The energy special chief secretary, K Vijayanand, stated that Andhra Pradesh had taken up 1,162.8 MW of feeder-level solarisation capacity through 228 solar power plants across the state under Component-C of the PM-KUSUM scheme. He reviewed progress of the projects via a video conference with the chief managing directors and directors of the distribution companies and with the managing director of NREDCAP. He directed officials to expedite implementation and adhere to stipulated timelines.

The state is targeting commissioning of 109.7 MW during September and October to strengthen renewable power generation and ensure reliable daytime power supply to agricultural feeders. The projects are being implemented by Andhra Pradesh Central Power Distribution Company Limited (APCPDCL), Andhra Pradesh Eastern Power Distribution Company Limited (APEPDCL) and Andhra Pradesh Southern Power Distribution Company Limited (APSPDCL), including the Krishna Regional Electricity Cooperative Society (KRECS). He asked officials and developers to focus on commissioning schedules and operational readiness.

Land acquisition has been completed for all 228 plants, and officials were instructed to monitor civil works, equipment procurement, financial closure and statutory documentation on a project-wise basis. The authority stressed the need to resolve implementation bottlenecks at the initial stage to avoid delays. APCPDCL is implementing 49 plants with 191.5 MW, APEPDCL is executing 33 plants with 220.3 MW, and APSPDCL and KRECS account for the largest share with 146 plants totalling 751 MW.

A three MW feeder-level solar plant at the 33 kV NN Tandra sub-station in the Palnadu circle was commissioned on 27 August, and a further 109.7 MW is planned for commissioning during September and October. Timely completion, the review noted, would help Andhra Pradesh secure maximum central financial assistance under PM-KUSUM and bolster the state transition to clean energy while providing quality daytime power to the agricultural sector.

The energy special chief secretary, K Vijayanand, stated that Andhra Pradesh had taken up 1,162.8 MW of feeder-level solarisation capacity through 228 solar power plants across the state under Component-C of the PM-KUSUM scheme. He reviewed progress of the projects via a video conference with the chief managing directors and directors of the distribution companies and with the managing director of NREDCAP. He directed officials to expedite implementation and adhere to stipulated timelines. The state is targeting commissioning of 109.7 MW during September and October to strengthen renewable power generation and ensure reliable daytime power supply to agricultural feeders. The projects are being implemented by Andhra Pradesh Central Power Distribution Company Limited (APCPDCL), Andhra Pradesh Eastern Power Distribution Company Limited (APEPDCL) and Andhra Pradesh Southern Power Distribution Company Limited (APSPDCL), including the Krishna Regional Electricity Cooperative Society (KRECS). He asked officials and developers to focus on commissioning schedules and operational readiness. Land acquisition has been completed for all 228 plants, and officials were instructed to monitor civil works, equipment procurement, financial closure and statutory documentation on a project-wise basis. The authority stressed the need to resolve implementation bottlenecks at the initial stage to avoid delays. APCPDCL is implementing 49 plants with 191.5 MW, APEPDCL is executing 33 plants with 220.3 MW, and APSPDCL and KRECS account for the largest share with 146 plants totalling 751 MW. A three MW feeder-level solar plant at the 33 kV NN Tandra sub-station in the Palnadu circle was commissioned on 27 August, and a further 109.7 MW is planned for commissioning during September and October. Timely completion, the review noted, would help Andhra Pradesh secure maximum central financial assistance under PM-KUSUM and bolster the state transition to clean energy while providing quality daytime power to the agricultural sector.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Suzuki Targets 4 mn Units in India by FY30, Builds Global Hub

Suzuki Motor Corporation plans to raise annual production capacity in India to approximately 4 mn units from fiscal 2030, strengthening the country’s role as a manufacturing and export hub for its global operations. The Japanese car maker announced the target as part of its Technology Strategy 2026, which outlines its development and manufacturing priorities for the coming decade. The company also aims to improve development efficiency by 30 per cent from the FY20 level and manufacturing efficiency by 50 per cent by FY30. It plans to halve the lead time required to develop new vehicles by im..

Next Story
Infrastructure Transport

Ayodhya Airport to Add Flights to Delhi, Bengaluru and Mumbai

Ayodhya airport will get additional direct air services to Delhi and Bengaluru from October 1, followed by a daily non-stop connection to Mumbai from October 30. The existing IndiGo service to Hyderabad is also being prepared for conversion into a daily operation, widening travel options from the temple city. Passengers travelling to Delhi will have two direct options at different times of day from October 1. Akasa Air flight QP 1608 will depart Ayodhya at 12:50 pm and arrive in Delhi at 2:20 pm, while Air India Express flight IX 1274 will leave at 2:10 pm and reach the capital at 3:45 pm. Ind..

Next Story
Infrastructure Urban

Cement Prices Rise Again in Himachal Pradesh

Cement prices in Himachal Pradesh have increased for the second time this month, raising construction expenses for households, contractors and other consumers. Cement companies raised rates by Rs. 5 per bag on Friday, 10 days after a similar increase was implemented on September 15. The two revisions have lifted prices by a total of Rs. 10 per bag within 10 days. Dealers Pawan, Rohit, Manoj and Rakesh said the latest rates were being applied across the market, adding to the financial pressure on people building or renovating homes. ACC Suraksha cement is now priced at Rs. 425 per bag, compared..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code