Mahalaxmi Skywalk Cut Short Ahead Of Metro Station
ECONOMY & POLICY

Mahalaxmi Skywalk Cut Short Ahead Of Metro Station

Mumbai's first travelator-equipped skywalk intended to link the monorail at Sant Gadge Maharaj Chowk with Metro Line three Mahalaxmi station has been shortened and will now stop about 200 metres before the station, forcing commuters to complete part of the interchange on foot. The footover bridge was planned to offer a seamless transfer between modes but the truncated alignment requires users to navigate footpaths and cross busy roads. Officials indicated that the revised structure will nevertheless improve commuter movement.

The original footover bridge measured 384 metres and was to provide a direct connection to the metro station, but the alignment now terminates at Jacob Circle, also known as Saat Rasta. Commuters will need to cross three lanes of the Saat Rasta roundabout and use crowded footpaths to switch systems, raising fresh questions over the multi-modal integration strategy for the city. Authorities described technical infeasibility caused by the Brihanmumbai Municipal Corporation flyover from Keshavrao Khadye Marg as a key constraint.

Other factors cited included the Metro Line three underground tunnel influence zone, a heritage police station, underground utilities and traffic restrictions linked to Elphinstone bridge reconstruction. The area also contains water reservoirs, drains and sewer lines, and Saat Rasta is a key procession route during Ganesh Chaturthi, complicating planning. Planners found the original alignment would have affected 78 trees, while the modified plan removes the need for tree cutting. Officials said the redesign balanced safety, heritage and environmental concerns.

The contract had been awarded to a joint venture led by Niraj Cement Structurals Ltd at Rs 826.6 million (Rs 826.6 mn), and following redesign the project cost stands at Rs 700.5 mn. The shortening of the skywalk by over 100 metres reduced project costs by more than Rs 100 mn. Officials indicated that a later link to Mahalaxmi railway station was not part of the original scope but could be considered, and some commuters cautioned that the shortened structure will necessitate careful road crossing despite wide footpaths.

Mumbai's first travelator-equipped skywalk intended to link the monorail at Sant Gadge Maharaj Chowk with Metro Line three Mahalaxmi station has been shortened and will now stop about 200 metres before the station, forcing commuters to complete part of the interchange on foot. The footover bridge was planned to offer a seamless transfer between modes but the truncated alignment requires users to navigate footpaths and cross busy roads. Officials indicated that the revised structure will nevertheless improve commuter movement. The original footover bridge measured 384 metres and was to provide a direct connection to the metro station, but the alignment now terminates at Jacob Circle, also known as Saat Rasta. Commuters will need to cross three lanes of the Saat Rasta roundabout and use crowded footpaths to switch systems, raising fresh questions over the multi-modal integration strategy for the city. Authorities described technical infeasibility caused by the Brihanmumbai Municipal Corporation flyover from Keshavrao Khadye Marg as a key constraint. Other factors cited included the Metro Line three underground tunnel influence zone, a heritage police station, underground utilities and traffic restrictions linked to Elphinstone bridge reconstruction. The area also contains water reservoirs, drains and sewer lines, and Saat Rasta is a key procession route during Ganesh Chaturthi, complicating planning. Planners found the original alignment would have affected 78 trees, while the modified plan removes the need for tree cutting. Officials said the redesign balanced safety, heritage and environmental concerns. The contract had been awarded to a joint venture led by Niraj Cement Structurals Ltd at Rs 826.6 million (Rs 826.6 mn), and following redesign the project cost stands at Rs 700.5 mn. The shortening of the skywalk by over 100 metres reduced project costs by more than Rs 100 mn. Officials indicated that a later link to Mahalaxmi railway station was not part of the original scope but could be considered, and some commuters cautioned that the shortened structure will necessitate careful road crossing despite wide footpaths.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

NABARD Holds Seminar on Vigilance, Integrity and Good Governance

National Bank for Agriculture and Rural Development (NABARD) organised a seminar on “Vigilance: Strengthening Integrity and Good Governance” on 25 August 2026 at its Head Office in Mumbai as part of the ongoing Vigilance Awareness Campaign 2026 being observed from 17 August to 16 November 2026, with the theme “Probity for Prosperity."" The seminar was graced by Suresh N Patel, Former Central Vigilance Commissioner, Government of India, as the chief guest and keynote speaker.  The programme was attended by G S Rawat, Deputy Managing Director, Dr Ajay K Sood, Deputy Managing Dire..

Next Story
Equipment

XCMG Unveils World's First 14,000-Ton Ring Crane for Heavy Lifting

XCMG has announced that the first main unit of the world's first 14,000-ton ring crane has rolled off the production line, marking a historic breakthrough in ultra-heavy lifting technology. Jointly developed by XCMG and Sinopec Heavy Lifting & Transportation Co., Ltd., the crane will be the largest-capacity ring crane ever built, setting a new benchmark for major construction projects worldwide.The crane features a modular configuration comprising two main units that work in tandem. The first main unit has completed final assembly and can independently perform lifting operations. Once both..

Next Story
Infrastructure Urban

Thriveni Logistics orders 200 tip trailers from Jagdamba trailers

Jagdamba Trailers (JTPL), one of India’s growing trailer manufacturers, has secured a significant order for 200 Tip Trailers from Thriveni Transport and Logistics Pvt. Ltd., a leading mining and logistics company serving operations across India and overseas.The order, placed for iron ore transportation, is a major milestone for JTPL, particularly as the company secured the business after competing with more than 10 established trailer manufacturers. It also strengthens an already successful relationship between the two companies. Approximately one and a half years ago, Thriveni Transport and..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code