Navi Mumbai airport development begins after long delay
AVIATION & AIRPORTS

Navi Mumbai airport development begins after long delay

The stalled Navi Mumbai International Airport (NMIA) project has finally started, with major the challenges being cleared.

The City and Industrial Development Corporation (CIDCO) aims to complete the development works of the first phase of the airport by the end of 2024.

The project is being developed on 2,268 hectares of land, from which 1,160 hectares will have the actual airport. The expected cost of the project is Rs 16,700 crore.

Recently, Adani Group took over the project. The project had land acquisition, rehabilitation and resettlement challenges due to opposition from the locals for years.

The Adani Group concessionaire has demanded the acquisition of the entire project land before beginning the actual development.

Ten villages within the core airport area had to be shifted, affecting 3,000 families. Nearly 22.5% of the developing land and other incentives were offered to the project affected people (PAPs). The project also had environmental issues and permissions from the central and state governments, and changes in the concessionaire required new approvals.

Vice-Chairman and Managing Director of CIDCO, Sanjay Mukherjee, said, CIDCO and NMIAL acquired the project in 1997 and are now starting at full pace. CIDCO has completed land acquisition, rehabilitation and predevelopment civil works. It is one of the most vital steps toward the successful execution of the project.

He added that NMIAL had obtained all clearances and financial closure. CIDCO has handed over the site to NMIAL, which has commenced the work of the airport at full speed.

Image Source

Also read: Adani Group concludes financing for Navi Mumbai airport project

The stalled Navi Mumbai International Airport (NMIA) project has finally started, with major the challenges being cleared. The City and Industrial Development Corporation (CIDCO) aims to complete the development works of the first phase of the airport by the end of 2024. The project is being developed on 2,268 hectares of land, from which 1,160 hectares will have the actual airport. The expected cost of the project is Rs 16,700 crore. Recently, Adani Group took over the project. The project had land acquisition, rehabilitation and resettlement challenges due to opposition from the locals for years. The Adani Group concessionaire has demanded the acquisition of the entire project land before beginning the actual development. Ten villages within the core airport area had to be shifted, affecting 3,000 families. Nearly 22.5% of the developing land and other incentives were offered to the project affected people (PAPs). The project also had environmental issues and permissions from the central and state governments, and changes in the concessionaire required new approvals. Vice-Chairman and Managing Director of CIDCO, Sanjay Mukherjee, said, CIDCO and NMIAL acquired the project in 1997 and are now starting at full pace. CIDCO has completed land acquisition, rehabilitation and predevelopment civil works. It is one of the most vital steps toward the successful execution of the project. He added that NMIAL had obtained all clearances and financial closure. CIDCO has handed over the site to NMIAL, which has commenced the work of the airport at full speed. Image Source Also read: Adani Group concludes financing for Navi Mumbai airport project

Next Story
Infrastructure Urban

InsideFPV Delivers ₹10 Crore Kamikaze Drone Order Under MoD’s EPR Route

InsideFPV, a Surat-based drone technology manufacturer, has successfully executed a ₹10 crore defence contract to supply indigenous kamikaze drones under the Ministry of Defence’s Emergency Procurement Route (EPR). The company completed the delivery of hundreds of FPV kamikaze drone platforms within a rapid two-month timeframe, highlighting its ability to meet urgent military procurement timelines.The supply orders were fulfilled under the emergency procurement mechanism, which is aimed at fast-tracking acquisitions for immediate operational needs. InsideFPV’s quick execution reflects it..

Next Story
Infrastructure Energy

Vedanta Resources Secures Fitch Upgrade to ‘BB-’, Best Rating Since 2015

Vedanta Resources Limited (VRL), a global player in metals, oil & gas, critical minerals, power and technology, has received a credit rating upgrade from Fitch Ratings, marking its strongest bond rating in over a decade.Fitch has raised Vedanta Resources’ Long-Term Foreign-Currency Issuer Default Rating (IDR) to ‘BB-’ from ‘B+’, while maintaining a Stable Outlook. The agency also upgraded VRL’s senior unsecured rating, along with the ratings of US dollar-denominated bonds issued by Vedanta Resources Finance II Plc and guaranteed by VRL, to ‘BB-’.The upgrade represents Vedan..

Next Story
Real Estate

NAREDCO NextGen NCR Chapter Launched

The NAREDCO NextGen NCR Chapter was recently launched at Excelerate 2026 in Mumbai, marking a key step towards integrating emerging real estate leaders from the National Capital Region with the national platform. The initiative aims to promote sustainable and responsible urban development through collaboration and knowledge exchange.The event brought together young developers, entrepreneurs, and professionals from across NCR, including Noida, Gurugram, Ghaziabad, Faridabad, Bhiwadi, and Meerut. Discussions focused on urban development, finance, sustainability, innovation, and policy, emphasisi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement