GERC Closes Petition After Four Point One Five MW Project Commissioned
ECONOMY & POLICY

GERC Closes Petition After Four Point One Five MW Project Commissioned

The Gujarat Electricity Regulatory Commission (GERC) has closed a legal petition after the petitioner withdrew its case following commissioning of a captive solar project. The petition concerned a four point one five megawatt (MW) captive solar plant and was filed by Durga Processors Private Limited, a Surat based company, as Petition No. 2438 of 2025. The Commission disposed of the petition after a hearing in Gandhinagar that reviewed submissions from both parties. The respondent was Gujarat Energy Transmission Corporation Limited (GETCO).

The petitioner had sought an extension for commissioning of the project evacuation line, bays and metering infrastructure connected to the captive plant and had requested a three month extension from the original transmission capacity allotment date of 30 December 2023. The company had also asked the Commission to direct GETCO not to invoke a bank guarantee of Rs two point zero seven five million (mn) during the proposed extension. The petition had been filed under Section 86 of the Electricity Act, 2003 and related to regulatory interpretation of a tariff order.

During the hearing on 26 February 2026 the petitioner stated that the plant had been commissioned on nine April 2025 and submitted a commissioning certificate issued by the Gujarat Energy Development Agency (GEDA) dated 27 May 2025. The petitioner explained that the petition had arisen from a misunderstanding of applicable regulatory provisions and that the firm had relied on a tariff order that did not apply. GETCO told the Commission that it had no objection to withdrawal of the petition. The petitioner filed a formal affidavit on 27 February 2026 confirming the request to withdraw.

A bench comprising Chairman Pankaj Joshi and Members Hiren Shah and Jatin N. Thakkar reviewed the records and concluded that disposal as withdrawn was appropriate. The Commission issued an order closing the matter on five March 2026, ending the proceedings since the solar plant had already been commissioned and regulatory relief was no longer required.

The Gujarat Electricity Regulatory Commission (GERC) has closed a legal petition after the petitioner withdrew its case following commissioning of a captive solar project. The petition concerned a four point one five megawatt (MW) captive solar plant and was filed by Durga Processors Private Limited, a Surat based company, as Petition No. 2438 of 2025. The Commission disposed of the petition after a hearing in Gandhinagar that reviewed submissions from both parties. The respondent was Gujarat Energy Transmission Corporation Limited (GETCO). The petitioner had sought an extension for commissioning of the project evacuation line, bays and metering infrastructure connected to the captive plant and had requested a three month extension from the original transmission capacity allotment date of 30 December 2023. The company had also asked the Commission to direct GETCO not to invoke a bank guarantee of Rs two point zero seven five million (mn) during the proposed extension. The petition had been filed under Section 86 of the Electricity Act, 2003 and related to regulatory interpretation of a tariff order. During the hearing on 26 February 2026 the petitioner stated that the plant had been commissioned on nine April 2025 and submitted a commissioning certificate issued by the Gujarat Energy Development Agency (GEDA) dated 27 May 2025. The petitioner explained that the petition had arisen from a misunderstanding of applicable regulatory provisions and that the firm had relied on a tariff order that did not apply. GETCO told the Commission that it had no objection to withdrawal of the petition. The petitioner filed a formal affidavit on 27 February 2026 confirming the request to withdraw. A bench comprising Chairman Pankaj Joshi and Members Hiren Shah and Jatin N. Thakkar reviewed the records and concluded that disposal as withdrawn was appropriate. The Commission issued an order closing the matter on five March 2026, ending the proceedings since the solar plant had already been commissioned and regulatory relief was no longer required.

Next Story
Real Estate

Casagrand Launches 41-Acre Highcity Project in Chennai

Casagrand has launched Casagrand Highcity, a 41-acre integrated residential development on Chennai’s Outer Ring Road (ORR), marking the company’s largest residential project to date.The project will comprise over 4,000 two and three BHK apartments across four G+22 towers and is positioned as one of the largest organised residential developments in the ORR corridor.Located along Chennai’s emerging residential and infrastructure growth belt, the project benefits from connectivity to IT hubs including Navalur, Siruseri SIPCOT and Porur, as well as industrial clusters such as Sriperumbudur, ..

Next Story
Real Estate

Brigade, Marriott Open Courtyard Kochi Infopark

Brigade Hotel Ventures (BHVL) and Marriott International have opened Courtyard by Marriott Kochi Infopark, a rebranded and upgraded hotel formerly operating as Four Points by Sheraton Kochi Infopark.Located in Kakkanad adjoining Infopark Kochi, the 218-room property strengthens Brigade’s hospitality portfolio in one of the city’s key IT and commercial corridors. The hotel is positioned to cater to corporate, MICE and leisure travellers visiting Infopark, SmartCity and other business hubs in Kochi.The property offers flexible workspaces, smart TVs and high-speed WiFi across rooms and suites..

Next Story
Real Estate

WorkEZ Expands South India Portfolio to 1.7 Mn Sq Ft

Work Easy Space Solutions (WorkEZ) has expanded its managed workspace portfolio to approximately 1.7 million sq. ft. across 12 operational buildings and two upcoming developments, strengthening its footprint across South India.The expansion includes the addition of 65,000 sq. ft. at Phoenix One National Park in Chennai and the company’s entry into Kochi through a partnership with Lulu Developers, adding another 70,000 sq. ft.WorkEZ has also signed a 0.4 million sq. ft. development in Coimbatore with Veeras Infra following the successful leasing of 0.1 million sq. ft. in the first phase. The ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement