GERC Closes Petition After Four Point One Five MW Project Commissioned
ECONOMY & POLICY

GERC Closes Petition After Four Point One Five MW Project Commissioned

The Gujarat Electricity Regulatory Commission (GERC) has closed a legal petition after the petitioner withdrew its case following commissioning of a captive solar project. The petition concerned a four point one five megawatt (MW) captive solar plant and was filed by Durga Processors Private Limited, a Surat based company, as Petition No. 2438 of 2025. The Commission disposed of the petition after a hearing in Gandhinagar that reviewed submissions from both parties. The respondent was Gujarat Energy Transmission Corporation Limited (GETCO).

The petitioner had sought an extension for commissioning of the project evacuation line, bays and metering infrastructure connected to the captive plant and had requested a three month extension from the original transmission capacity allotment date of 30 December 2023. The company had also asked the Commission to direct GETCO not to invoke a bank guarantee of Rs two point zero seven five million (mn) during the proposed extension. The petition had been filed under Section 86 of the Electricity Act, 2003 and related to regulatory interpretation of a tariff order.

During the hearing on 26 February 2026 the petitioner stated that the plant had been commissioned on nine April 2025 and submitted a commissioning certificate issued by the Gujarat Energy Development Agency (GEDA) dated 27 May 2025. The petitioner explained that the petition had arisen from a misunderstanding of applicable regulatory provisions and that the firm had relied on a tariff order that did not apply. GETCO told the Commission that it had no objection to withdrawal of the petition. The petitioner filed a formal affidavit on 27 February 2026 confirming the request to withdraw.

A bench comprising Chairman Pankaj Joshi and Members Hiren Shah and Jatin N. Thakkar reviewed the records and concluded that disposal as withdrawn was appropriate. The Commission issued an order closing the matter on five March 2026, ending the proceedings since the solar plant had already been commissioned and regulatory relief was no longer required.

The Gujarat Electricity Regulatory Commission (GERC) has closed a legal petition after the petitioner withdrew its case following commissioning of a captive solar project. The petition concerned a four point one five megawatt (MW) captive solar plant and was filed by Durga Processors Private Limited, a Surat based company, as Petition No. 2438 of 2025. The Commission disposed of the petition after a hearing in Gandhinagar that reviewed submissions from both parties. The respondent was Gujarat Energy Transmission Corporation Limited (GETCO). The petitioner had sought an extension for commissioning of the project evacuation line, bays and metering infrastructure connected to the captive plant and had requested a three month extension from the original transmission capacity allotment date of 30 December 2023. The company had also asked the Commission to direct GETCO not to invoke a bank guarantee of Rs two point zero seven five million (mn) during the proposed extension. The petition had been filed under Section 86 of the Electricity Act, 2003 and related to regulatory interpretation of a tariff order. During the hearing on 26 February 2026 the petitioner stated that the plant had been commissioned on nine April 2025 and submitted a commissioning certificate issued by the Gujarat Energy Development Agency (GEDA) dated 27 May 2025. The petitioner explained that the petition had arisen from a misunderstanding of applicable regulatory provisions and that the firm had relied on a tariff order that did not apply. GETCO told the Commission that it had no objection to withdrawal of the petition. The petitioner filed a formal affidavit on 27 February 2026 confirming the request to withdraw. A bench comprising Chairman Pankaj Joshi and Members Hiren Shah and Jatin N. Thakkar reviewed the records and concluded that disposal as withdrawn was appropriate. The Commission issued an order closing the matter on five March 2026, ending the proceedings since the solar plant had already been commissioned and regulatory relief was no longer required.

Next Story
Infrastructure Urban

Centre Examines Duty Relief Under MOOWR For Battery Storage Imports

The finance ministry is examining whether to continue customs warehousing benefits under the Manufacture and Other Operations in Warehouse Regulations, 2019 framework for imported battery energy storage systems. It plans consultations with the ministries of power and new and renewable energy to decide on the future scope of duty and GST deferment for such imports. The review follows concerns from the renewable energy sector that the current approach is creating an uneven playing field. Under the regulations, companies may import goods without paying customs duty or goods and services tax upfro..

Next Story
Infrastructure Urban

Jamshedpur MP Seeks Rs 4,820 Million Plan For Tatanagar Platforms

Member of Parliament Bidyut Baran Mahato held a meeting with Vikas Jain, Executive Director (Public Grievances) of the Railway Board, following a special session of Parliament to press for accelerated rail infrastructure work around Jamshedpur and Tatanagar. The discussions addressed a range of projects that the ministry is prioritising for the area. Final Location Surveys for the construction of the fourth and fifth railway lines between Pandrasali and Kandra and for the development of a satellite station near Tatanagar have already been approved, clearing the way for detailed planning. Mahat..

Next Story
Infrastructure Energy

Final Batch Of Two 3,300 HP Locomotives Reach Mozambique

The final batch of two 3,300 horsepower (hp) locomotives manufactured by Banaras Locomotive Works (BLW) has reached Mozambique, marking completion of an export consignment. The locomotives arrived at Maputo harbour and were cleared for onward movement to the national rail operator. The shipment closes a programme that began with earlier consignments delivered over the past months. Banaras Locomotive Works, a production unit of Indian Railways, built the locomotives under a contract with the Mozambican rail authority and managed the final inspections and commissioning preparations prior to disp..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement