India Needs 86 GW Additional Thermal Power by FY36, 64 GW Under Works
POWER & RENEWABLE ENERGY

India Needs 86 GW Additional Thermal Power by FY36, 64 GW Under Works

India needs to add 86,440 MW of thermal power generation capacity by 2035–36, and 63,545 MW of that capacity is reported to be at various stages of implementation, the Minister of State for Power Shripad Naik informed Parliament. The figures were provided in a written reply in the Rajya Sabha and draw on the National Generation Adequacy Plan covering 2026–27 to 2035–36. The plan was prepared by the Central Electricity Authority (CEA) in March 2026.

The CEA estimated that required coal and lignite based thermal capacity to meet projected electricity demand by 2035–36 is about 315,000 MW. Against this requirement, installed coal and lignite based capacity as on March 31, 2026, stood at 228,560 MW, leaving a shortfall of 86,440 MW. The shortfall reflects the gap between existing assets and projected demand over the planning horizon.

Of the additional capacity needed, projects totalling 63,545 MW are at various stages of implementation, signalling substantial ongoing investment in thermal generation. The remaining requirement will need to be met through new projects, timely completion of existing schemes and any adjustments captured in future revisions of the national adequacy plan. The data underlines the continuing role of coal and lignite in the power mix while planning for supply adequacy.

The plan sets a clear timeline to 2035–36 and provides a basis for infrastructure investment and regulatory oversight. Officials and stakeholders will need to align project schedules, fuel availability and environmental clearances to bridge the identified gap. The written reply indicates that Parliament has been furnished with the current status and that implementation progress will be monitored as projects advance. The ministry will continue to update Parliament as project milestones are achieved.

India needs to add 86,440 MW of thermal power generation capacity by 2035–36, and 63,545 MW of that capacity is reported to be at various stages of implementation, the Minister of State for Power Shripad Naik informed Parliament. The figures were provided in a written reply in the Rajya Sabha and draw on the National Generation Adequacy Plan covering 2026–27 to 2035–36. The plan was prepared by the Central Electricity Authority (CEA) in March 2026. The CEA estimated that required coal and lignite based thermal capacity to meet projected electricity demand by 2035–36 is about 315,000 MW. Against this requirement, installed coal and lignite based capacity as on March 31, 2026, stood at 228,560 MW, leaving a shortfall of 86,440 MW. The shortfall reflects the gap between existing assets and projected demand over the planning horizon. Of the additional capacity needed, projects totalling 63,545 MW are at various stages of implementation, signalling substantial ongoing investment in thermal generation. The remaining requirement will need to be met through new projects, timely completion of existing schemes and any adjustments captured in future revisions of the national adequacy plan. The data underlines the continuing role of coal and lignite in the power mix while planning for supply adequacy. The plan sets a clear timeline to 2035–36 and provides a basis for infrastructure investment and regulatory oversight. Officials and stakeholders will need to align project schedules, fuel availability and environmental clearances to bridge the identified gap. The written reply indicates that Parliament has been furnished with the current status and that implementation progress will be monitored as projects advance. The ministry will continue to update Parliament as project milestones are achieved.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Emiza Expands Bhiwandi Fulfilment Capacity by 2.32 Lakh Sq Ft

Emiza, a leading third-party logistics (3PL) provider, has expanded its Mumbai operations with the launch of two new fulfilment facilities in Bhiwandi, adding a combined capacity of 2.32 lakh sq ft to its network.The new facilities, spread across 75,000 sq ft and 1,57,000 sq ft, mark Emiza’s fifth and sixth warehouses in the Mumbai region. The expansion strengthens the company’s fulfilment infrastructure in Western India amid the rapid growth of India’s digital commerce ecosystem.With increasing online consumption, wider product categories and rising customer expectations for faster deli..

Next Story
Infrastructure Urban

Ingersoll Rand Showcases Air Solutions for Semiconductor Sector

Ingersoll Rand will showcase its advanced compressed air solutions for India’s growing semiconductor ecosystem at SEMICON India 2026, scheduled from September 17–19 at Yashobhoomi, New Delhi.The company will display its portfolio of oil-free compressors, centrifugal compression technologies and advanced air treatment systems at Stall No. 1156, Hall No. 1. The solutions are designed to address the stringent air quality, reliability and efficiency requirements of semiconductor manufacturing applications.With India accelerating investments across semiconductor manufacturing, packaging, equipm..

Next Story
Infrastructure Energy

RECPDCL Transfers Musalgaon Transmission SPV to MSETCL

REC Power Development and Consultancy Limited (RECPDCL), a wholly owned subsidiary of REC Limited, has handed over Musalgaon Power Transmission Limited, a project-specific Special Purpose Vehicle (SPV), to Maharashtra State Electricity Transmission Company Limited (MSETCL).MSETCL emerged as the successful bidder through the Tariff-Based Competitive Bidding (TBCB) process conducted by RECPDCL, the Bid Process Coordinator, for developing Maharashtra’s intra-state transmission project on a Build, Own, Operate and Transfer (BOOT) basis.The SPV was handed over by Shri Ratnesh Kumar, General Manag..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code