Infrastructure Project Price Overruns Climb to Six-Month High
ECONOMY & POLICY

Infrastructure Project Price Overruns Climb to Six-Month High

According to data released by the federal government, price overruns climbed to a six-month high in September, reversing the features made in the previous couple of months. In September, the predicted price of central infrastructure tasks was 21.92% more than the unique price, compared to 19.08% in August.

The federal government may seek to spend an additional Rs 4.5 lakh crore on projects costing Rs 150 crore or more, bringing the total investment to Rs 24.8 lakh crore. In addition, the completion time increased from 36.96 months to 38.63 months in comparison to the previous month. Though the number of delayed assignments decreased to 823 in September from 830 in August, 58% are currently delayed for more than two years.

In September, the federal government's monitoring portal considered 1,418 tasks, 12 of which were added from the previous month. In September, the federal government completed 46 missions. The report notes that 268 tasks had been on schedule, whereas 242 confronted price and time overruns.Nevertheless, it highlights that this may occasionally not current the precise image on the bottom, as not all businesses could also be reporting or offering checklist of milestones.

?The involved administrative Ministry might prefer to assessment the tasks with a view to keep away from additional price overrun, time overruns, to agency up milestones in case of milestone will not be accessible, to agency up revised price estimates and revised commissioning schedule if the identical has been not revised and lapsed,? the report acknowledged.

Railways was one of the ministries experiencing the greatest price overruns, with estimated costs in 173 tasks being 68.1% more than the original cost. The 41 jobs of the Ministry of Water Resources saw 195.6% cost overruns, whereas highways, which accounted for over half of all tasks monitored under the system, only 4.3% cost overruns.

Northeastern states had the lowest price overruns, followed by Andhra Pradesh.

According to data released by the federal government, price overruns climbed to a six-month high in September, reversing the features made in the previous couple of months. In September, the predicted price of central infrastructure tasks was 21.92% more than the unique price, compared to 19.08% in August. The federal government may seek to spend an additional Rs 4.5 lakh crore on projects costing Rs 150 crore or more, bringing the total investment to Rs 24.8 lakh crore. In addition, the completion time increased from 36.96 months to 38.63 months in comparison to the previous month. Though the number of delayed assignments decreased to 823 in September from 830 in August, 58% are currently delayed for more than two years. In September, the federal government's monitoring portal considered 1,418 tasks, 12 of which were added from the previous month. In September, the federal government completed 46 missions. The report notes that 268 tasks had been on schedule, whereas 242 confronted price and time overruns.Nevertheless, it highlights that this may occasionally not current the precise image on the bottom, as not all businesses could also be reporting or offering checklist of milestones. ?The involved administrative Ministry might prefer to assessment the tasks with a view to keep away from additional price overrun, time overruns, to agency up milestones in case of milestone will not be accessible, to agency up revised price estimates and revised commissioning schedule if the identical has been not revised and lapsed,? the report acknowledged. Railways was one of the ministries experiencing the greatest price overruns, with estimated costs in 173 tasks being 68.1% more than the original cost. The 41 jobs of the Ministry of Water Resources saw 195.6% cost overruns, whereas highways, which accounted for over half of all tasks monitored under the system, only 4.3% cost overruns. Northeastern states had the lowest price overruns, followed by Andhra Pradesh.

Next Story
Infrastructure Urban

DCPC Prepares for Special Campaign 5.0 with Focus on E-Waste

The Department of Chemicals and Petrochemicals (DCPC), Ministry of Chemicals and Fertilisers, is gearing up for Special Campaign 5.0, to be held from 2nd to 31st October 2025. The initiative will focus on e-waste disposal as per MoEFCC’s E-Waste Management Rules 2022, space optimisation, and enhancing workplace efficiency across field offices.Special Campaign 4.0, conducted between October 2023 and October 2024, delivered notable results in record management, grievance redressal, scrap disposal, and cleanliness drives.Key outcomes of Special Campaign 4.0Records management: 2,443 physical fil..

Next Story
Real Estate

BlackRock India Leases 1.4 Lakh Sq Ft in Bengaluru

BlackRock Services India, the domestic arm of global asset manager BlackRock, has leased 1.4 lakh sq ft of office space at IndiQube Symphony in Bengaluru, according to Propstack data. The 10-year deal is valued at around Rs 4.10 billion.The lease, among the largest transactions in India’s co-working sector, highlights the growing preference of global institutions for flexible office providers. The agreement, commencing October 1, 2025, covers ground plus five floors in KNG Tower 1 at Ashoknagar, MG Road — one of Bengaluru’s prime commercial hubs.As per the lease document, BlackRock will ..

Next Story
Infrastructure Transport

L&T Bags Rs 25–50 Bn Order for Mumbai-Ahmedabad Bullet Train Track Works

Larsen & Toubro’s (L&T) Transportation Infrastructure business has secured an order valued between Rs 25 crore and Rs 50 billion from the National High Speed Rail Corporation Limited (NHSRCL) for the Mumbai-Ahmedabad High Speed Rail (MAHSR) corridor.The contract, Package T1, involves the design, supply, construction, testing, and commissioning of 156 route km of high-speed ballastless track on a Design-Build Lump Sum Price basis. The stretch runs from Mumbai’s Bandra-Kurla Complex to Zaroli village in Gujarat and includes 21 km of underground track and 135 km of elevated viaduct.Se..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?