SECI invites bids for 1.2 GW ISTS-connected wind-solar hybrid plants
POWER & RENEWABLE ENERGY

SECI invites bids for 1.2 GW ISTS-connected wind-solar hybrid plants

The Solar Energy Corporation of India (SECI) has floated a tender for installing 1,200 MW of interstate transmission system (ISTS)-connected wind-solar hybrid power plants (Tranche-V) across India.

The deadline to submit the proposals is 6th December 2021, and tenders will be opened on December 8.

The bidder should present a single tender proposing a minimum quantum of contracted energy of 50 MW and a maximum capacity of 1,200 MW.

For every project, the minimum project capacity must be 50 MW. The total capacity projects to be allotted to a bidder would be limited to 1,200 MW.

Interested bidders will have to provide an amount of Rs 1.146 million as a performance bank guarantee at least a week before inking the power purchase agreement (PPA).

The scheduled commissioning date for commissioning the project’s total capacity must be 18 months from the effective date of the PPA.

The hybrid plants must be created for interconnection with the transmission network of the central transmission utility at a voltage level of 220 kV or above.

Under this bid, a hybrid power project will mean a project involving two elements – one solar and one wind power project. The rated established project capacity of either of the two elements shall be at least 33% of the contracted capacity.

The declared yearly capacity utilisation factor (CUF) should, in no case, be lower than 30%. The developer should manage energy supply to obtain annual supply corresponding to CUF not lower than 90% of the declared value and not over 120% of the stated CUF value during the PPA duration of 25 years.

Under the request for selection (RfS) terms, SECI has offered to advance only commercially established and operational technologies to minimise the technology risk and attain timely commissioning of the projects.

To guarantee only quality systems are set up, only wind turbine models registered in the Revised List of Models and Manufacturers released by the Ministry of New and Renewable Energy as updated as on the date of commissioning of the projects will be approved for deployment.

The bidders are suggested to take cognisance of the imposition of Basic Customs Duty (BCD) on solar cells and modules while making their response to this RfS.

The bidder’s net worth must be at least Rs 11.46 million per MW of the quoted capacity as of the last day of the prior fiscal year.

The bidder’s minimum yearly turnover should be at least Rs 6.154 million per MW of the quoted capacity during the last fiscal year. In the form of profit before depreciation, interest, and taxes, the bidder’s internal resource production capacity should be at least Rs 1.231 million per MW of the quoted capacity, as on the last date of the preceding financial year.

The bidder should have a permission letter from the lending institution committing a line of credit for a minimum value of Rs 1.538 million per MW of the quoted capacity.

Image Source


Also read: India can achieve 450 GW renewable energy target by 2030: John Kerry

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

The Solar Energy Corporation of India (SECI) has floated a tender for installing 1,200 MW of interstate transmission system (ISTS)-connected wind-solar hybrid power plants (Tranche-V) across India. The deadline to submit the proposals is 6th December 2021, and tenders will be opened on December 8. The bidder should present a single tender proposing a minimum quantum of contracted energy of 50 MW and a maximum capacity of 1,200 MW. For every project, the minimum project capacity must be 50 MW. The total capacity projects to be allotted to a bidder would be limited to 1,200 MW. Interested bidders will have to provide an amount of Rs 1.146 million as a performance bank guarantee at least a week before inking the power purchase agreement (PPA). The scheduled commissioning date for commissioning the project’s total capacity must be 18 months from the effective date of the PPA. The hybrid plants must be created for interconnection with the transmission network of the central transmission utility at a voltage level of 220 kV or above. Under this bid, a hybrid power project will mean a project involving two elements – one solar and one wind power project. The rated established project capacity of either of the two elements shall be at least 33% of the contracted capacity. The declared yearly capacity utilisation factor (CUF) should, in no case, be lower than 30%. The developer should manage energy supply to obtain annual supply corresponding to CUF not lower than 90% of the declared value and not over 120% of the stated CUF value during the PPA duration of 25 years. Under the request for selection (RfS) terms, SECI has offered to advance only commercially established and operational technologies to minimise the technology risk and attain timely commissioning of the projects. To guarantee only quality systems are set up, only wind turbine models registered in the Revised List of Models and Manufacturers released by the Ministry of New and Renewable Energy as updated as on the date of commissioning of the projects will be approved for deployment. The bidders are suggested to take cognisance of the imposition of Basic Customs Duty (BCD) on solar cells and modules while making their response to this RfS. The bidder’s net worth must be at least Rs 11.46 million per MW of the quoted capacity as of the last day of the prior fiscal year. The bidder’s minimum yearly turnover should be at least Rs 6.154 million per MW of the quoted capacity during the last fiscal year. In the form of profit before depreciation, interest, and taxes, the bidder’s internal resource production capacity should be at least Rs 1.231 million per MW of the quoted capacity, as on the last date of the preceding financial year. The bidder should have a permission letter from the lending institution committing a line of credit for a minimum value of Rs 1.538 million per MW of the quoted capacity. Image SourceAlso read: India can achieve 450 GW renewable energy target by 2030: John Kerry

Next Story
Infrastructure Transport

Uttar Pradesh unveils infrastructure-led growth roadmap at RAHSTA

Mumbai, 9 July 2026: Uttar Pradesh’s ambitious infrastructure-led growth strategy took centre stage on Day 2 of the 16th RAHSTA Expo, where senior government officials outlined how expressways, industrial corridors and technology-driven governance are transforming the state into one of India's most attractive investment destinations.Delivering the keynote address, Srihari Pratap Shahi, IAS, Additional Chief Executive Officer, Uttar Pradesh Expressways Industrial Development Authority (UPEIDA), highlighted the state's long-term vision of integrating world-class expressways with industrial dev..

Next Story
Real Estate

NCW closes PRIME Offices Fund at Rs 40 billion

Nuvama and Cushman & Wakefield Management (NCW) has announced the final close of its flagship PRIME Offices Fund at approximately Rs 40 billion, exceeding its original target of Rs 30 billion following strong investor demand.The fund was launched to provide Indian investors with access to institutional-grade commercial office assets across key office markets in the country. According to NCW, the increase in the fund size was supported by strong investor participation and the availability of investment opportunities in India's office sector.The fund has already committed around 45 per cent ..

Next Story
Real Estate

Mayfair Housing adopts Autodesk Forma for digital project planning

Mayfair Housing has entered into a three-year strategic partnership with Autodesk to deploy Autodesk Forma, an AI-enabled cloud platform, as part of its digital transformation programme aimed at improving project planning and execution across its development and redevelopment portfolio.The platform will be integrated into the company's Building Information Modelling (BIM) workflow to support architects, planners and project teams during the early stages of design and development. Autodesk Forma combines real-world data, environmental simulations and collaborative workflows to facilitate data-d..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement