Tamil Nadu Awards 1,400 MWh BESS To Eagle Infra And OPG
ECONOMY & POLICY

Tamil Nadu Awards 1,400 MWh BESS To Eagle Infra And OPG

In a state auction conducted by the Tamil Nadu Green Energy Corporation, two developers were awarded a majority of the capacity in a seven standalone Battery Energy Storage System (BESS) tender that originally targeted 375 megawatts (MW) and 1,500 megawatt?hours (MWh) of storage. The final awarded energy capacity amounted to 1,400 MWh and the MW capacity was split almost evenly between the winners, with each developer securing 175 MW and 700 MWh. Eagle Infra India secured capacity at a tariff of Rs315,000 per MW per month and OPG Power Ventures won an equivalent quantum at a tariff of Rs316,000 per MW per month.

Under the contracts the developers will be responsible for designing, financing, installing and operating the battery energy storage systems and for integrating them with the state transmission network. The facilities will draw power from the grid through TANTRANSCO and TNPDCL and will charge and discharge capacity under instructions from the state load dispatch centre to manage peak demand and grid fluctuations. The projects will operate as standalone BESS assets connected to the transmission system.

The tender imposed strict technical standards requiring the batteries to maintain 95 per cent annual availability and to complete one and a half cycles per day while delivering a minimum round?trip efficiency of 85 per cent. To improve financial viability the government will provide viability gap funding equivalent to Rs one point eight million per MWh. Developers have 18 months to complete the construction and the commissioned systems will operate under a 15?year contract.

The allocation is intended to strengthen grid stability, support renewable energy integration and provide additional flexibility to the state network as variable generation grows. The slightly different tariffs signal market dynamics and the reduction from the tender target of 1,500 MWh to an awarded 1,400 MWh reflects the final procurement outcome. Once operational the BESS assets are expected to help manage peak demand and reduce operational pressure on conventional generators.

In a state auction conducted by the Tamil Nadu Green Energy Corporation, two developers were awarded a majority of the capacity in a seven standalone Battery Energy Storage System (BESS) tender that originally targeted 375 megawatts (MW) and 1,500 megawatt?hours (MWh) of storage. The final awarded energy capacity amounted to 1,400 MWh and the MW capacity was split almost evenly between the winners, with each developer securing 175 MW and 700 MWh. Eagle Infra India secured capacity at a tariff of Rs315,000 per MW per month and OPG Power Ventures won an equivalent quantum at a tariff of Rs316,000 per MW per month. Under the contracts the developers will be responsible for designing, financing, installing and operating the battery energy storage systems and for integrating them with the state transmission network. The facilities will draw power from the grid through TANTRANSCO and TNPDCL and will charge and discharge capacity under instructions from the state load dispatch centre to manage peak demand and grid fluctuations. The projects will operate as standalone BESS assets connected to the transmission system. The tender imposed strict technical standards requiring the batteries to maintain 95 per cent annual availability and to complete one and a half cycles per day while delivering a minimum round?trip efficiency of 85 per cent. To improve financial viability the government will provide viability gap funding equivalent to Rs one point eight million per MWh. Developers have 18 months to complete the construction and the commissioned systems will operate under a 15?year contract. The allocation is intended to strengthen grid stability, support renewable energy integration and provide additional flexibility to the state network as variable generation grows. The slightly different tariffs signal market dynamics and the reduction from the tender target of 1,500 MWh to an awarded 1,400 MWh reflects the final procurement outcome. Once operational the BESS assets are expected to help manage peak demand and reduce operational pressure on conventional generators.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code