tonne Manitovac crane was used to handle heavy precast elements, whereas a 100-tonne hydraulic crane was used for marine erection. The hydraulic crane was mounted with the help of modular pontoons. For the protection work of the bank, 18-m-long boom excavators were used. “The new-generation hydraulic rig is capable of boring 60-m-deep bores and was mainly used for pile construction,” he adds. “However, the vibro-hammers were used for the mattress supporting temporary liner erection.”

Overcoming challenges

River water level does not fluctuate from high tide to low tide everyday like the sea. “Hence, planning and execution of activities related to water levels should be precise; any miss will hit the project schedule badly,” explains Yoganand. “For the terminal project, all required equipment to perform the activity had to be planned and mobilised in a timely fashion.”

Also, waterways can have an adverse impact on the ecology of rivers – not every waterway is cheap and a desirable option in terms of ecology. However, to overcome these challenges, “regular environment impact studies were conducted,” Yoganand affirms. “And, tests for phytoplankton and zooplankton were conducted to prevent any damage to the river water, plants and aquatic ecology.”

In conclusion

Indeed, several safety and environment-friendly measures were undertaken during the execution of the project and after its commissioning. Further, special care was taken to ensure aquatic sustainability and ecology of the river. Besides avoiding direct discharge of any harmful effluents into the Ganga, measures like recycling of construction waste like bentonite fluid was conducted and the debris of construction was collected and disposed in a designated land fill.

Project Details

  • Location: Ramnagar, Varanasi

  • Year of completion: 2018

  • Total construction area: 5.50 hectare

  • Contractor: Afcons Infrastructure. Tel: 022-6719 1000. Website: www.afcons.com

  • Structural consultant: AECOM. Website: www.aecom.com

  • Civil engineer: Inland Water Authority of India (MoS, Government of India). Tel: 0120-254 4036. Website: www.iwai.nic.in

