Slipforms for hydropower projects
POWER & RENEWABLE ENERGY

Slipforms for hydropower projects

HCC opted for slipforms for the concreting of a 115-m-deep surge shaft for the Punatsangchhu hydropower project Stage I, a 1,200-mw, run-of-the-river project in Western Bhutan.

“We opted for slip-forming because it enables continuous, non-interrupted, cast-in-place jointless concrete structures that have superior performance characteristics compared to piece-wise construction using discrete form elements,” says S D Jeur, Senior Vice-President, Projects, HCC.

Slipforms with a three-layered platform structure were used. The entire formwork structure was built in-house. The top platform was used to erect the reinforcement concrete, the middle platform was used for general movement, and the bottom one was used to provide the finishing to the concrete surface.

Slipforms have to be in a continuous motion so that the concrete does not stick to them. The speed of this formwork depends on several factors like the weather condition, the amount of concrete poured at a time and the size of the structure. As the slipform can move (slipping rate, usually between 5 and 30 cm/hour) whenever the concrete can carry the load of its weight in the lowest parts of form sheet, the likely concrete setting time was determined based on the weather conditions (temperature, humidity, etc), cement ratio, type of cement, slump and admixtures.

Usually, the slipform structure rises up with the daily progress of 0.75 m/day in standard conditions. However, at Punatsangchhu-I HEP, the daily progress harnessed from slipform was at an average of 1 m/day. The concrete lining thickness varied from 850 mm at the top, 1,200 mm in the middle and 1,500 mm at the bottom. Concrete was poured into the forms in layers of about 200 mm.

CHARU BAHRI

HCC opted for slipforms for the concreting of a 115-m-deep surge shaft for the Punatsangchhu hydropower project Stage I, a 1,200-mw, run-of-the-river project in Western Bhutan. “We opted for slip-forming because it enables continuous, non-interrupted, cast-in-place jointless concrete structures that have superior performance characteristics compared to piece-wise construction using discrete form elements,” says S D Jeur, Senior Vice-President, Projects, HCC. Slipforms with a three-layered platform structure were used. The entire formwork structure was built in-house. The top platform was used to erect the reinforcement concrete, the middle platform was used for general movement, and the bottom one was used to provide the finishing to the concrete surface. Slipforms have to be in a continuous motion so that the concrete does not stick to them. The speed of this formwork depends on several factors like the weather condition, the amount of concrete poured at a time and the size of the structure. As the slipform can move (slipping rate, usually between 5 and 30 cm/hour) whenever the concrete can carry the load of its weight in the lowest parts of form sheet, the likely concrete setting time was determined based on the weather conditions (temperature, humidity, etc), cement ratio, type of cement, slump and admixtures. Usually, the slipform structure rises up with the daily progress of 0.75 m/day in standard conditions. However, at Punatsangchhu-I HEP, the daily progress harnessed from slipform was at an average of 1 m/day. The concrete lining thickness varied from 850 mm at the top, 1,200 mm in the middle and 1,500 mm at the bottom. Concrete was poured into the forms in layers of about 200 mm. CHARU BAHRI

Next Story
Infrastructure Urban

Gentari and Shell team up to boost EV charging network in India

Gentari Green Mobility India and Shell India have entered into a strategic roaming partnership aimed at improving electric vehicle (EV) charging accessibility across the country. Starting from 10 July, users of the Gentari Go app will be able to access Shell Recharge charging stations, while Shell Recharge users will also gain access to Gentari’s charging network, covering over 450 chargers.This collaboration is designed to expand the EV charging infrastructure and improve service quality in India by enabling interoperability between the two platforms. Gentari Go already operates more than 3..

Next Story
Infrastructure Transport

Maharashtra may allow higher FSI in Mumbai airport funnel zone

The Maharashtra government is considering the possibility of allowing higher potential Floor Space Index (FSI) for buildings located within Mumbai's airport funnel zone, in response to the redevelopment challenges caused by stringent height restrictions in these areas.The affected regions mainly include Vile Parle, Santacruz, and Kurla. As part of its revised policy for the funnel zone, the state government is, for the first time, offering Transfer of Development Rights (TDR) specifically for redevelopment purposes rather than for land acquisition.The issue was highlighted in the Assembly, whe..

Next Story
Infrastructure Transport

Adani Ports, Airports May Raise $250 Mn from MUFG Amid US Scrutiny

Two entities under the Adani Group are in advanced negotiations to secure around $250 million in offshore bilateral loans from Mitsubishi UFJ Financial Group (MUFG), according to a Bloomberg report citing sources familiar with the matter.Adani Ports and Special Economic Zone is expected to raise approximately $100 million, while Adani Airport Holdings aims to secure about $150 million. The agreement related to the ports business could be finalised as early as this week. In addition to MUFG, both companies are also reportedly exploring funding options with other Japanese banks.This marks MUFG..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?