CERC Restores Grid Connectivity for Serentica and ReNew
POWER & RENEWABLE ENERGY

CERC Restores Grid Connectivity for Serentica and ReNew

The Central Electricity Regulatory Commission set aside revocation of grid connectivity for renewable projects by Serentica Renewables India 4 Pvt Ltd and ReNew Green entities and directed payment of compensation for commissioning delays. The Commission emphasised the need to protect transmission infrastructure while ensuring regulatory compliance. Relief was conditional and linked to specified penalties.

The dispute began after the Central Transmission Utility of India Limited revoked connectivity on the ground that projects had not been commissioned within timelines under the General Network Access regulations. The developers contested the action, arguing they were transitioned entities and that the six-month revocation period should be measured from the new connectivity start date granted during transition rather than from the scheduled date of commercial operation (SCOD). They cited uncontrollable factors including unprecedented rainfall that halted construction for more than 100 workdays, right of way issues, farmer protests and clearance delays.

The petitioners said projects were at advanced stages with multiple wind turbine generators erected and substantial capital deployed, noting investments of around Rs 11,870 million (mn) by Serentica and about Rs 26,810 mn by ReNew. CTUIL maintained that transitioned developers became deemed applicants bound by the regulations and that the grant of connectivity did not alter original commissioning timelines. The transmission utility argued it lacked authority to relax statutory provisions and that revocation followed the prescribed procedure when deadlines were missed.

After review CERC found that Regulation 24.6 applies to transitioned entities but identified a gap in the transition process that left the scheduled date of commercial operation undefined and therefore ruled that the SCOD should be equated to the new connectivity start date in such cases. The Commission set aside the revocation notices under its powers but granted conditional relief requiring payment of compensation linked to delays, beginning with charges equivalent to 50 per cent of bank guarantees for the first three months and escalating daily penalties thereafter. The Commission capped delay at 15 months and warned connectivity will be revoked if projects are not commissioned within that timeframe, aiming to safeguard investments.

The Central Electricity Regulatory Commission set aside revocation of grid connectivity for renewable projects by Serentica Renewables India 4 Pvt Ltd and ReNew Green entities and directed payment of compensation for commissioning delays. The Commission emphasised the need to protect transmission infrastructure while ensuring regulatory compliance. Relief was conditional and linked to specified penalties. The dispute began after the Central Transmission Utility of India Limited revoked connectivity on the ground that projects had not been commissioned within timelines under the General Network Access regulations. The developers contested the action, arguing they were transitioned entities and that the six-month revocation period should be measured from the new connectivity start date granted during transition rather than from the scheduled date of commercial operation (SCOD). They cited uncontrollable factors including unprecedented rainfall that halted construction for more than 100 workdays, right of way issues, farmer protests and clearance delays. The petitioners said projects were at advanced stages with multiple wind turbine generators erected and substantial capital deployed, noting investments of around Rs 11,870 million (mn) by Serentica and about Rs 26,810 mn by ReNew. CTUIL maintained that transitioned developers became deemed applicants bound by the regulations and that the grant of connectivity did not alter original commissioning timelines. The transmission utility argued it lacked authority to relax statutory provisions and that revocation followed the prescribed procedure when deadlines were missed. After review CERC found that Regulation 24.6 applies to transitioned entities but identified a gap in the transition process that left the scheduled date of commercial operation undefined and therefore ruled that the SCOD should be equated to the new connectivity start date in such cases. The Commission set aside the revocation notices under its powers but granted conditional relief requiring payment of compensation linked to delays, beginning with charges equivalent to 50 per cent of bank guarantees for the first three months and escalating daily penalties thereafter. The Commission capped delay at 15 months and warned connectivity will be revoked if projects are not commissioned within that timeframe, aiming to safeguard investments.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Assam Gets Approval For 350,000 PMAY Homes

Assam Chief Minister Himanta Biswa Sarma met Union Agriculture Minister Shivraj Singh Chouhan in New Delhi, where the minister handed an approval document for 310,000 new homes under the Pradhan Mantri Awas Yojana. The chief minister subsequently posted on X expressing gratitude and noting that the minister had formally handed approval for 380,000 homes as well. The release and the social media post contained varying figures, with broader references to 350,000 homes reported in some summaries. The approvals carry central assistance equivalent to Rs 50 billion (bn), corresponding to the five th..

Next Story
Infrastructure Urban

KPIGreen Achieves Highest Energised Capacity of 630+ MW DC

KPI Green Energy energised more than 630 MW DC of capacity in the June to August quarter, marking the highest quarterly addition in the company's history. The capacity was brought online across its Independent Power Producer (IPP) and Engineering, Procurement and Construction (EPC) businesses. The company said the achievement reflected the scale, speed and consistency of its project execution engine. The firm described the quarter as a material operational milestone since its founding. The milestone covers a diversified mix of IPP assets and projects executed under the EPC vertical, spanning u..

Next Story
Infrastructure Energy

Adani Energy Solutions Wins Rs 47 bn Maharashtra Transmission Project

Adani Energy Solutions has won a transmission contract in Maharashtra valued at Rs 47 billion (Rs 47 bn) to evacuate 4,500 megawatt (MW) of renewable and storage power. The company informed exchanges that the project will facilitate pumped storage potential near Satara and strengthen the inter-regional corridor between the Western and Southern grids. The award follows a competitive bidding process and will support renewable energy evacuation to major load centres in the state. The scope includes establishment of a 765/400 kV substation at Satara, construction of a Kolhapur-Satara 765 kV double..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code