  • Project management consultant: e-gis. Website: www.egis-group.com

India’s water transport is gaining a divergent new boost. The government is not only exploiting the country’s water potential optimally but upgrading existing waterways and creating new riverine pathways. With the aim to promote inland waterways as a cheaper and environment-friendly means of transportation, Prime Minister Narendra Modi recently inaugurated India’s first multi-modal terminal in Varanasi by receiving the country’s first container cargo transported on inland waterways from Kolkata. With an estimated Rs 53.69 billion, equally shared between the Government of India and the World Bank, this is the first of four multi-modal terminals being constructed on the National Waterway-1 (River Ganga) as part of the Jal Vikas project of the Inland Waterways Authority of India. The project involves the construction of three multi-modal terminals – in Varanasi, Sahibganj and Haldia – two inter-modal terminals and five roll-on-roll-off (Ro-Ro) terminal pairs. The contract for construction of Phase-I of the multi-modal terminal in Varanasi has been bagged by Afcons Infrastructure. Afcons is the leader in marine construction in India, and, is counted among the top 10 marine companies globally (as per the latest ENR survey). While the terminal in Varanasi reportedly costs Rs 1.69 billion, the second terminal in Sahibhanj, Jharkhand, is expected to be built at Rs 2.80 billion and likely to be ready by June 2019. The third terminal in Haldia will reportedly cost Rs 5.17 billion and is expected to be ready by January 2020. Immense potential Banked on 1,320 km of National Waterway-1 from Haldia to Varanasi and spread over 43 hectare, the cargo handling capacity of the terminal is 1.26 mtpa. The cargo that will be handled at the terminal includes stone chips, cement, food grains, fertilisers, sugar, etc. The potential of inland waterways to emerge as a viable alternative to road transport is immense in a country where barely 3.5 per cent of trade is done through this route. The country’s first terminal on the River Ganga not only promises to generate employment but save fuel and resources at large. “Owing to the shift of low and medium value cargo to the inland waterways terminal, the project is a big relief to rail and road transport,” says Yoganand M, Project Manager, Afcons Infrastructure. “This way, the railways and roadways will be able to carry high volume and deliver items much faster, thus resulting in increased revenue.” The terminal facilitates a direct greenfield road connecting to NH-2, two mobile harbour cranes capable of lifting 50 tonne at 18-m reach, workers amenities with rest area, dedicated passenger pontoon jetty and terminal administration building. Besides, the project and proposed freight village in Varanasi are expected to generate 500 direct and over 2,000 indirect employment opportunities. Scope of work The berthing structure of 8,400 sq m has been constructed using new-generation hydraulic piling rigs and vibro-hammers, with the innovative construction method of using pre-fab mattress projecting inside the river for the construction of the pile foundation. With 72 supporting piles of a total length of 52 m, the piles were constructed in two phases – the first involved the construction of pile from the mattress level to the founding level, while the second phase involved the construction from the mattress level to the final top level. All elements of the superstructure like beams, slabs and fender blocks were precast and erected under floating conditions using modular pontoons and a hydraulic crane of 100-tonne capacity. Elaborating upon the high-quality materials used in construction, Yoganand said, “The construction joints were provided with GI high rib mesh for best integrity of the structure, and the best quality of aggregates available at Dalla quarry, situated around 140 km from the terminal site, was procured. Also, high-quality corrosion resistant steel (CRS) and high-grade OPC 53 cement were used.” A 200-tonne Manitovac crane was used to handle heavy precast elements, whereas a 100-tonne hydraulic crane was used for marine erection. The hydraulic crane was mounted with the help of modular pontoons. For the protection work of the bank, 18-m-long boom excavators were used. “The new-generation hydraulic rig is capable of boring 60-m-deep bores and was mainly used for pile construction,” he adds. “However, the vibro-hammers were used for the mattress supporting temporary liner erection.” Overcoming challenges River water level does not fluctuate from high tide to low tide everyday like the sea. “Hence, planning and execution of activities related to water levels should be precise; any miss will hit the project schedule badly,” explains Yoganand. “For the terminal project, all required equipment to perform the activity had to be planned and mobilised in a timely fashion.” Also, waterways can have an adverse impact on the ecology of rivers – not every waterway is cheap and a desirable option in terms of ecology. However, to overcome these challenges, “regular environment impact studies were conducted,” Yoganand affirms. “And, tests for phytoplankton and zooplankton were conducted to prevent any damage to the river water, plants and aquatic ecology.” In conclusion Indeed, several safety and environment-friendly measures were undertaken during the execution of the project and after its commissioning. Further, special care was taken to ensure aquatic sustainability and ecology of the river. Besides avoiding direct discharge of any harmful effluents into the Ganga, measures like recycling of construction waste like bentonite fluid was conducted and the debris of construction was collected and disposed in a designated land fill. Project Details Location: Ramnagar, Varanasi Year of completion: 2018 Total construction area: 5.50 hectare Contractor: Afcons Infrastructure. Tel: 022-6719 1000. Website: www.afcons.com Structural consultant: AECOM. Website: www.aecom.com Civil engineer: Inland Water Authority of India (MoS, Government of India). Tel: 0120-254 4036. Website: www.iwai.nic.in Project management consultant: e-gis. Website: www.egis-group.com

Next Story
Resources

Cushman & Wakefield Names Sona Aggarwal as APAC Retail Lead

Cushman & Wakefield, a global real estate services firm, has announced the appointment of Sona Aggarwal as Managing Director, Head of Retail Sales and Strategy, Asia Pacific. Based in Singapore, Sona joins at a pivotal time as the firm scales up its regional retail platform, aiming to deliver global expertise to clients across Asia Pacific (APAC) and beyond. With over 25 years of experience in global brand management and retail operations, Sona has led the launch and operations of more than 200 stores across APAC, managing cross-border teams of over 1,300 people. Her deep understandin..

Next Story
Technology

CommScope Launches CableGuide 360 and Enhanced FiberREACH Solutions

CommScope, a global leader in network connectivity, has introduced two new solutions under its SYSTIMAX® 2.0 portfolio—the enhanced FiberREACH™ solution and the new CableGuide 360™ platform. These solutions aim to help enterprises extend power and connectivity to the network edge while simplifying high-density cable management. Previously known as the Powered Fiber Cable System (PFCS), FiberREACH builds on its legacy by integrating advanced hybrid-fibre cabling, increased power delivery, and chassis solutions. The upgraded system now supports up to 90W of Power over Ethernet (PoE) ..

Next Story
Real Estate

Lodha Buys Rs 5.67 Billion Transit Units in Mankhurd

Mumbai-based listed real estate developer Lodha Developers Limited has acquired 945 permanent transit camp (PTC) units measuring 339,000 square feet from Arihant Construction Company for Rs 5.67 billion. The transaction, registered on 3 June 2025, is part of Lodha’s obligations under the Slum Rehabilitation Authority (SRA) scheme related to its ongoing township project in Vikhroli.The acquired units in Mankhurd will be handed over to the SRA to secure development rights for free-sale construction under the Vikhroli project. The deal includes a stamp duty payment of Rs 340.2 million and regis..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?