Rs 10k crore in pipeline for coal-fired thermal power project in UP
POWER & RENEWABLE ENERGY

Rs 10k crore in pipeline for coal-fired thermal power project in UP

The Uttar Pradesh Government will invest nearly Rs 10,500 crore in a Greenfield 1,320 megawatt (MW) thermal power project in Etah district of Western UP. The Jawaharpur thermal power project, comprising two units of 660 MW each and thus totalling 1,320 MW, will help the UP government in meeting the rising power demand, which has already touched 26,000 MW during summer. The plant has already been delayed by more than two years now and the state is making all out efforts to expedite its synchronisation.

M Devraj, chairman of both the apex state power utilities - UP Power Corporation (UPPCL) and UP Rajya Vidyut Utpadan Nigam Limited (UPRVUNL), has issued ordered officials to speed up the project. Jawaharpur Vidyut Utpadan Nigam Limited, which is setting up the 1,320 Mw plant, is a full subsidiary of UPRVUNL. The plant, which was initially estimated to be synchronised in 2021, witnessed inordinate delays compounded by the impact of the lockdown.

Later, the plant was expected to be synchronised by April this year, but fresh timeline was also missed. The state energy department mandarins have expressed displeasure at the serial delays, prompting the UPPCL chief to take the concerned officials and agencies to task. “The UPRVUNL chairman has been arduously making spot visits of the various thermal power projects, nudging for the ongoing civil and other works,” a government spokesperson said.

The Jawaharpur plant is being equipped with supercritical technology. It will be fed with coal from the Saharpur Jamarpani coal block in Jharkhand to be developed by UPRVUNL. A ‘Bridge Linkage’ for the project has been granted by the coal ministry.

The Uttar Pradesh Government will invest nearly Rs 10,500 crore in a Greenfield 1,320 megawatt (MW) thermal power project in Etah district of Western UP. The Jawaharpur thermal power project, comprising two units of 660 MW each and thus totalling 1,320 MW, will help the UP government in meeting the rising power demand, which has already touched 26,000 MW during summer. The plant has already been delayed by more than two years now and the state is making all out efforts to expedite its synchronisation.M Devraj, chairman of both the apex state power utilities - UP Power Corporation (UPPCL) and UP Rajya Vidyut Utpadan Nigam Limited (UPRVUNL), has issued ordered officials to speed up the project. Jawaharpur Vidyut Utpadan Nigam Limited, which is setting up the 1,320 Mw plant, is a full subsidiary of UPRVUNL. The plant, which was initially estimated to be synchronised in 2021, witnessed inordinate delays compounded by the impact of the lockdown.Later, the plant was expected to be synchronised by April this year, but fresh timeline was also missed. The state energy department mandarins have expressed displeasure at the serial delays, prompting the UPPCL chief to take the concerned officials and agencies to task. “The UPRVUNL chairman has been arduously making spot visits of the various thermal power projects, nudging for the ongoing civil and other works,” a government spokesperson said.The Jawaharpur plant is being equipped with supercritical technology. It will be fed with coal from the Saharpur Jamarpani coal block in Jharkhand to be developed by UPRVUNL. A ‘Bridge Linkage’ for the project has been granted by the coal ministry.

Next Story
Infrastructure Urban

Panasonic Showcases Connected Display Solutions

Panasonic Life Solutions India showcased its integrated display, projection, broadcast and communication technologies at Panasonic Tech Summit 2026 in New Delhi. Hosted through its System Solutions Division, the two-day event highlighted connected technology solutions for education, healthcare, retail, transportation, corporate offices and entertainment.The summit, themed ‘Turning Technology into Value’, featured experience-led zones covering QSR, retail, transit, corporate offices, healthcare, education, security, projection, home theatre and professional displays. Panasonic also introduc..

Next Story
Infrastructure Transport

Kapsch to Deliver India’s First C-ITS Project

"Kapsch TrafficCom will deliver India’s first Cooperative Intelligent Transport Systems project on a key expressway near New Delhi. The project will be implemented with Superwave Communication And Infrasolution Limited to demonstrate how connected mobility can improve road safety and traffic efficiency.The pilot will use real-time connectivity and AI-enabled situational awareness to support road users, especially in high-risk areas such as temporary work zones. Drivers will receive alerts on roadworks, maintenance vehicles, hazardous locations, traffic queues and temporary virtual signage di..

Next Story
Infrastructure Urban

Eurobond Net Profit Rises 44 Per Cent

Euro Panel Products, the parent company of Eurobond, reported a 44.13 per cent year-on-year rise in net profit for FY25–26. The company’s revenue from operations grew 18.91 per cent to Rs 503.20 crore, compared to Rs 423.18 crore in the previous financial year.The company’s full-year EBITDA stood at Rs 56.67 crore, marking a 31.82 per cent increase. Profit after tax rose to Rs 26.56 crore, while net worth increased 20.15 per cent to Rs 160.07 crore. Earnings per share for the year stood at Rs 10.84.Divyam Rajesh Shah, Whole Time Director and CFO, Euro Panel Products, said the company’s..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->