Mulapeta Port Project Gets 409-Day Extension To 2026
PORTS & SHIPPING

Mulapeta Port Project Gets 409-Day Extension To 2026

The state government has approved a 409-day extension for the Mulapeta Greenfield Port project, permitting completion by 30 November 2026 without levying liquidated damages on the contractor. Officials said the extension was justified as delays stemmed from factors beyond the contractor’s control, including adverse weather, cyclones, restrictions on minor minerals, limited site access and delays in handing over encumbrance-free land for external infrastructure.

Phase I of the Mulapeta Port—previously known as Bhavanapadu Port—was sanctioned on 17 August 2021 with a total project cost of Rs 43.62 billion under the landlord model. The contract was awarded to Viswa Samudra Ports (JV), Hyderabad, on 2 August 2022 at a value of Rs 29.50 billion, with the original completion date set for 17 October 2025.

Key project components include construction of breakwaters, dredging works, berthing structures, onshore facilities, and the development of external road and rail links, along with power and water supply infrastructure. As of October 2025, physical progress stood at 60.49 per cent and financial progress at 56.28 per cent.

Following a detailed review, project management consultant TCE Ltd recommended granting the extension, citing unavoidable delays. The EPC contractor has provided an undertaking stating it will not seek additional costs due to the extended timeline, while maintaining its contractual rights.

The state government has approved a 409-day extension for the Mulapeta Greenfield Port project, permitting completion by 30 November 2026 without levying liquidated damages on the contractor. Officials said the extension was justified as delays stemmed from factors beyond the contractor’s control, including adverse weather, cyclones, restrictions on minor minerals, limited site access and delays in handing over encumbrance-free land for external infrastructure. Phase I of the Mulapeta Port—previously known as Bhavanapadu Port—was sanctioned on 17 August 2021 with a total project cost of Rs 43.62 billion under the landlord model. The contract was awarded to Viswa Samudra Ports (JV), Hyderabad, on 2 August 2022 at a value of Rs 29.50 billion, with the original completion date set for 17 October 2025. Key project components include construction of breakwaters, dredging works, berthing structures, onshore facilities, and the development of external road and rail links, along with power and water supply infrastructure. As of October 2025, physical progress stood at 60.49 per cent and financial progress at 56.28 per cent. Following a detailed review, project management consultant TCE Ltd recommended granting the extension, citing unavoidable delays. The EPC contractor has provided an undertaking stating it will not seek additional costs due to the extended timeline, while maintaining its contractual rights.

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement