All-Weather Road To Kishtwar To Open In April 2027
ROADS & HIGHWAYS

All-Weather Road To Kishtwar To Open In April 2027

The long wait of people in Marwah, Warwan and parts of Dachhan for an all weather road linking Nowpachi with district headquarters Kishtwar is due to end in April 2027, officials said. More than 75,000 people are expected to benefit as authorities plan to complete two remaining bridges and a short rocky stretch to finish the link.

Officials estimate the new route will cut the distance to Kishtwar by about 177 km compared with the fair weather road via Margan Top, reducing a 280 km journey to roughly 103 km and cutting travel time from about 10 to 11 hours to around four hours. The link is intended to provide year round access that previously existed only for five months.

Work progressed unevenly over decades with sections completed in phases and long pauses in activity. A contractor abandoned the job for two to three years before district authorities pressed for resumption and material was mobilised at critical sites. Agencies now report focused efforts on the remaining stretches and supervision has been stepped up to accelerate completion.

The final stretch covers about 13 km, including roughly two km of hard rock that needs blasting, and two major bridges remain. The Suid bridge will be a steel girder structure with a 35 m span and one embankment is complete; authorities expect its completion in about three months. The Sirshi bridge at Pakkal will have a 58 m span and is due by the end of March 2027.

Project accounts show the 22 km package still needs protection work, surfacing and the two bridges at a value of Rs 222.1 mn while Package I totals Rs 255.8 mn; the remaining package is Rs 121.6 mn. Engineers said contractors have been instructed to follow PMGSY standards and that, subject to the remaining works, the road should be operational in April 2027.

The long wait of people in Marwah, Warwan and parts of Dachhan for an all weather road linking Nowpachi with district headquarters Kishtwar is due to end in April 2027, officials said. More than 75,000 people are expected to benefit as authorities plan to complete two remaining bridges and a short rocky stretch to finish the link. Officials estimate the new route will cut the distance to Kishtwar by about 177 km compared with the fair weather road via Margan Top, reducing a 280 km journey to roughly 103 km and cutting travel time from about 10 to 11 hours to around four hours. The link is intended to provide year round access that previously existed only for five months. Work progressed unevenly over decades with sections completed in phases and long pauses in activity. A contractor abandoned the job for two to three years before district authorities pressed for resumption and material was mobilised at critical sites. Agencies now report focused efforts on the remaining stretches and supervision has been stepped up to accelerate completion. The final stretch covers about 13 km, including roughly two km of hard rock that needs blasting, and two major bridges remain. The Suid bridge will be a steel girder structure with a 35 m span and one embankment is complete; authorities expect its completion in about three months. The Sirshi bridge at Pakkal will have a 58 m span and is due by the end of March 2027. Project accounts show the 22 km package still needs protection work, surfacing and the two bridges at a value of Rs 222.1 mn while Package I totals Rs 255.8 mn; the remaining package is Rs 121.6 mn. Engineers said contractors have been instructed to follow PMGSY standards and that, subject to the remaining works, the road should be operational in April 2027.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Suzuki Targets 4 mn Units in India by FY30, Builds Global Hub

Suzuki Motor Corporation plans to raise annual production capacity in India to approximately 4 mn units from fiscal 2030, strengthening the country’s role as a manufacturing and export hub for its global operations. The Japanese car maker announced the target as part of its Technology Strategy 2026, which outlines its development and manufacturing priorities for the coming decade. The company also aims to improve development efficiency by 30 per cent from the FY20 level and manufacturing efficiency by 50 per cent by FY30. It plans to halve the lead time required to develop new vehicles by im..

Next Story
Infrastructure Transport

Ayodhya Airport to Add Flights to Delhi, Bengaluru and Mumbai

Ayodhya airport will get additional direct air services to Delhi and Bengaluru from October 1, followed by a daily non-stop connection to Mumbai from October 30. The existing IndiGo service to Hyderabad is also being prepared for conversion into a daily operation, widening travel options from the temple city. Passengers travelling to Delhi will have two direct options at different times of day from October 1. Akasa Air flight QP 1608 will depart Ayodhya at 12:50 pm and arrive in Delhi at 2:20 pm, while Air India Express flight IX 1274 will leave at 2:10 pm and reach the capital at 3:45 pm. Ind..

Next Story
Infrastructure Urban

Cement Prices Rise Again in Himachal Pradesh

Cement prices in Himachal Pradesh have increased for the second time this month, raising construction expenses for households, contractors and other consumers. Cement companies raised rates by Rs. 5 per bag on Friday, 10 days after a similar increase was implemented on September 15. The two revisions have lifted prices by a total of Rs. 10 per bag within 10 days. Dealers Pawan, Rohit, Manoj and Rakesh said the latest rates were being applied across the market, adding to the financial pressure on people building or renovating homes. ACC Suraksha cement is now priced at Rs. 425 per bag, compared..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code