Environmental Hearing Set for 1000 MW Naying Hydro Project
POWER & RENEWABLE ENERGY

Environmental Hearing Set for 1000 MW Naying Hydro Project

The environmental public hearing for the 1,000 MW Naying hydroelectric project will take place on November 12 at Yapik community hall in Shi-Yomi district, Arunachal Pradesh, officials confirmed. The run-of-the-river project on the Siyom (Yomgo) river is being developed by the North Eastern Electric Power Corporation (NEEPCO).

Construction, including a concrete dam, underground powerhouse, and tunnel, is expected to commence around 2028, with commissioning planned by 2032. The project aims to generate approximately 4,966.77 GWh of electricity.

The Naying project received Central Electricity Authority concurrence in 2013. Earlier construction timelines were delayed due to environmental and social concerns, including the diversion of significant forest land and public protests over dam impacts.

On October 7, the Arunachal Pradesh government approved joint ventures between NEEPCO and Arunachal Pradesh Hydropower Corporation Ltd to advance the state’s hydro power mission under the Decade of Hydro Power (2025–35), targeting 19 GW capacity, investment attraction, and job creation while supporting India’s net-zero goals.

The environmental public hearing for the 1,000 MW Naying hydroelectric project will take place on November 12 at Yapik community hall in Shi-Yomi district, Arunachal Pradesh, officials confirmed. The run-of-the-river project on the Siyom (Yomgo) river is being developed by the North Eastern Electric Power Corporation (NEEPCO). Construction, including a concrete dam, underground powerhouse, and tunnel, is expected to commence around 2028, with commissioning planned by 2032. The project aims to generate approximately 4,966.77 GWh of electricity. The Naying project received Central Electricity Authority concurrence in 2013. Earlier construction timelines were delayed due to environmental and social concerns, including the diversion of significant forest land and public protests over dam impacts. On October 7, the Arunachal Pradesh government approved joint ventures between NEEPCO and Arunachal Pradesh Hydropower Corporation Ltd to advance the state’s hydro power mission under the Decade of Hydro Power (2025–35), targeting 19 GW capacity, investment attraction, and job creation while supporting India’s net-zero goals.

Next Story
Infrastructure Energy

Vedanta Aluminium Uses 1.57 bn Units of Green Energy in FY25

Vedanta Aluminium, India’s largest aluminium producer, recently reported consumption of 1.57 billion units of renewable energy in FY25, marking a significant milestone in its 2030 decarbonisation roadmap. The company also achieved an 8.96 per cent reduction in greenhouse gas (GHG) emissions intensity compared to FY21, reinforcing its leadership in India’s low-carbon manufacturing transition. During FY25, Vedanta Aluminium expanded its renewable energy portfolio through long-term power purchase agreements, strengthening its strategy to source nearly 1,500 MW of renewable power over the lon..

Next Story
Real Estate

Oberoi Group to Develop Luxury Resort at Makaibari Tea Estate

EIH Limited, the flagship company of The Oberoi Group, has announced the signing of a management agreement to develop an Oberoi luxury resort at the iconic Makaibari Tea Estate in Darjeeling. The project marks a key milestone in the Group’s long-term strategy of creating distinctive hospitality experiences in rare and environmentally significant locations. Established in 1859, Makaibari is one of the world’s oldest tea estates and is globally recognised for its Himalayan landscape, primary forests and exceptional biodiversity. Spread across 1,236 acres, the estate houses one of the world..

Next Story
Real Estate

GHV Infra Secures Rs 1.09 Bn EPC Order in Jamshedpur

GHV Infra Projects Ltd, a fast-growing EPC company in India’s infrastructure and construction sector, has recently secured a Rs 1.09 billion work order in Jamshedpur, Jharkhand. Awarded by a reputed group entity, the contract covers end-to-end civil construction, mechanical, electrical and plumbing (MEP) systems, along with high-quality finishing works for a large building development. The project will be executed over a 30-month period, with defined benchmarks for quality, safety and timely delivery. The order strengthens GHV Infra’s footprint in Jamshedpur, a key industrial hub known fo..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App