GERC Closes Petition After Four Point One Five MW Project Commissioned
ECONOMY & POLICY

GERC Closes Petition After Four Point One Five MW Project Commissioned

The Gujarat Electricity Regulatory Commission (GERC) has closed a legal petition after the petitioner withdrew its case following commissioning of a captive solar project. The petition concerned a four point one five megawatt (MW) captive solar plant and was filed by Durga Processors Private Limited, a Surat based company, as Petition No. 2438 of 2025. The Commission disposed of the petition after a hearing in Gandhinagar that reviewed submissions from both parties. The respondent was Gujarat Energy Transmission Corporation Limited (GETCO).

The petitioner had sought an extension for commissioning of the project evacuation line, bays and metering infrastructure connected to the captive plant and had requested a three month extension from the original transmission capacity allotment date of 30 December 2023. The company had also asked the Commission to direct GETCO not to invoke a bank guarantee of Rs two point zero seven five million (mn) during the proposed extension. The petition had been filed under Section 86 of the Electricity Act, 2003 and related to regulatory interpretation of a tariff order.

During the hearing on 26 February 2026 the petitioner stated that the plant had been commissioned on nine April 2025 and submitted a commissioning certificate issued by the Gujarat Energy Development Agency (GEDA) dated 27 May 2025. The petitioner explained that the petition had arisen from a misunderstanding of applicable regulatory provisions and that the firm had relied on a tariff order that did not apply. GETCO told the Commission that it had no objection to withdrawal of the petition. The petitioner filed a formal affidavit on 27 February 2026 confirming the request to withdraw.

A bench comprising Chairman Pankaj Joshi and Members Hiren Shah and Jatin N. Thakkar reviewed the records and concluded that disposal as withdrawn was appropriate. The Commission issued an order closing the matter on five March 2026, ending the proceedings since the solar plant had already been commissioned and regulatory relief was no longer required.

The Gujarat Electricity Regulatory Commission (GERC) has closed a legal petition after the petitioner withdrew its case following commissioning of a captive solar project. The petition concerned a four point one five megawatt (MW) captive solar plant and was filed by Durga Processors Private Limited, a Surat based company, as Petition No. 2438 of 2025. The Commission disposed of the petition after a hearing in Gandhinagar that reviewed submissions from both parties. The respondent was Gujarat Energy Transmission Corporation Limited (GETCO). The petitioner had sought an extension for commissioning of the project evacuation line, bays and metering infrastructure connected to the captive plant and had requested a three month extension from the original transmission capacity allotment date of 30 December 2023. The company had also asked the Commission to direct GETCO not to invoke a bank guarantee of Rs two point zero seven five million (mn) during the proposed extension. The petition had been filed under Section 86 of the Electricity Act, 2003 and related to regulatory interpretation of a tariff order. During the hearing on 26 February 2026 the petitioner stated that the plant had been commissioned on nine April 2025 and submitted a commissioning certificate issued by the Gujarat Energy Development Agency (GEDA) dated 27 May 2025. The petitioner explained that the petition had arisen from a misunderstanding of applicable regulatory provisions and that the firm had relied on a tariff order that did not apply. GETCO told the Commission that it had no objection to withdrawal of the petition. The petitioner filed a formal affidavit on 27 February 2026 confirming the request to withdraw. A bench comprising Chairman Pankaj Joshi and Members Hiren Shah and Jatin N. Thakkar reviewed the records and concluded that disposal as withdrawn was appropriate. The Commission issued an order closing the matter on five March 2026, ending the proceedings since the solar plant had already been commissioned and regulatory relief was no longer required.

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement