+
Godawari Power Reports Stable H1 With Strong Margins And Project Progress
POWER & RENEWABLE ENERGY

Godawari Power Reports Stable H1 With Strong Margins And Project Progress

Godawari Power & Ispat Ltd, a fully integrated steel producer, has announced its financial results for Q2 and H1 FY26, reporting stable performance supported by higher pellet and galvanised product volumes and continued progress on major expansion projects.

Q2 FY26 – Key Financial Highlights

Revenue, EBITDA and PAT recorded slight year-on-year growth, driven by increased sales volumes of pellets and rolled structural products.

Sequentially, sales, EBITDA and PAT were lower due to reduced realisations in iron ore pellets and finished steel.

EBITDA and PAT margins remained strong at 20 per cent and 12 per cent, respectively.

H1 FY26 – Key Financial Highlights

Sales turnover remained largely stable, supported by higher production and sales of pellets and galvanised fabricated products.

EBITDA and PAT were lower year-on-year due to softer sales realisations.

Margins remained healthy, with EBITDA at 22 per cent and PAT at 14 per cent.

Q2 & H1 FY26 – Key Operational Updates

Mining expansion: Public hearing for expanding the Ari Dongri Iron Ore Mine from 2.35 MTPA to 6 MTPA has been completed. Environmental approval is expected by December 2025.

Volume performance: GPIL is on track to meet its FY26 production targets, with strong progress in ferro alloys (55 per cent), rolled products (54 per cent), and sponge iron (53 per cent). Iron ore mining, pellet production and steel billets have all crossed 43 per cent of full-year targets.

Land acquisition:

452 acres secured for the Integrated Steel Plant (ISP) and CRM complex.

112 acres acquired for the Battery Energy Storage System (BESS) project.

CRM complex: Work is progressing on the 0.7 MnT cold-rolled steel complex; land is acquired and major equipment orders are placed.

Battery storage: Godawari New Energy Pvt Ltd, a wholly owned subsidiary, is developing a BESS facility in Maharashtra; land acquisition is complete.

Solar power: The Board has approved an additional 250 MW solar project, supplementing the earlier 125 MW for captive use at the ISP and CRM complex.

PGCIL approval: GPIL has received approval to supply steel billets to all manufacturers of galvanised steel structures for transmission projects, supporting margin enhancement in value-added products.

Boria Tibu Mine: Operations resumed in May 2025 following approval of the updated five-year mining plan by the Indian Bureau of Mines.

Management Commentary Mr B.L. Agrawal, Chairman and Managing Director, said H1 FY26 reflected steady performance and strong operational progress. Revenues remained stable, supported by higher pellet and galvanised-product volumes, while margins remained healthy despite softer realisations. He highlighted major strategic progress, including the Ari Dongri mine expansion, the approval of an additional 250 MW solar project, advancement of the 0.7 MnT CRM complex, and movement on the battery energy storage project with required land already secured. Backed by a strong net-cash position, ongoing capacity expansion and a firm ESG commitment, GPIL is well positioned for sustainable, long-term value creation driven by efficiency gains, solar-led cost savings and the advantages of captive iron ore resources.

