+
India Grants Relief to Renewables Hit by Bustard Ruling
POWER & RENEWABLE ENERGY

India Grants Relief to Renewables Hit by Bustard Ruling

India’s clean energy ministry has granted renewable energy developers additional time to commission projects delayed by a Supreme Court case on power transmission lines in habitats of the endangered Great Indian Bustard.

In an order issued on Monday, the Ministry of New and Renewable Energy said delays in obtaining approvals for overhead transmission lines in bustard habitats in Rajasthan and Gujarat will be treated as force majeure. This will allow developers to seek extensions to scheduled commissioning dates.

The decision follows a December 2025 verdict by the Supreme Court of India that brought an end to the long-running case and endorsed the recommendations of an expert panel aimed at protecting the critically endangered bird. The panel proposed tighter restrictions on new wind and large solar projects within designated habitat zones, along with undergrounding key power distribution lines and rerouting high-voltage transmission corridors.

Earlier court directions had curtailed the use of overhead transmission lines in bustard habitats, prompting several developers to pause projects while awaiting regulatory clarity. Under the latest order, renewable energy implementation agencies have been directed to grant extensions for delays occurring between March 21, 2024 and December 19, 2025. The ministry did not specify the duration of the extensions.

Developers had faced the risk of grid disconnection and financial penalties from India’s transmission authority as project timelines slipped amid regulatory uncertainty.

India has set a target of achieving 500 gigawatts of non-fossil fuel power capacity by 2030. However, the country’s transmission network, spanning around 495,000 circuit kilometres, has lagged the rapid expansion of generation capacity. Alongside commissioning relief, the ministry has also asked the power ministry and grid operators to provide corresponding concessions on connectivity and transmission charges for projects affected by the bustard-related delays.

India’s clean energy ministry has granted renewable energy developers additional time to commission projects delayed by a Supreme Court case on power transmission lines in habitats of the endangered Great Indian Bustard. In an order issued on Monday, the Ministry of New and Renewable Energy said delays in obtaining approvals for overhead transmission lines in bustard habitats in Rajasthan and Gujarat will be treated as force majeure. This will allow developers to seek extensions to scheduled commissioning dates. The decision follows a December 2025 verdict by the Supreme Court of India that brought an end to the long-running case and endorsed the recommendations of an expert panel aimed at protecting the critically endangered bird. The panel proposed tighter restrictions on new wind and large solar projects within designated habitat zones, along with undergrounding key power distribution lines and rerouting high-voltage transmission corridors. Earlier court directions had curtailed the use of overhead transmission lines in bustard habitats, prompting several developers to pause projects while awaiting regulatory clarity. Under the latest order, renewable energy implementation agencies have been directed to grant extensions for delays occurring between March 21, 2024 and December 19, 2025. The ministry did not specify the duration of the extensions. Developers had faced the risk of grid disconnection and financial penalties from India’s transmission authority as project timelines slipped amid regulatory uncertainty. India has set a target of achieving 500 gigawatts of non-fossil fuel power capacity by 2030. However, the country’s transmission network, spanning around 495,000 circuit kilometres, has lagged the rapid expansion of generation capacity. Alongside commissioning relief, the ministry has also asked the power ministry and grid operators to provide corresponding concessions on connectivity and transmission charges for projects affected by the bustard-related delays.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

NABARD Holds Seminar on Vigilance, Integrity and Good Governance

National Bank for Agriculture and Rural Development (NABARD) organised a seminar on “Vigilance: Strengthening Integrity and Good Governance” on 25 August 2026 at its Head Office in Mumbai as part of the ongoing Vigilance Awareness Campaign 2026 being observed from 17 August to 16 November 2026, with the theme “Probity for Prosperity."" The seminar was graced by Suresh N Patel, Former Central Vigilance Commissioner, Government of India, as the chief guest and keynote speaker.  The programme was attended by G S Rawat, Deputy Managing Director, Dr Ajay K Sood, Deputy Managing Dire..

Next Story
Equipment

XCMG Unveils World's First 14,000-Ton Ring Crane for Heavy Lifting

XCMG has announced that the first main unit of the world's first 14,000-ton ring crane has rolled off the production line, marking a historic breakthrough in ultra-heavy lifting technology. Jointly developed by XCMG and Sinopec Heavy Lifting & Transportation Co., Ltd., the crane will be the largest-capacity ring crane ever built, setting a new benchmark for major construction projects worldwide.The crane features a modular configuration comprising two main units that work in tandem. The first main unit has completed final assembly and can independently perform lifting operations. Once both..

Next Story
Infrastructure Urban

Thriveni Logistics orders 200 tip trailers from Jagdamba trailers

Jagdamba Trailers (JTPL), one of India’s growing trailer manufacturers, has secured a significant order for 200 Tip Trailers from Thriveni Transport and Logistics Pvt. Ltd., a leading mining and logistics company serving operations across India and overseas.The order, placed for iron ore transportation, is a major milestone for JTPL, particularly as the company secured the business after competing with more than 10 established trailer manufacturers. It also strengthens an already successful relationship between the two companies. Approximately one and a half years ago, Thriveni Transport and..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code