BGRESL to commence work on Ennore thermal power station project
POWER & RENEWABLE ENERGY

BGRESL to commence work on Ennore thermal power station project

After five years, the physical work on the 660 MW Ennore thermal power station expansion project is likely to commence with the handing over of the site to the contractor BGR Energy Systems (BGRESL).

The ETPS expansion project site was handed over to the BGRESL in June and they have started work on the testing of the structures with a team of IIT Madras experts. After the completion of the tests, the contractor will commence the work.

ETPS expansion project work has been facing delay after delay. Tangedco awarded the EPC contract to Lanco Infra Tech (LITL) in May 2014. However, the LITL faced financial troubles and work came to a halt in August 2017. Tangedco terminated the contract in April 2018 ever since the project came to a standstill.

After five years, the physical work on the 660 MW Ennore thermal power station expansion project is likely to commence with the handing over of the site to the contractor BGR Energy Systems (BGRESL). The ETPS expansion project site was handed over to the BGRESL in June and they have started work on the testing of the structures with a team of IIT Madras experts. After the completion of the tests, the contractor will commence the work. ETPS expansion project work has been facing delay after delay. Tangedco awarded the EPC contract to Lanco Infra Tech (LITL) in May 2014. However, the LITL faced financial troubles and work came to a halt in August 2017. Tangedco terminated the contract in April 2018 ever since the project came to a standstill.

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App