India Grants Relief to Renewables Hit by Bustard Ruling
POWER & RENEWABLE ENERGY

India Grants Relief to Renewables Hit by Bustard Ruling

India’s clean energy ministry has granted renewable energy developers additional time to commission projects delayed by a Supreme Court case on power transmission lines in habitats of the endangered Great Indian Bustard.

In an order issued on Monday, the Ministry of New and Renewable Energy said delays in obtaining approvals for overhead transmission lines in bustard habitats in Rajasthan and Gujarat will be treated as force majeure. This will allow developers to seek extensions to scheduled commissioning dates.

The decision follows a December 2025 verdict by the Supreme Court of India that brought an end to the long-running case and endorsed the recommendations of an expert panel aimed at protecting the critically endangered bird. The panel proposed tighter restrictions on new wind and large solar projects within designated habitat zones, along with undergrounding key power distribution lines and rerouting high-voltage transmission corridors.

Earlier court directions had curtailed the use of overhead transmission lines in bustard habitats, prompting several developers to pause projects while awaiting regulatory clarity. Under the latest order, renewable energy implementation agencies have been directed to grant extensions for delays occurring between March 21, 2024 and December 19, 2025. The ministry did not specify the duration of the extensions.

Developers had faced the risk of grid disconnection and financial penalties from India’s transmission authority as project timelines slipped amid regulatory uncertainty.

India has set a target of achieving 500 gigawatts of non-fossil fuel power capacity by 2030. However, the country’s transmission network, spanning around 495,000 circuit kilometres, has lagged the rapid expansion of generation capacity. Alongside commissioning relief, the ministry has also asked the power ministry and grid operators to provide corresponding concessions on connectivity and transmission charges for projects affected by the bustard-related delays.

India’s clean energy ministry has granted renewable energy developers additional time to commission projects delayed by a Supreme Court case on power transmission lines in habitats of the endangered Great Indian Bustard. In an order issued on Monday, the Ministry of New and Renewable Energy said delays in obtaining approvals for overhead transmission lines in bustard habitats in Rajasthan and Gujarat will be treated as force majeure. This will allow developers to seek extensions to scheduled commissioning dates. The decision follows a December 2025 verdict by the Supreme Court of India that brought an end to the long-running case and endorsed the recommendations of an expert panel aimed at protecting the critically endangered bird. The panel proposed tighter restrictions on new wind and large solar projects within designated habitat zones, along with undergrounding key power distribution lines and rerouting high-voltage transmission corridors. Earlier court directions had curtailed the use of overhead transmission lines in bustard habitats, prompting several developers to pause projects while awaiting regulatory clarity. Under the latest order, renewable energy implementation agencies have been directed to grant extensions for delays occurring between March 21, 2024 and December 19, 2025. The ministry did not specify the duration of the extensions. Developers had faced the risk of grid disconnection and financial penalties from India’s transmission authority as project timelines slipped amid regulatory uncertainty. India has set a target of achieving 500 gigawatts of non-fossil fuel power capacity by 2030. However, the country’s transmission network, spanning around 495,000 circuit kilometres, has lagged the rapid expansion of generation capacity. Alongside commissioning relief, the ministry has also asked the power ministry and grid operators to provide corresponding concessions on connectivity and transmission charges for projects affected by the bustard-related delays.

Next Story
Real Estate

Integrated Waterproofing Strategies

Waterproofing buildings used to be an annual pre-monsoon affair but the evolution of real-estate development has changed that approach. In new developments, developers are weaving waterproofing solutions into both the design and construction phases, an approach that Nikhil Madan, Managing Director, Mahima Group, says, “is all about ensuring lasting durability [of the building] and keeping lifecycle risks including water seepage and extensive maintenance to a minimum.”Watertight by designAluminium formwork systems aren’t commonly thought of as a waterproofing tool but at the Mahima Group,..

Next Story
Infrastructure Urban

GROHE Showcases Water-Led Design At Milan

GROHE unveiled its GROHE SPA Aqua Sanctuary at Milan Design Week 2026, transforming Piccolo Teatro Studio Melato into an immersive showcase of water, design and wellbeing. Built on the philosophy of ‘Wellbeing Through Water’, the installation reimagined bathrooms as holistic spaces for relaxation, rejuvenation and self-care.The Aqua Sanctuary was presented through three interconnected sanctums. The first showcased the 3D-printed GROHE SPA AquaTree shower and faucet, highlighting bespoke innovation and biophilic design. The second featured the Atrio Private Collection and GROHE SPA x Buster..

Next Story
Infrastructure Transport

Rahee Group Expands Rail Manufacturing Capacity

Rahee Group has outlined a multi-year investment roadmap to expand its operational footprint and strengthen manufacturing capabilities for India’s growing railway and urban transit sector. The Group is expanding in Odisha with a new Track Component Casting Unit, for which the groundbreaking ceremony was held on 8 April 2026 in the presence of Odisha Chief Minister Mohan Charan Majhi.The Group’s flagship EPC arm, Rahee Infratech Ltd, continues to focus on complex rail infrastructure projects, including track systems, bridges, viaducts and ballastless infrastructure. Its wholly owned subsidi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->