Godawari Power & Ispat Ltd, a fully integrated steel producer, has announced its financial results for Q2 and H1 FY26, reporting stable performance supported by higher pellet and galvanised product volumes and continued progress on major expansion projects. Q2 FY26 – Key Financial Highlights Revenue, EBITDA and PAT recorded slight year-on-year growth, driven by increased sales volumes of pellets and rolled structural products. Sequentially, sales, EBITDA and PAT were lower due to reduced realisations in iron ore pellets and finished steel. EBITDA and PAT margins remained strong at 20 per cent and 12 per cent, respectively. H1 FY26 – Key Financial Highlights Sales turnover remained largely stable, supported by higher production and sales of pellets and galvanised fabricated products. EBITDA and PAT were lower year-on-year due to softer sales realisations. Margins remained healthy, with EBITDA at 22 per cent and PAT at 14 per cent. Q2 & H1 FY26 – Key Operational Updates Mining expansion: Public hearing for expanding the Ari Dongri Iron Ore Mine from 2.35 MTPA to 6 MTPA has been completed. Environmental approval is expected by December 2025. Volume performance: GPIL is on track to meet its FY26 production targets, with strong progress in ferro alloys (55 per cent), rolled products (54 per cent), and sponge iron (53 per cent). Iron ore mining, pellet production and steel billets have all crossed 43 per cent of full-year targets. Land acquisition: 452 acres secured for the Integrated Steel Plant (ISP) and CRM complex. 112 acres acquired for the Battery Energy Storage System (BESS) project. CRM complex: Work is progressing on the 0.7 MnT cold-rolled steel complex; land is acquired and major equipment orders are placed. Battery storage: Godawari New Energy Pvt Ltd, a wholly owned subsidiary, is developing a BESS facility in Maharashtra; land acquisition is complete. Solar power: The Board has approved an additional 250 MW solar project, supplementing the earlier 125 MW for captive use at the ISP and CRM complex. PGCIL approval: GPIL has received approval to supply steel billets to all manufacturers of galvanised steel structures for transmission projects, supporting margin enhancement in value-added products. Boria Tibu Mine: Operations resumed in May 2025 following approval of the updated five-year mining plan by the Indian Bureau of Mines. Management Commentary Mr B.L. Agrawal, Chairman and Managing Director, said H1 FY26 reflected steady performance and strong operational progress. Revenues remained stable, supported by higher pellet and galvanised-product volumes, while margins remained healthy despite softer realisations. He highlighted major strategic progress, including the Ari Dongri mine expansion, the approval of an additional 250 MW solar project, advancement of the 0.7 MnT CRM complex, and movement on the battery energy storage project with required land already secured. Backed by a strong net-cash position, ongoing capacity expansion and a firm ESG commitment, GPIL is well positioned for sustainable, long-term value creation driven by efficiency gains, solar-led cost savings and the advantages of captive iron ore resources.

Next Story
Infrastructure Transport

MMRDA Installs 325-Tonne Steel Spans on Mumbai Metro Line 4

The Mumbai Metropolitan Region Development Authority (MMRDA) has achieved a key construction milestone on Metro Line 4 with the successful installation of three large steel spans at Bhandup West during overnight operations.The spans, together weighing 325 metric tonnes, were launched using eight heavy-duty cranes and 12 multi-axle vehicles. The operation required precise engineering and meticulous planning to minimise disruption in the densely populated suburban area.Due to effective inter-agency coordination, the work—originally scheduled across four nights—was completed within just two n..

Next Story
Infrastructure Transport

CMRL Targets March 2027 Opening for Vadapalani–Panagal Park

Chennai Metro Rail Limited (CMRL) is progressing as scheduled to open the Vadapalani–Panagal Park section of Phase II’s Corridor 4 by March 2027. The 3.5 km underground stretch is part of the 26.1 km Corridor 4 connecting Lighthouse with Poonamallee Bypass.Construction activities are advancing steadily, with tunnelling works between Vadapalani and Panagal Park already completed. Track-laying operations are expected to commence shortly. At Panagal Park station, structural works have reached the concourse and platform levels, while excavation continues at the lowest level.CMRL is also consid..

Next Story
Infrastructure Transport

Maha-Metro Invites Pune Metro Civil Maintenance Bids

Maharashtra Metro Rail Corporation Limited (Maha-Metro) has invited bids for the annual civil maintenance contract of the Pune Metro Rail Project. The tender, bearing ID and number P1-O&M-20/2025, is scheduled to close on 23 February 2026, with a pre-bid meeting slated for 10 February 2026. The earnest money deposit (EMD) for the contract is Rs 3,50,500, and the duration of the contract is one year.The scope of work includes annual civil maintenance of 28 elevated and underground stations, 28.079 km of elevated viaduct including steel bridges, 12.15 km of tunnels, and two depots under the ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App