Highway projects mostly at risk in four states
Real Estate

Highway projects mostly at risk in four states

Photo: For representational purpose

Construction of national highways came to a grinding halt with the nationwide lockdown imposed on March 25, 2020, to fight the COVID-19 pandemic. However, to the relief of developers, the government allowed resumption of construction  from April 20, subject to clearances from district administrations.

But activity remains stalled due to severe shortage of labour and raw material, and difficulty in securing requisite clearances.

What’s more, the Centre has divided districts into red, orange and green zones based on the extent of contagion. Only insitu construction is allowed in red zones until the next announcement.

As per a press note by CRISIL Research, the firm’s analysis of over 270 under-construction national highways indicates the top 10 states account for 80 per cent of the projects.

The zones of maximum risk

Projects are most at risk in four of these states – Maharashtra, Uttar Pradesh, Tamil Nadu and Andhra Pradesh – that account for over a third of the projects.

In Maharashtra, which has 11 per cent of the national highway projects, as much as 55 per cent of it is in red zones.

In Uttar Pradesh, which has the lion’s share of projects under construction at 15 per cent, a third is in the red zones.

Projects in Tamil Nadu and Andhra Pradesh, each with over 35 per cent projects in red zones, are also at risk.

In the milieu, for developers, containment of the pandemic and lifting of the extended lockdown are the key monitorables for a return to normalcy.

About a fifth of under-construction NHAI projects are in the red zones of the top 10 states

Those in Maharashtra, Uttar Pradesh, Gujarat, Tamil Nadu and Andhra Pradesh are at higher risk


Photo: For representational purpose Construction of national highways came to a grinding halt with the nationwide lockdown imposed on March 25, 2020, to fight the COVID-19 pandemic. However, to the relief of developers, the government allowed resumption of construction  from April 20, subject to clearances from district administrations. But activity remains stalled due to severe shortage of labour and raw material, and difficulty in securing requisite clearances. What’s more, the Centre has divided districts into red, orange and green zones based on the extent of contagion. Only insitu construction is allowed in red zones until the next announcement. As per a press note by CRISIL Research, the firm’s analysis of over 270 under-construction national highways indicates the top 10 states account for 80 per cent of the projects. The zones of maximum risk Projects are most at risk in four of these states – Maharashtra, Uttar Pradesh, Tamil Nadu and Andhra Pradesh – that account for over a third of the projects. In Maharashtra, which has 11 per cent of the national highway projects, as much as 55 per cent of it is in red zones. In Uttar Pradesh, which has the lion’s share of projects under construction at 15 per cent, a third is in the red zones. Projects in Tamil Nadu and Andhra Pradesh, each with over 35 per cent projects in red zones, are also at risk. In the milieu, for developers, containment of the pandemic and lifting of the extended lockdown are the key monitorables for a return to normalcy. About a fifth of under-construction NHAI projects are in the red zones of the top 10 states Those in Maharashtra, Uttar Pradesh, Gujarat, Tamil Nadu and Andhra Pradesh are at higher risk

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App