Panel Urges MoHUA To Expedite Wastewater Projects
WATER & WASTE

Panel Urges MoHUA To Expedite Wastewater Projects

Five years after the launch of AMRUT 2.0 the Parliamentary Standing Committee on Housing and Urban Affairs urged MoHUA to expedite sewerage and septage management projects. It noted that of 594 approved projects, with a total approved cost of Rs 683.09 billion (bn), only 104 projects, or 17.51 per cent, have been completed while 398 projects, or 67 per cent, remain under implementation. The report was chaired by Telugu Desam Party Member of Parliament Magunta Sreenivasulu Reddy.

The panel noted that 502 projects have reached the awarded or grounded stage but 38 projects involving an approved cost of Rs 75.64 billion (bn) remain at the tender stage. It said the slow pace of implementation under AMRUT and AMRUT 2.0 is delaying planned expansion of sanitation infrastructure and undermining urban sanitation outcomes in statutory towns. The committee urged removal of administrative and procedural impediments to speed execution.

The committee found that fund release to states has been sluggish. Against the total Central Assistance commitment of Rs 660.60 billion (bn) under AMRUT and AMRUT 2.0 only Rs 227.63 billion (bn), or 34.46 per cent, has been released so far and this could affect timely creation of treatment capacity, sewerage connectivity and septage management systems in rapidly urbanising areas. It called for closer monitoring of fund flows and identification of projects where release is lagging.

MoHUA said delays stemmed from tendering, land acquisition, statutory clearances, contractor issues, changes in project scope and limited technical capacity at urban local bodies, and stressed that projects are long gestation and require centre state coordination. The committee recommended milestone based monitoring and stricter timelines for states and union territories given the mission now ends on 31 March 2027, and asked the ministry to identify where fund release is lagging. AMRUT 2.0 was launched in October 2021 and had an initial outlay of Rs 3 trillion (tn), including a central outlay of Rs 767.60 billion (bn).

Five years after the launch of AMRUT 2.0 the Parliamentary Standing Committee on Housing and Urban Affairs urged MoHUA to expedite sewerage and septage management projects. It noted that of 594 approved projects, with a total approved cost of Rs 683.09 billion (bn), only 104 projects, or 17.51 per cent, have been completed while 398 projects, or 67 per cent, remain under implementation. The report was chaired by Telugu Desam Party Member of Parliament Magunta Sreenivasulu Reddy. The panel noted that 502 projects have reached the awarded or grounded stage but 38 projects involving an approved cost of Rs 75.64 billion (bn) remain at the tender stage. It said the slow pace of implementation under AMRUT and AMRUT 2.0 is delaying planned expansion of sanitation infrastructure and undermining urban sanitation outcomes in statutory towns. The committee urged removal of administrative and procedural impediments to speed execution. The committee found that fund release to states has been sluggish. Against the total Central Assistance commitment of Rs 660.60 billion (bn) under AMRUT and AMRUT 2.0 only Rs 227.63 billion (bn), or 34.46 per cent, has been released so far and this could affect timely creation of treatment capacity, sewerage connectivity and septage management systems in rapidly urbanising areas. It called for closer monitoring of fund flows and identification of projects where release is lagging. MoHUA said delays stemmed from tendering, land acquisition, statutory clearances, contractor issues, changes in project scope and limited technical capacity at urban local bodies, and stressed that projects are long gestation and require centre state coordination. The committee recommended milestone based monitoring and stricter timelines for states and union territories given the mission now ends on 31 March 2027, and asked the ministry to identify where fund release is lagging. AMRUT 2.0 was launched in October 2021 and had an initial outlay of Rs 3 trillion (tn), including a central outlay of Rs 767.60 billion (bn).

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code