+
Carnac Bridge to Reopen By 10 June After Delay
ROADS & HIGHWAYS

Carnac Bridge to Reopen By 10 June After Delay

Mumbai’s historic Carnac Bridge, a vital link connecting South Mumbai to the eastern suburbs, is now on course for completion by 10 June 2025, despite recent construction delays.

The Brihanmumbai Municipal Corporation (BMC) resumed work after a 15-day setback due to the delayed arrival of essential steel girders. The contractor responsible has been fined Rs 18 million for failing to meet the original delivery deadline of 30 April. Penalties were imposed at Rs 1 million per day from 1 to 2 May, increasing to Rs 2 million per day from 3 to 10 May. To speed up progress, BMC deployed engineers to the contractor’s plant in Daman to supervise fabrication and dispatch.

All 30 steel girders are now on-site, and installation has begun. These will support both the main bridge and its approach roads. Once fitted, work will progress to surface levelling and final road-laying. The BMC is prioritising pre-monsoon completion, citing the bridge’s role in easing traffic flow across South Mumbai.

The new four-lane structure replaces the original two-lane bridge, allowing for greater vehicle capacity and improved connectivity between P D’Mello Road and the Eastern Freeway. The original Carnac Bridge, built in 1866, was deemed unsafe and dismantled in 2022.

This reconstruction reflects BMC’s commitment to modernising the city’s infrastructure. Officials have warned that delays beyond 10 June could cause significant disruption due to the monsoon. The timely opening of the upgraded bridge is crucial for decongesting the area and reinforcing Mumbai’s east–west traffic corridors.

The BMC’s imposition of penalties and on-site monitoring highlight a focused approach to urban development and public safety.

Mumbai’s historic Carnac Bridge, a vital link connecting South Mumbai to the eastern suburbs, is now on course for completion by 10 June 2025, despite recent construction delays.The Brihanmumbai Municipal Corporation (BMC) resumed work after a 15-day setback due to the delayed arrival of essential steel girders. The contractor responsible has been fined Rs 18 million for failing to meet the original delivery deadline of 30 April. Penalties were imposed at Rs 1 million per day from 1 to 2 May, increasing to Rs 2 million per day from 3 to 10 May. To speed up progress, BMC deployed engineers to the contractor’s plant in Daman to supervise fabrication and dispatch.All 30 steel girders are now on-site, and installation has begun. These will support both the main bridge and its approach roads. Once fitted, work will progress to surface levelling and final road-laying. The BMC is prioritising pre-monsoon completion, citing the bridge’s role in easing traffic flow across South Mumbai.The new four-lane structure replaces the original two-lane bridge, allowing for greater vehicle capacity and improved connectivity between P D’Mello Road and the Eastern Freeway. The original Carnac Bridge, built in 1866, was deemed unsafe and dismantled in 2022.This reconstruction reflects BMC’s commitment to modernising the city’s infrastructure. Officials have warned that delays beyond 10 June could cause significant disruption due to the monsoon. The timely opening of the upgraded bridge is crucial for decongesting the area and reinforcing Mumbai’s east–west traffic corridors.The BMC’s imposition of penalties and on-site monitoring highlight a focused approach to urban development and public safety.

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App