Land Acquisition Completed For 228 Solar Plants In Andhra Pradesh
POWER & RENEWABLE ENERGY

Land Acquisition Completed For 228 Solar Plants In Andhra Pradesh

Andhra Pradesh is implementing 1,162.8 megawatt (MW) of feeder-level solarisation through 228 solar power plants under Component-C of the PM-KUSUM scheme, the Special Chief Secretary for energy, K Vijayanand, said. The administration intends to commission 109.7 MW in September and October 2026 to boost renewable power generation and to ensure reliable electricity to agricultural feeders. The programme targets distributed generation at feeder level and aims to reduce dependence on conventional supply for irrigation.

The Special Chief Secretary reviewed project progress through a video conference with chief managing directors of the distribution companies and other officials and instructed DISCOMs and developers to expedite execution and to meet project timelines. He noted that land acquisition has been completed for all 228 plants and directed officials to monitor civil works, equipment procurement, financial closure and statutory documentation on a project-wise basis. He called for close coordination among DISCOMs, developers, the state nodal agency NREDCAP, financial institutions and implementing agencies to avoid delays.

Andhra Pradesh Central Power Distribution Company Limited (APCPDCL) is implementing 49 plants with 191.5 MW and has completed land acquisition for every project. Andhra Pradesh Eastern Power Distribution Company Limited (APEPDCL) is implementing 33 plants totalling 220.3 MW, with land acquired for all and purchase orders issued for 29 projects. Andhra Pradesh Southern Power Distribution Company Limited (APSPDCL) and Kuppam Renewable Energy Cooperative Society (KRECS) together account for 146 plants totalling 751 MW, with land acquisition and purchase orders completed.

Civil works are advancing across sites and developers are progressing with equipment mobilisation and contractual clearances. About 19.9 MW is expected to be ready for charging in September while, overall, 109.7 MW is planned for commissioning, with 27 MW scheduled for September and 82.7 MW for October. Officials were instructed to prioritise timely financial closure and statutory compliance to achieve the commissioning schedule and to secure reliable supply to the agricultural sector.

Andhra Pradesh is implementing 1,162.8 megawatt (MW) of feeder-level solarisation through 228 solar power plants under Component-C of the PM-KUSUM scheme, the Special Chief Secretary for energy, K Vijayanand, said. The administration intends to commission 109.7 MW in September and October 2026 to boost renewable power generation and to ensure reliable electricity to agricultural feeders. The programme targets distributed generation at feeder level and aims to reduce dependence on conventional supply for irrigation. The Special Chief Secretary reviewed project progress through a video conference with chief managing directors of the distribution companies and other officials and instructed DISCOMs and developers to expedite execution and to meet project timelines. He noted that land acquisition has been completed for all 228 plants and directed officials to monitor civil works, equipment procurement, financial closure and statutory documentation on a project-wise basis. He called for close coordination among DISCOMs, developers, the state nodal agency NREDCAP, financial institutions and implementing agencies to avoid delays. Andhra Pradesh Central Power Distribution Company Limited (APCPDCL) is implementing 49 plants with 191.5 MW and has completed land acquisition for every project. Andhra Pradesh Eastern Power Distribution Company Limited (APEPDCL) is implementing 33 plants totalling 220.3 MW, with land acquired for all and purchase orders issued for 29 projects. Andhra Pradesh Southern Power Distribution Company Limited (APSPDCL) and Kuppam Renewable Energy Cooperative Society (KRECS) together account for 146 plants totalling 751 MW, with land acquisition and purchase orders completed. Civil works are advancing across sites and developers are progressing with equipment mobilisation and contractual clearances. About 19.9 MW is expected to be ready for charging in September while, overall, 109.7 MW is planned for commissioning, with 27 MW scheduled for September and 82.7 MW for October. Officials were instructed to prioritise timely financial closure and statutory compliance to achieve the commissioning schedule and to secure reliable supply to the agricultural sector.

Related Stories

Gold Stories

Next Story
Infrastructure Energy

Alternative Fuels Overtake Petrol As August Retail Peaks

The Indian automobile industry recorded its best-ever August retail as alternative fuels such as compressed natural gas, hybrid and electric vehicles combined overtook petrol in the passenger vehicle segment for the first time. The shift coincided with oil price rises linked to the war in the Middle East and a cooled public response to higher ethanol content in petrol. Dealers attributed stronger demand to lower running costs and concerns over the E20 petrol transition. Data released by the Federation of Automobile Dealers Associations (FADA) showed total vehicle retail registrations in August..

Next Story
Infrastructure Urban

Singapore Minister Defends SIA Investment In Air India

Singapore government defended Singapore Airlines' investment in Air India after two weeks of public scrutiny over a funding request, saying the flag carrier must expand overseas and that outcomes are for the company and its shareholders to judge. The remarks in parliament followed reports that Air India had sought about US$1.5 billion (US$1.5 bn) of fresh equity from owners Tata Sons and Singapore Airlines. The issue drew attention because Singapore Airlines is majority-owned by Temasek and raised questions about Temasek's role. Officials framed the matter as a commercial decision rather than ..

Next Story
Infrastructure Transport

IndiGo To Begin Guwahati Bangkok Flights

IndiGo will launch non-stop flights between Guwahati and Bangkok from 27 October 2026, marking the carrier's first international operations from the city. A special inaugural service will operate on 27 October, with regular twice a week flights scheduled from 31 October on Wednesdays and Saturdays, subject to regulatory approvals. The new link will provide direct connectivity between Northeast India and Thailand and expand the airline's India–Thailand network. The inaugural Bangkok to Guwahati sector, flight 6E1086, is scheduled to depart Bangkok at 8:50 am and arrive in Guwahati at 10:25 am..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code