HC rules property tax applies post-occupancy certificate
Real Estate

HC rules property tax applies post-occupancy certificate

The high court has observed that property tax on a building can only be imposed after its completion, until which time the levy applies solely to the vacant or open land. In response to the petition filed by M/s BM Habitat, Justice Suraj Govindaraj has directed the Mysuru City Corporation to collect property tax for the petitioner's multiplex building on Vinobhanagar Road, Jayalakshmipuram, starting from April 25, 2011?the date when the occupancy certificate was issued.

The building had received plan sanction on January 18, 2006, and a commencement certificate on May 3, 2007. Despite completing construction on December 2, 2010, the occupancy certificate was only granted on April 25, 2011. Subsequently, on May 2, 2015, the city corporation issued a notice demanding property tax payment from January 17, 2008, citing the expiration of the two-year validity of the sanctioned plan.

Despite a high court order for reconsideration on February 16, 2018, the city corporation persisted in its demand for property tax from January 17, 2008, leading to further legal proceedings. The petitioner explained that construction was delayed until July 2010 due to the necessity of obtaining a no-objection certificate from the deputy commissioner for operating a multiplex and the delayed issuance of fire clearance. The occupancy certificate, crucial for property tax eligibility, was finally granted on April 25, 2011.

Justice Suraj Govindaraj acknowledged a significant delay on the part of the corporation in inspecting the property and issuing the occupancy certificate. Emphasising that there is no evidence showing the petitioner's use or occupation of the property before the certificate's issuance, the judge stated that property tax applies only after completion, post-occupancy certificate issuance.

The high court has observed that property tax on a building can only be imposed after its completion, until which time the levy applies solely to the vacant or open land. In response to the petition filed by M/s BM Habitat, Justice Suraj Govindaraj has directed the Mysuru City Corporation to collect property tax for the petitioner's multiplex building on Vinobhanagar Road, Jayalakshmipuram, starting from April 25, 2011?the date when the occupancy certificate was issued. The building had received plan sanction on January 18, 2006, and a commencement certificate on May 3, 2007. Despite completing construction on December 2, 2010, the occupancy certificate was only granted on April 25, 2011. Subsequently, on May 2, 2015, the city corporation issued a notice demanding property tax payment from January 17, 2008, citing the expiration of the two-year validity of the sanctioned plan. Despite a high court order for reconsideration on February 16, 2018, the city corporation persisted in its demand for property tax from January 17, 2008, leading to further legal proceedings. The petitioner explained that construction was delayed until July 2010 due to the necessity of obtaining a no-objection certificate from the deputy commissioner for operating a multiplex and the delayed issuance of fire clearance. The occupancy certificate, crucial for property tax eligibility, was finally granted on April 25, 2011. Justice Suraj Govindaraj acknowledged a significant delay on the part of the corporation in inspecting the property and issuing the occupancy certificate. Emphasising that there is no evidence showing the petitioner's use or occupation of the property before the certificate's issuance, the judge stated that property tax applies only after completion, post-occupancy certificate issuance.

Next Story
Infrastructure Urban

Panasonic Showcases Connected Display Solutions

Panasonic Life Solutions India showcased its integrated display, projection, broadcast and communication technologies at Panasonic Tech Summit 2026 in New Delhi. Hosted through its System Solutions Division, the two-day event highlighted connected technology solutions for education, healthcare, retail, transportation, corporate offices and entertainment.The summit, themed ‘Turning Technology into Value’, featured experience-led zones covering QSR, retail, transit, corporate offices, healthcare, education, security, projection, home theatre and professional displays. Panasonic also introduc..

Next Story
Infrastructure Transport

Kapsch to Deliver India’s First C-ITS Project

"Kapsch TrafficCom will deliver India’s first Cooperative Intelligent Transport Systems project on a key expressway near New Delhi. The project will be implemented with Superwave Communication And Infrasolution Limited to demonstrate how connected mobility can improve road safety and traffic efficiency.The pilot will use real-time connectivity and AI-enabled situational awareness to support road users, especially in high-risk areas such as temporary work zones. Drivers will receive alerts on roadworks, maintenance vehicles, hazardous locations, traffic queues and temporary virtual signage di..

Next Story
Infrastructure Urban

Eurobond Net Profit Rises 44 Per Cent

Euro Panel Products, the parent company of Eurobond, reported a 44.13 per cent year-on-year rise in net profit for FY25–26. The company’s revenue from operations grew 18.91 per cent to Rs 503.20 crore, compared to Rs 423.18 crore in the previous financial year.The company’s full-year EBITDA stood at Rs 56.67 crore, marking a 31.82 per cent increase. Profit after tax rose to Rs 26.56 crore, while net worth increased 20.15 per cent to Rs 160.07 crore. Earnings per share for the year stood at Rs 10.84.Divyam Rajesh Shah, Whole Time Director and CFO, Euro Panel Products, said the company’s..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->