+
Carnac Bridge to Reopen By 10 June After Delay
ROADS & HIGHWAYS

Carnac Bridge to Reopen By 10 June After Delay

Mumbai’s historic Carnac Bridge, a vital link connecting South Mumbai to the eastern suburbs, is now on course for completion by 10 June 2025, despite recent construction delays.

The Brihanmumbai Municipal Corporation (BMC) resumed work after a 15-day setback due to the delayed arrival of essential steel girders. The contractor responsible has been fined Rs 18 million for failing to meet the original delivery deadline of 30 April. Penalties were imposed at Rs 1 million per day from 1 to 2 May, increasing to Rs 2 million per day from 3 to 10 May. To speed up progress, BMC deployed engineers to the contractor’s plant in Daman to supervise fabrication and dispatch.

All 30 steel girders are now on-site, and installation has begun. These will support both the main bridge and its approach roads. Once fitted, work will progress to surface levelling and final road-laying. The BMC is prioritising pre-monsoon completion, citing the bridge’s role in easing traffic flow across South Mumbai.

The new four-lane structure replaces the original two-lane bridge, allowing for greater vehicle capacity and improved connectivity between P D’Mello Road and the Eastern Freeway. The original Carnac Bridge, built in 1866, was deemed unsafe and dismantled in 2022.

This reconstruction reflects BMC’s commitment to modernising the city’s infrastructure. Officials have warned that delays beyond 10 June could cause significant disruption due to the monsoon. The timely opening of the upgraded bridge is crucial for decongesting the area and reinforcing Mumbai’s east–west traffic corridors.

The BMC’s imposition of penalties and on-site monitoring highlight a focused approach to urban development and public safety.

Mumbai’s historic Carnac Bridge, a vital link connecting South Mumbai to the eastern suburbs, is now on course for completion by 10 June 2025, despite recent construction delays.The Brihanmumbai Municipal Corporation (BMC) resumed work after a 15-day setback due to the delayed arrival of essential steel girders. The contractor responsible has been fined Rs 18 million for failing to meet the original delivery deadline of 30 April. Penalties were imposed at Rs 1 million per day from 1 to 2 May, increasing to Rs 2 million per day from 3 to 10 May. To speed up progress, BMC deployed engineers to the contractor’s plant in Daman to supervise fabrication and dispatch.All 30 steel girders are now on-site, and installation has begun. These will support both the main bridge and its approach roads. Once fitted, work will progress to surface levelling and final road-laying. The BMC is prioritising pre-monsoon completion, citing the bridge’s role in easing traffic flow across South Mumbai.The new four-lane structure replaces the original two-lane bridge, allowing for greater vehicle capacity and improved connectivity between P D’Mello Road and the Eastern Freeway. The original Carnac Bridge, built in 1866, was deemed unsafe and dismantled in 2022.This reconstruction reflects BMC’s commitment to modernising the city’s infrastructure. Officials have warned that delays beyond 10 June could cause significant disruption due to the monsoon. The timely opening of the upgraded bridge is crucial for decongesting the area and reinforcing Mumbai’s east–west traffic corridors.The BMC’s imposition of penalties and on-site monitoring highlight a focused approach to urban development and public safety.

Next Story
Infrastructure Energy

Bihar Launches Rs 53.4 Billion Green Energy Plan

The Bihar government has taken a major stride towards clean energy with the launch of two new policies and the signing of agreements totalling Rs 53.4 billion. These initiatives aim to generate 2,357 megawatts (MW) of renewable energy through solar, wind, battery storage, and other sustainable technologies.The Bihar Renewable Energy Policy 2025 and the Pump Storage Policy 2025 were officially introduced at an event in Patna. Designed to attract significant investment, the policies seek to position Bihar as a key centre for clean energy projects. Energy Minister Bijendra Prasad Yadav stated tha..

Next Story
Infrastructure Transport

Bids Invited for Rs 62.5 Billion Vizag Metro Project

The long-anticipated Visakhapatnam Metro Project has made significant progress, with the Andhra Pradesh Metro Rail Corporation inviting bids for the first civil contract under Phase 1 of the Vizag Metro. The estimated cost of this contract is Rs 62.5 billion.This engineering, procurement and construction (EPC) contract covers the design and construction of a 46.23 km viaduct spanning three corridors, including a 20.16 km double-decker four-lane flyover cum metro viaduct. The project also comprises 42 elevated metro stations across Visakhapatnam.Recently, SYSTRA Consultancy signed a Memorandum ..

Next Story
Real Estate

Oberoi Realty to Buy Hotel Horizon for Rs 9.19 Billion

A consortium led by Mumbai-listed Oberoi Realty Ltd is set to acquire debt-laden Hotel Horizon Pvt Ltd in Juhu, Mumbai for Rs 9.19 billion (approximately USD 107 million) under a resolution plan approved through India’s Insolvency and Bankruptcy Code (IBC).In a filing to the stock exchange, Oberoi Realty confirmed that the Committee of Creditors of Hotel Horizon had approved the resolution plan, following which a letter of intent was issued. The consortium also includes Shree Naman Developers and JM Financial Properties.As per the resolution plan, the consortium will make a payment of Rs 9.1..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?