Coal India unit seeks bids for 13 MW solar project in Jharkhand
ECONOMY & POLICY

Coal India unit seeks bids for 13 MW solar project in Jharkhand

The Central Mine Planning & Design Institute (CMPDI), a subsidiary of Coal India, has issued an invitation for bids regarding the design, supply, installation, commissioning, and testing of grid-connected solar power projects with a cumulative capacity of 13 MW.

It was mentioned that these projects were intended for Central Coalfields Ranchi at NK Area Chatra, Jharkhand, and were accompanied by a five-year operation and maintenance (O&M) period.

It was further informed that the last date for the submission of bids was March 28, 2024, and the opening of bids would take place on the same day.

The notification emphasized that the commencement of work should take place within 30 days of the issuance of the letter of acceptance and the submission of the performance security. Alternatively, the work was required to begin within seven days after the site was handed over for the first activity.

Bidders were obligated to provide an earnest money deposit of Rs 5 million.

The entire contract period, spanning 2,065 days, was detailed in two main phases: the construction of the plant, including testing and commissioning, allotted 240 days, and the comprehensive operation and maintenance of the plant, scheduled for 1,825 days.

It was specified that bidders needed to have completed similar works, specifically related to the design, supply, installation, commissioning, and testing of grid-connected ground-mounted, rooftop, or floating solar projects. Additionally, they were required to have finished three similar completed works, each with a cost not less than 20% of the estimated cost put to tender, or two similar completed works, each with a cost not less than 25% of the estimated cost put to tender, or one similar completed work, with a cost not less than 40% of the estimated cost put to tender.

The Central Mine Planning & Design Institute (CMPDI), a subsidiary of Coal India, has issued an invitation for bids regarding the design, supply, installation, commissioning, and testing of grid-connected solar power projects with a cumulative capacity of 13 MW. It was mentioned that these projects were intended for Central Coalfields Ranchi at NK Area Chatra, Jharkhand, and were accompanied by a five-year operation and maintenance (O&M) period. It was further informed that the last date for the submission of bids was March 28, 2024, and the opening of bids would take place on the same day. The notification emphasized that the commencement of work should take place within 30 days of the issuance of the letter of acceptance and the submission of the performance security. Alternatively, the work was required to begin within seven days after the site was handed over for the first activity. Bidders were obligated to provide an earnest money deposit of Rs 5 million. The entire contract period, spanning 2,065 days, was detailed in two main phases: the construction of the plant, including testing and commissioning, allotted 240 days, and the comprehensive operation and maintenance of the plant, scheduled for 1,825 days. It was specified that bidders needed to have completed similar works, specifically related to the design, supply, installation, commissioning, and testing of grid-connected ground-mounted, rooftop, or floating solar projects. Additionally, they were required to have finished three similar completed works, each with a cost not less than 20% of the estimated cost put to tender, or two similar completed works, each with a cost not less than 25% of the estimated cost put to tender, or one similar completed work, with a cost not less than 40% of the estimated cost put to tender.

Next Story
Infrastructure Urban

Centre Clears Power Distribution Upgrade for Uttar Pradesh

The Central Government has approved power distribution projects worth Rs 407.39 billion for Uttar Pradesh under the Revamped Distribution Sector Scheme (RDSS). The investment will be used to modernise the state's electricity distribution infrastructure and strengthen network capacity across urban and rural areas. The package targets one of the country's largest distribution networks as the state experiences rapid urbanisation and rising electricity consumption. Planned interventions include the strengthening of distribution lines, modernisation of substations, replacement of ageing electrical ..

Next Story
Infrastructure Energy

India Data Centres To Consume 191 TWh By 2040 Driving Renewables

A Wood Mackenzie report says India's operational data centre capacity is projected to increase more than fivefold to 12 gigawatt (GW) by 2030 from 2.2 GW in 2025 as artificial intelligence (AI) and cloud computing drive demand. It projects electricity consumption to rise from 10 terawatt-hour (TWh) in 2025 to 191 TWh by 2040. The study forecasts a compound annual growth rate of around 40 per cent and notes AI-dedicated capacity will surge nearly 24-fold from 275 megawatt (MW) in 2025 to 6,546 MW by 2030. The report places India's digital economy at Rs 32 trillion (tn) in 2025 and says it contr..

Next Story
Infrastructure Transport

Hydrogen Train Completes 1,200 Kilometres Of Trials

India's first hydrogen train was flagged off between Jind and Sonipat on July 17 and has travelled over 1,200 kilometres in trials, saving diesel consumption of more than 3,200 litres, a Railway Ministry press release said. The deployment marks the introduction of a zero-emission fuel cell train into route testing and represents a milestone in domestic rail innovation. The train generates electricity onboard through a chemical reaction between hydrogen and oxygen, producing electricity to propel the vehicle while emitting only water vapour as a by-product. There is no smoke and no tailpipe car..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement