+
360 projects report cost overruns of Rs 3.88 tn
PORTS & SHIPPING

360 projects report cost overruns of Rs 3.88 tn

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for June 2019, according to which, out of a total 1,608 projects, more than 360 have shown cost overruns to the tune of Rs 3.88 trillion.

The report states that the original estimated cost of all the projects is approximately Rs 19.18 trillion. Completion cost is now expected to be around Rs 23.05 trillion. This amounts to cost overruns of around 20.23 per cent from the original cost. Additionally, the report included the number of projects that had crossed their deadlines; these amounted to 550. The average time overrun for all 550 projects was reported to be 39.24 months.

Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints because of funding, geographical conditions, labour issues and court cases, among other reasons.

“Project implementation in certain infrastructure sectors continues to remain challenging, with many projects witnessing significant time and cost overruns,” says Shubham Jain, Group Head & Senior Vice-President, Corporate Ratings, ICRA. “As per the recent data available, the aggregate cost overrun for all major ongoing infrastructure projects as a percentage of original cost had increased to over 20 per cent—the highest in about eight years. Two key sectors—railways and power—have contributed to the majority of the cost overruns. This is despite the various reform measures undertaken by the Government. Delays in land acquisition, the difficulty faced in project financing, and increasing cost of land acquisition have been some of the key reasons behind the time and cost overruns.”

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for June 2019, according to which, out of a total 1,608 projects, more than 360 have shown cost overruns to the tune of Rs 3.88 trillion. The report states that the original estimated cost of all the projects is approximately Rs 19.18 trillion. Completion cost is now expected to be around Rs 23.05 trillion. This amounts to cost overruns of around 20.23 per cent from the original cost. Additionally, the report included the number of projects that had crossed their deadlines; these amounted to 550. The average time overrun for all 550 projects was reported to be 39.24 months. Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints because of funding, geographical conditions, labour issues and court cases, among other reasons. “Project implementation in certain infrastructure sectors continues to remain challenging, with many projects witnessing significant time and cost overruns,” says Shubham Jain, Group Head & Senior Vice-President, Corporate Ratings, ICRA. “As per the recent data available, the aggregate cost overrun for all major ongoing infrastructure projects as a percentage of original cost had increased to over 20 per cent—the highest in about eight years. Two key sectors—railways and power—have contributed to the majority of the cost overruns. This is despite the various reform measures undertaken by the Government. Delays in land acquisition, the difficulty faced in project financing, and increasing cost of land acquisition have been some of the key reasons behind the time and cost overruns.”

Next Story
Infrastructure Urban

ITCONS Gains on New Rs 3.5 Million Defence Contract

ITCONS E-Solutions is trading at Rs 549.00, up by Rs 12.10 or 2.25 per cent from its previous close of Rs 536.90 on the BSE. The scrip opened at Rs 549.00 and has touched an intraday high and low of Rs 549.00, with 200 shares traded so far.A BSE ‘MT’ group stock with a face value of Rs 10, ITCONS touched its 52-week high of Rs 767.00 on 25 September 2024 and a 52-week low of Rs 166.70 on 5 August 2024. Over the past week, the stock has fluctuated between Rs 560.00 and Rs 510.60. The company's current market capitalisation stands at Rs 3.3 billion.Promoters hold 58.22 per cent of the compan..

Next Story
Infrastructure Urban

Delhi Extends EV Policy Till March 2026

The Delhi government has extended its existing Electric Vehicle (EV) Policy until 31 March 2026, or until a revised version is approved. The decision was made during a Cabinet meeting chaired by Chief Minister Rekha Gupta on Tuesday.According to Transport Minister Pankaj Kumar Singh, the draft of the new policy will undergo broader public consultation before being finalised, prompting the extension to allow time for thorough stakeholder engagement.The consultation process will include inputs from citizens, environmental groups, academic institutions, industry experts, and private firms. Key fo..

Next Story
Infrastructure Urban

Ather Crosses 400 Fast Chargers in Maharashtra

Electric two-wheeler manufacturer Ather Energy announced on Thursday that it has surpassed 400 fast charging points under its Ather Grid network across Maharashtra.The company's fast charging infrastructure now spans 35 cities in the state, including key urban centres such as Mumbai, Nashik, Pune, and Nagpur."Crossing 400 fast chargers in the state is about giving riders the assurance that they'll always find a charger when they need one. As we expand our retail presence, the charging network will continue to grow in tandem to make EV ownership truly seamless," said Ravneet Singh Phokela, Chie..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?