HERC Orders Open Access Approval For 100 MW Renewable Supply
POWER & RENEWABLE ENERGY

HERC Orders Open Access Approval For 100 MW Renewable Supply

The Haryana Electricity Regulatory Commission (HERC) has ordered state utilities to grant full open access clearance for Jindal Stainless Limited to procure 100 Megawatt (MW) of round-the-clock renewable energy for its manufacturing facility in Hisar. The order dated 23 June 2026 held that refusal to issue a full No Objection Certificate was not legally justified once operational formalities were satisfied. The commission said long-term open access has priority over temporary arrangements.

The dispute began when the State Transmission Utility, Haryana Vidyut Prasaran Nigam Limited and the Grid Co-ordination Committee declined a full NOC for transfers from captive interstate wind?solar hybrid projects in Gujarat and Madhya Pradesh. Jindal Stainless had sought approval to source 100 MW to meet plant demand in Hisar. Utilities cited peak summer demand of around 16,500 MW and transmission constraints, and argued that allowing long-term transfers could limit the ability to import emergency power through Temporary General Network Access (T-GNA) and raise Deviation Settlement Mechanism (DSM) charges.

Jindal Stainless challenged the partial denial before HERC, arguing that it violated the Electricity Act, 2003 and the principle of non-discriminatory open access because the procurement would replace existing grid consumption rather than increase net demand. The company offered voluntary measures to accept complete curtailment of up to 100 MW during severe grid constraints without compensation and to bear all DSM costs and related risks. It estimated annual savings of Rs 650 mn to Rs one bn for distribution companies as a result of reduced short-term purchases.

HERC directed Haryana Vidyut Prasaran Nigam Limited to finalise the operational procedures, undertakings and mechanisms within two weeks and to issue the full NOC once arrangements were completed. The commission warned that denying long-term open access could discourage investment and hamper progress towards India’s target of 500 GW of non-fossil capacity by 2030. The order requires the utility to complete formalities so the company can commence procurement of the approved 100 MW.

The Haryana Electricity Regulatory Commission (HERC) has ordered state utilities to grant full open access clearance for Jindal Stainless Limited to procure 100 Megawatt (MW) of round-the-clock renewable energy for its manufacturing facility in Hisar. The order dated 23 June 2026 held that refusal to issue a full No Objection Certificate was not legally justified once operational formalities were satisfied. The commission said long-term open access has priority over temporary arrangements. The dispute began when the State Transmission Utility, Haryana Vidyut Prasaran Nigam Limited and the Grid Co-ordination Committee declined a full NOC for transfers from captive interstate wind?solar hybrid projects in Gujarat and Madhya Pradesh. Jindal Stainless had sought approval to source 100 MW to meet plant demand in Hisar. Utilities cited peak summer demand of around 16,500 MW and transmission constraints, and argued that allowing long-term transfers could limit the ability to import emergency power through Temporary General Network Access (T-GNA) and raise Deviation Settlement Mechanism (DSM) charges. Jindal Stainless challenged the partial denial before HERC, arguing that it violated the Electricity Act, 2003 and the principle of non-discriminatory open access because the procurement would replace existing grid consumption rather than increase net demand. The company offered voluntary measures to accept complete curtailment of up to 100 MW during severe grid constraints without compensation and to bear all DSM costs and related risks. It estimated annual savings of Rs 650 mn to Rs one bn for distribution companies as a result of reduced short-term purchases. HERC directed Haryana Vidyut Prasaran Nigam Limited to finalise the operational procedures, undertakings and mechanisms within two weeks and to issue the full NOC once arrangements were completed. The commission warned that denying long-term open access could discourage investment and hamper progress towards India’s target of 500 GW of non-fossil capacity by 2030. The order requires the utility to complete formalities so the company can commence procurement of the approved 100 MW.

Related Stories

Gold Stories

Next Story
Real Estate

Gradiant expands Coimbatore engineering centre

Gradiant has expanded its Global Engineering Center (GEC) in Coimbatore, more than doubling its engineering workforce from approximately 100 to over 200 professionals as it strengthens its global project execution capabilities.The expanded centre will bring together multidisciplinary expertise across process engineering, detailed design and project engineering, enabling the India team to take on greater responsibility for the engineering and design of Gradiant’s international projects.According to Govind Alagappan, COO, Gradiant, Coimbatore’s engineering talent and industrial heritage make..

Next Story
Infrastructure Urban

Domestic Firms Choose Locally Designed Reactors to Cut Delays

Domestic companies in the nuclear sector are choosing locally designed reactors to avoid time consuming approvals and supply chain bottlenecks that can delay project execution. The shift reflects an emphasis on reducing dependence on foreign designs and accelerating construction schedules by aligning design, manufacturing and regulatory processes within national frameworks. Industry participants expect that locally designed systems will allow closer coordination with regulators and vendors, shortening lead times for certification and component delivery. Localisation is projected to stimulate t..

Next Story
Infrastructure Urban

Kadiyam Kavya Seeks Separate Railway Division For Kazipet

Warangal Member of Parliament Kadiyam Kavya has urged the establishment of a separate railway division based at Kazipet and submitted a representation to the South Central Railway (SCR) general manager at the headquarters in Secunderabad. She highlighted Kazipet's role as a major railway hub and argued that the junction has not seen development commensurate with its strategic importance. The representative action aimed to press for administrative reorganisation to address local operational and developmental needs. She noted that creation of an independent Kazipet division has been a long stand..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement