Rs 10k crore in pipeline for coal-fired thermal power project in UP
POWER & RENEWABLE ENERGY

Rs 10k crore in pipeline for coal-fired thermal power project in UP

The Uttar Pradesh Government will invest nearly Rs 10,500 crore in a Greenfield 1,320 megawatt (MW) thermal power project in Etah district of Western UP. The Jawaharpur thermal power project, comprising two units of 660 MW each and thus totalling 1,320 MW, will help the UP government in meeting the rising power demand, which has already touched 26,000 MW during summer. The plant has already been delayed by more than two years now and the state is making all out efforts to expedite its synchronisation.

M Devraj, chairman of both the apex state power utilities - UP Power Corporation (UPPCL) and UP Rajya Vidyut Utpadan Nigam Limited (UPRVUNL), has issued ordered officials to speed up the project. Jawaharpur Vidyut Utpadan Nigam Limited, which is setting up the 1,320 Mw plant, is a full subsidiary of UPRVUNL. The plant, which was initially estimated to be synchronised in 2021, witnessed inordinate delays compounded by the impact of the lockdown.

Later, the plant was expected to be synchronised by April this year, but fresh timeline was also missed. The state energy department mandarins have expressed displeasure at the serial delays, prompting the UPPCL chief to take the concerned officials and agencies to task. “The UPRVUNL chairman has been arduously making spot visits of the various thermal power projects, nudging for the ongoing civil and other works,” a government spokesperson said.

The Jawaharpur plant is being equipped with supercritical technology. It will be fed with coal from the Saharpur Jamarpani coal block in Jharkhand to be developed by UPRVUNL. A ‘Bridge Linkage’ for the project has been granted by the coal ministry.

The Uttar Pradesh Government will invest nearly Rs 10,500 crore in a Greenfield 1,320 megawatt (MW) thermal power project in Etah district of Western UP. The Jawaharpur thermal power project, comprising two units of 660 MW each and thus totalling 1,320 MW, will help the UP government in meeting the rising power demand, which has already touched 26,000 MW during summer. The plant has already been delayed by more than two years now and the state is making all out efforts to expedite its synchronisation.M Devraj, chairman of both the apex state power utilities - UP Power Corporation (UPPCL) and UP Rajya Vidyut Utpadan Nigam Limited (UPRVUNL), has issued ordered officials to speed up the project. Jawaharpur Vidyut Utpadan Nigam Limited, which is setting up the 1,320 Mw plant, is a full subsidiary of UPRVUNL. The plant, which was initially estimated to be synchronised in 2021, witnessed inordinate delays compounded by the impact of the lockdown.Later, the plant was expected to be synchronised by April this year, but fresh timeline was also missed. The state energy department mandarins have expressed displeasure at the serial delays, prompting the UPPCL chief to take the concerned officials and agencies to task. “The UPRVUNL chairman has been arduously making spot visits of the various thermal power projects, nudging for the ongoing civil and other works,” a government spokesperson said.The Jawaharpur plant is being equipped with supercritical technology. It will be fed with coal from the Saharpur Jamarpani coal block in Jharkhand to be developed by UPRVUNL. A ‘Bridge Linkage’ for the project has been granted by the coal ministry.

Next Story
Technology

Building Faster, Smarter, and Greener!

Backed by ULCCS’s century-old legacy, U-Sphere combines technology, modular design and sustainable practices to deliver faster and more efficient projects. In an interaction with CW, Rohit Prabhakar, Director - Business Development, shares how the company’s integrated model of ‘Speed-Build’, ‘Smart-Build’ and ‘Sustain-Build’ is redefining construction efficiency, quality and environmental responsibility in India.U-Sphere positions itself at the intersection of speed, sustainability and smart design. How does this translate into measurable efficiency on the ground?At U..

Next Story
Infrastructure Transport

Smart Roads, Smarter India

India’s infrastructure boom is not only about laying more kilometres of highways – it’s about building them smarter, safer and more sustainably. From drones mapping fragile Himalayan slopes to 3D machine-controlled graders reducing human error, technology is steadily reshaping the way projects are planned and executed. Yet, the journey towards digitisation remains complex, demanding not just capital but also coordination, training and vision.Until recently, engineers largely depended on Survey of India toposheets and traditional survey methods like total stations or DGPS to prepare detai..

Next Story
Real Estate

What Does DCPR 2034 Mean?

The Maharashtra government has eased approval norms for high-rise buildings under DCPR 2034, enabling the municipal commissioner to sanction projects up to 180 m on large plots. This change is expected to streamline approvals, reduce procedural delays and accelerate redevelopment, drawing reactions from developers, planners and industry experts about its implications for Mumbai’s vertical growth.Under the revised DCPR 2034 rules, buildings on plots of 2,000 sq m or more can now be approved up to 180 m by the municipal commissioner, provided structural and geotechnical reports are certified b..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?