Delay Analysis in Construction Arbitration
ECONOMY & POLICY

Delay Analysis in Construction Arbitration

In construction disputes, ‘delay analysis’ is essential for establishing the cause of delay, which in turn determines whether the contractor is entitled to an extension of time and associated costs or whether the employer is justified in imposing liquidated damages. This article enunciates various methods employed in the analysis of construction delays. It provides a detailed overview of the techniques used to identify, quantify and apportion delays among project stakeholders that are critical for the resolution of disputes pertaining to extension of time (EOT) and substantiation of EOT claims.

Methods

The 2nd edition of the Society of Construction Law Delay and Disruption Protocol, 2017, (SCL Protocol) identifies six primary methods for delay analysis, categorised broadly into prospective and retrospective methods as described below:

  • Impacted as-planned analysis: This prospective method involves inserting delay events into a logic-linked baseline programme to assess their theoretical impact on the completion of the project.

To read the full story Click Here.

In construction disputes, ‘delay analysis’ is essential for establishing the cause of delay, which in turn determines whether the contractor is entitled to an extension of time and associated costs or whether the employer is justified in imposing liquidated damages. This article enunciates various methods employed in the analysis of construction delays. It provides a detailed overview of the techniques used to identify, quantify and apportion delays among project stakeholders that are critical for the resolution of disputes pertaining to extension of time (EOT) and substantiation of EOT claims.MethodsThe 2nd edition of the Society of Construction Law Delay and Disruption Protocol, 2017, (SCL Protocol) identifies six primary methods for delay analysis, categorised broadly into prospective and retrospective methods as described below:Impacted as-planned analysis: This prospective method involves inserting delay events into a logic-linked baseline programme to assess their theoretical impact on the completion of the project.To read the full story Click Here.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code