India Grants Relief to Renewables Hit by Bustard Ruling
POWER & RENEWABLE ENERGY

India Grants Relief to Renewables Hit by Bustard Ruling

India’s clean energy ministry has granted renewable energy developers additional time to commission projects delayed by a Supreme Court case on power transmission lines in habitats of the endangered Great Indian Bustard.

In an order issued on Monday, the Ministry of New and Renewable Energy said delays in obtaining approvals for overhead transmission lines in bustard habitats in Rajasthan and Gujarat will be treated as force majeure. This will allow developers to seek extensions to scheduled commissioning dates.

The decision follows a December 2025 verdict by the Supreme Court of India that brought an end to the long-running case and endorsed the recommendations of an expert panel aimed at protecting the critically endangered bird. The panel proposed tighter restrictions on new wind and large solar projects within designated habitat zones, along with undergrounding key power distribution lines and rerouting high-voltage transmission corridors.

Earlier court directions had curtailed the use of overhead transmission lines in bustard habitats, prompting several developers to pause projects while awaiting regulatory clarity. Under the latest order, renewable energy implementation agencies have been directed to grant extensions for delays occurring between March 21, 2024 and December 19, 2025. The ministry did not specify the duration of the extensions.

Developers had faced the risk of grid disconnection and financial penalties from India’s transmission authority as project timelines slipped amid regulatory uncertainty.

India has set a target of achieving 500 gigawatts of non-fossil fuel power capacity by 2030. However, the country’s transmission network, spanning around 495,000 circuit kilometres, has lagged the rapid expansion of generation capacity. Alongside commissioning relief, the ministry has also asked the power ministry and grid operators to provide corresponding concessions on connectivity and transmission charges for projects affected by the bustard-related delays.

India’s clean energy ministry has granted renewable energy developers additional time to commission projects delayed by a Supreme Court case on power transmission lines in habitats of the endangered Great Indian Bustard. In an order issued on Monday, the Ministry of New and Renewable Energy said delays in obtaining approvals for overhead transmission lines in bustard habitats in Rajasthan and Gujarat will be treated as force majeure. This will allow developers to seek extensions to scheduled commissioning dates. The decision follows a December 2025 verdict by the Supreme Court of India that brought an end to the long-running case and endorsed the recommendations of an expert panel aimed at protecting the critically endangered bird. The panel proposed tighter restrictions on new wind and large solar projects within designated habitat zones, along with undergrounding key power distribution lines and rerouting high-voltage transmission corridors. Earlier court directions had curtailed the use of overhead transmission lines in bustard habitats, prompting several developers to pause projects while awaiting regulatory clarity. Under the latest order, renewable energy implementation agencies have been directed to grant extensions for delays occurring between March 21, 2024 and December 19, 2025. The ministry did not specify the duration of the extensions. Developers had faced the risk of grid disconnection and financial penalties from India’s transmission authority as project timelines slipped amid regulatory uncertainty. India has set a target of achieving 500 gigawatts of non-fossil fuel power capacity by 2030. However, the country’s transmission network, spanning around 495,000 circuit kilometres, has lagged the rapid expansion of generation capacity. Alongside commissioning relief, the ministry has also asked the power ministry and grid operators to provide corresponding concessions on connectivity and transmission charges for projects affected by the bustard-related delays.

Next Story
Infrastructure Urban

InsideFPV Delivers ₹10 Crore Kamikaze Drone Order Under MoD’s EPR Route

InsideFPV, a Surat-based drone technology manufacturer, has successfully executed a ₹10 crore defence contract to supply indigenous kamikaze drones under the Ministry of Defence’s Emergency Procurement Route (EPR). The company completed the delivery of hundreds of FPV kamikaze drone platforms within a rapid two-month timeframe, highlighting its ability to meet urgent military procurement timelines.The supply orders were fulfilled under the emergency procurement mechanism, which is aimed at fast-tracking acquisitions for immediate operational needs. InsideFPV’s quick execution reflects it..

Next Story
Infrastructure Urban

InsideFPV Delivers ₹10 Crore Kamikaze Drone Order Under MoD’s EPR Route

InsideFPV, a Surat-based drone technology manufacturer, has successfully executed a ₹10 crore defence contract to supply indigenous kamikaze drones under the Ministry of Defence’s Emergency Procurement Route (EPR). The company completed the delivery of hundreds of FPV kamikaze drone platforms within a rapid two-month timeframe, highlighting its ability to meet urgent military procurement timelines.The supply orders were fulfilled under the emergency procurement mechanism, which is aimed at fast-tracking acquisitions for immediate operational needs. InsideFPV’s quick execution reflects it..

Next Story
Infrastructure Energy

Vedanta Resources Secures Fitch Upgrade to ‘BB-’, Best Rating Since 2015

Vedanta Resources Limited (VRL), a global player in metals, oil & gas, critical minerals, power and technology, has received a credit rating upgrade from Fitch Ratings, marking its strongest bond rating in over a decade.Fitch has raised Vedanta Resources’ Long-Term Foreign-Currency Issuer Default Rating (IDR) to ‘BB-’ from ‘B+’, while maintaining a Stable Outlook. The agency also upgraded VRL’s senior unsecured rating, along with the ratings of US dollar-denominated bonds issued by Vedanta Resources Finance II Plc and guaranteed by VRL, to ‘BB-’.The upgrade represents Vedan..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement