BGRESL to commence work on Ennore thermal power station project
POWER & RENEWABLE ENERGY

BGRESL to commence work on Ennore thermal power station project

After five years, the physical work on the 660 MW Ennore thermal power station expansion project is likely to commence with the handing over of the site to the contractor BGR Energy Systems (BGRESL).

The ETPS expansion project site was handed over to the BGRESL in June and they have started work on the testing of the structures with a team of IIT Madras experts. After the completion of the tests, the contractor will commence the work.

ETPS expansion project work has been facing delay after delay. Tangedco awarded the EPC contract to Lanco Infra Tech (LITL) in May 2014. However, the LITL faced financial troubles and work came to a halt in August 2017. Tangedco terminated the contract in April 2018 ever since the project came to a standstill.

After five years, the physical work on the 660 MW Ennore thermal power station expansion project is likely to commence with the handing over of the site to the contractor BGR Energy Systems (BGRESL). The ETPS expansion project site was handed over to the BGRESL in June and they have started work on the testing of the structures with a team of IIT Madras experts. After the completion of the tests, the contractor will commence the work. ETPS expansion project work has been facing delay after delay. Tangedco awarded the EPC contract to Lanco Infra Tech (LITL) in May 2014. However, the LITL faced financial troubles and work came to a halt in August 2017. Tangedco terminated the contract in April 2018 ever since the project came to a standstill.

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement