Land Acquisition Completed For 228 Solar Plants In Andhra Pradesh
POWER & RENEWABLE ENERGY

Land Acquisition Completed For 228 Solar Plants In Andhra Pradesh

Andhra Pradesh is implementing 1,162.8 megawatt (MW) of feeder-level solarisation through 228 solar power plants under Component-C of the PM-KUSUM scheme, the Special Chief Secretary for energy, K Vijayanand, said. The administration intends to commission 109.7 MW in September and October 2026 to boost renewable power generation and to ensure reliable electricity to agricultural feeders. The programme targets distributed generation at feeder level and aims to reduce dependence on conventional supply for irrigation.

The Special Chief Secretary reviewed project progress through a video conference with chief managing directors of the distribution companies and other officials and instructed DISCOMs and developers to expedite execution and to meet project timelines. He noted that land acquisition has been completed for all 228 plants and directed officials to monitor civil works, equipment procurement, financial closure and statutory documentation on a project-wise basis. He called for close coordination among DISCOMs, developers, the state nodal agency NREDCAP, financial institutions and implementing agencies to avoid delays.

Andhra Pradesh Central Power Distribution Company Limited (APCPDCL) is implementing 49 plants with 191.5 MW and has completed land acquisition for every project. Andhra Pradesh Eastern Power Distribution Company Limited (APEPDCL) is implementing 33 plants totalling 220.3 MW, with land acquired for all and purchase orders issued for 29 projects. Andhra Pradesh Southern Power Distribution Company Limited (APSPDCL) and Kuppam Renewable Energy Cooperative Society (KRECS) together account for 146 plants totalling 751 MW, with land acquisition and purchase orders completed.

Civil works are advancing across sites and developers are progressing with equipment mobilisation and contractual clearances. About 19.9 MW is expected to be ready for charging in September while, overall, 109.7 MW is planned for commissioning, with 27 MW scheduled for September and 82.7 MW for October. Officials were instructed to prioritise timely financial closure and statutory compliance to achieve the commissioning schedule and to secure reliable supply to the agricultural sector.

Andhra Pradesh is implementing 1,162.8 megawatt (MW) of feeder-level solarisation through 228 solar power plants under Component-C of the PM-KUSUM scheme, the Special Chief Secretary for energy, K Vijayanand, said. The administration intends to commission 109.7 MW in September and October 2026 to boost renewable power generation and to ensure reliable electricity to agricultural feeders. The programme targets distributed generation at feeder level and aims to reduce dependence on conventional supply for irrigation. The Special Chief Secretary reviewed project progress through a video conference with chief managing directors of the distribution companies and other officials and instructed DISCOMs and developers to expedite execution and to meet project timelines. He noted that land acquisition has been completed for all 228 plants and directed officials to monitor civil works, equipment procurement, financial closure and statutory documentation on a project-wise basis. He called for close coordination among DISCOMs, developers, the state nodal agency NREDCAP, financial institutions and implementing agencies to avoid delays. Andhra Pradesh Central Power Distribution Company Limited (APCPDCL) is implementing 49 plants with 191.5 MW and has completed land acquisition for every project. Andhra Pradesh Eastern Power Distribution Company Limited (APEPDCL) is implementing 33 plants totalling 220.3 MW, with land acquired for all and purchase orders issued for 29 projects. Andhra Pradesh Southern Power Distribution Company Limited (APSPDCL) and Kuppam Renewable Energy Cooperative Society (KRECS) together account for 146 plants totalling 751 MW, with land acquisition and purchase orders completed. Civil works are advancing across sites and developers are progressing with equipment mobilisation and contractual clearances. About 19.9 MW is expected to be ready for charging in September while, overall, 109.7 MW is planned for commissioning, with 27 MW scheduled for September and 82.7 MW for October. Officials were instructed to prioritise timely financial closure and statutory compliance to achieve the commissioning schedule and to secure reliable supply to the agricultural sector.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Suzuki Targets 4 mn Units in India by FY30, Builds Global Hub

Suzuki Motor Corporation plans to raise annual production capacity in India to approximately 4 mn units from fiscal 2030, strengthening the country’s role as a manufacturing and export hub for its global operations. The Japanese car maker announced the target as part of its Technology Strategy 2026, which outlines its development and manufacturing priorities for the coming decade. The company also aims to improve development efficiency by 30 per cent from the FY20 level and manufacturing efficiency by 50 per cent by FY30. It plans to halve the lead time required to develop new vehicles by im..

Next Story
Infrastructure Transport

Ayodhya Airport to Add Flights to Delhi, Bengaluru and Mumbai

Ayodhya airport will get additional direct air services to Delhi and Bengaluru from October 1, followed by a daily non-stop connection to Mumbai from October 30. The existing IndiGo service to Hyderabad is also being prepared for conversion into a daily operation, widening travel options from the temple city. Passengers travelling to Delhi will have two direct options at different times of day from October 1. Akasa Air flight QP 1608 will depart Ayodhya at 12:50 pm and arrive in Delhi at 2:20 pm, while Air India Express flight IX 1274 will leave at 2:10 pm and reach the capital at 3:45 pm. Ind..

Next Story
Infrastructure Urban

Cement Prices Rise Again in Himachal Pradesh

Cement prices in Himachal Pradesh have increased for the second time this month, raising construction expenses for households, contractors and other consumers. Cement companies raised rates by Rs. 5 per bag on Friday, 10 days after a similar increase was implemented on September 15. The two revisions have lifted prices by a total of Rs. 10 per bag within 10 days. Dealers Pawan, Rohit, Manoj and Rakesh said the latest rates were being applied across the market, adding to the financial pressure on people building or renovating homes. ACC Suraksha cement is now priced at Rs. 425 per bag, compared..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code