Marine Drive - Worli Section To Be Ready By November
ROADS & HIGHWAYS

Marine Drive - Worli Section To Be Ready By November

The first phase of the Mumbai coastal road project, from Marine Drive to Worli, is scheduled to be finished in November 2023. The Brihanmumbai Municipal Corporation (BMC) is building the first phase of the coastal road at a cost of Rs 12,500 crore to speed up suburban commutes to and from South Mumbai.

BMC aimed to open Phase I, a 10.58-kilometre stretch from Marine Drive to Worli in south Mumbai, by November, said BMC head engineer Mantayya Swami. The ambitious coastal road project (phase 1), when finished, will provide an 8.5 km long and 20-metre wide sea promenade to the city between Priyadarshini Park on Napean Sea Road and the Worli side of the Bandra Worli Sea Link.

The project will be built in two stages. The second phase entails linking the Bandra Sea Link to the Kandivali Junction. Construction on this stretch is yet to commence.

While Larsen and Toubro is completing Packages 1 and 4 of the coastal road at a cost of Rs 7,489 crore, Hindustan Construction Company (HCC) and Hyundai Development Company (45%) are completing Packages 2 and 3 at a cost of Rs 2,126 crore.

The first phase of the Mumbai coastal road project, from Marine Drive to Worli, is scheduled to be finished in November 2023. The Brihanmumbai Municipal Corporation (BMC) is building the first phase of the coastal road at a cost of Rs 12,500 crore to speed up suburban commutes to and from South Mumbai.

BMC aimed to open Phase I, a 10.58-kilometre stretch from Marine Drive to Worli in south Mumbai, by November, said BMC head engineer Mantayya Swami.

The ambitious coastal road project (phase 1), when finished, will provide an 8.5 km long and 20-metre wide sea promenade to the city between Priyadarshini Park on Napean Sea Road and the Worli side of the Bandra Worli Sea Link.

The project is to be constructed in two phases. The second phase involves connecting Bandra Sea Link to Kandivali Junction. Work on this stretch is yet to commence.

While Larsen and Toubro is executing Package 1 and 4 of the coastal road at Rs 7,489 crore, a joint venture between Hindustan Construction Company (HCC) and Hyundai Development Company (45 per cent) is executing Package 2 and 3 at the cost of Rs 2,126 crore.

Also Read
Belgavi receives projects worth more than Rs 2,700 crore
Jai Balaji Inds to enter into cement biz

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

The first phase of the Mumbai coastal road project, from Marine Drive to Worli, is scheduled to be finished in November 2023. The Brihanmumbai Municipal Corporation (BMC) is building the first phase of the coastal road at a cost of Rs 12,500 crore to speed up suburban commutes to and from South Mumbai. BMC aimed to open Phase I, a 10.58-kilometre stretch from Marine Drive to Worli in south Mumbai, by November, said BMC head engineer Mantayya Swami. The ambitious coastal road project (phase 1), when finished, will provide an 8.5 km long and 20-metre wide sea promenade to the city between Priyadarshini Park on Napean Sea Road and the Worli side of the Bandra Worli Sea Link. The project will be built in two stages. The second phase entails linking the Bandra Sea Link to the Kandivali Junction. Construction on this stretch is yet to commence. While Larsen and Toubro is completing Packages 1 and 4 of the coastal road at a cost of Rs 7,489 crore, Hindustan Construction Company (HCC) and Hyundai Development Company (45%) are completing Packages 2 and 3 at a cost of Rs 2,126 crore. The first phase of the Mumbai coastal road project, from Marine Drive to Worli, is scheduled to be finished in November 2023. The Brihanmumbai Municipal Corporation (BMC) is building the first phase of the coastal road at a cost of Rs 12,500 crore to speed up suburban commutes to and from South Mumbai. BMC aimed to open Phase I, a 10.58-kilometre stretch from Marine Drive to Worli in south Mumbai, by November, said BMC head engineer Mantayya Swami. The ambitious coastal road project (phase 1), when finished, will provide an 8.5 km long and 20-metre wide sea promenade to the city between Priyadarshini Park on Napean Sea Road and the Worli side of the Bandra Worli Sea Link. The project is to be constructed in two phases. The second phase involves connecting Bandra Sea Link to Kandivali Junction. Work on this stretch is yet to commence. While Larsen and Toubro is executing Package 1 and 4 of the coastal road at Rs 7,489 crore, a joint venture between Hindustan Construction Company (HCC) and Hyundai Development Company (45 per cent) is executing Package 2 and 3 at the cost of Rs 2,126 crore. Also Read Belgavi receives projects worth more than Rs 2,700 crore Jai Balaji Inds to enter into cement biz

Next Story
Infrastructure Transport

Uttar Pradesh unveils infrastructure-led growth roadmap at RAHSTA

Mumbai, 9 July 2026: Uttar Pradesh’s ambitious infrastructure-led growth strategy took centre stage on Day 2 of the 16th RAHSTA Expo, where senior government officials outlined how expressways, industrial corridors and technology-driven governance are transforming the state into one of India's most attractive investment destinations.Delivering the keynote address, Srihari Pratap Shahi, IAS, Additional Chief Executive Officer, Uttar Pradesh Expressways Industrial Development Authority (UPEIDA), highlighted the state's long-term vision of integrating world-class expressways with industrial dev..

Next Story
Real Estate

NCW closes PRIME Offices Fund at Rs 40 billion

Nuvama and Cushman & Wakefield Management (NCW) has announced the final close of its flagship PRIME Offices Fund at approximately Rs 40 billion, exceeding its original target of Rs 30 billion following strong investor demand.The fund was launched to provide Indian investors with access to institutional-grade commercial office assets across key office markets in the country. According to NCW, the increase in the fund size was supported by strong investor participation and the availability of investment opportunities in India's office sector.The fund has already committed around 45 per cent ..

Next Story
Real Estate

Mayfair Housing adopts Autodesk Forma for digital project planning

Mayfair Housing has entered into a three-year strategic partnership with Autodesk to deploy Autodesk Forma, an AI-enabled cloud platform, as part of its digital transformation programme aimed at improving project planning and execution across its development and redevelopment portfolio.The platform will be integrated into the company's Building Information Modelling (BIM) workflow to support architects, planners and project teams during the early stages of design and development. Autodesk Forma combines real-world data, environmental simulations and collaborative workflows to facilitate data-d..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement