MMRDA to assist MBMC in road concrete work
ROADS & HIGHWAYS

MMRDA to assist MBMC in road concrete work

The Mumbai Metropolitan Region Development Authority (MMRDA) announced its intention to assist the Mira-Bhayandar Municipal Corporation (MBMC) in the concretization of approximately 22 kilometres of internal and arterial roads within the twin city. The project, estimated at a cost of Rs 3.16 billion, is scheduled to span two years.

Prior to the outbreak of Covid, the MBMC had initiated the process of converting all roads falling under its jurisdiction from bituminous or unpaved surfaces to concrete ones. However, they were only able to complete one-third of the 236-kilometre-long stretch. Consequently, the MMRDA has offered its support.

According to an official, the plan for road improvement and concretization is divided into four packages. The first package will encompass 12 roads, totalling 5.304 kilometres, located in ward 2. The second phase will include 11 roads, with a combined length of 4.367 kilometres, situated in wards 2 and 4. The third part of the plan consists of 14 roads, measuring 6.385 kilometres, while the final package comprises a dozen roads with a cumulative length of 5.751 kilometres, located in wards 4 and 5.

The civic area spans 79.4 square kilometres, with approximately 18.73% of the total network, equivalent to 14.9 square kilometres, designated by the government as areas under the special planning authority.

Also read: 
Bhopal cabinet approves major infrastructure projects
NHAI's project awarding and asset monetisation updates for FY24


The Mumbai Metropolitan Region Development Authority (MMRDA) announced its intention to assist the Mira-Bhayandar Municipal Corporation (MBMC) in the concretization of approximately 22 kilometres of internal and arterial roads within the twin city. The project, estimated at a cost of Rs 3.16 billion, is scheduled to span two years. Prior to the outbreak of Covid, the MBMC had initiated the process of converting all roads falling under its jurisdiction from bituminous or unpaved surfaces to concrete ones. However, they were only able to complete one-third of the 236-kilometre-long stretch. Consequently, the MMRDA has offered its support. According to an official, the plan for road improvement and concretization is divided into four packages. The first package will encompass 12 roads, totalling 5.304 kilometres, located in ward 2. The second phase will include 11 roads, with a combined length of 4.367 kilometres, situated in wards 2 and 4. The third part of the plan consists of 14 roads, measuring 6.385 kilometres, while the final package comprises a dozen roads with a cumulative length of 5.751 kilometres, located in wards 4 and 5. The civic area spans 79.4 square kilometres, with approximately 18.73% of the total network, equivalent to 14.9 square kilometres, designated by the government as areas under the special planning authority. Also read:  Bhopal cabinet approves major infrastructure projectsNHAI's project awarding and asset monetisation updates for FY24

Next Story
Infrastructure Urban

MoHUA Plans New Role for Smart City SPVs

In a significant policy move, the Ministry of Housing and Urban Affairs (MoHUA) has issued an advisory encouraging the continued use and repurposing of Special Purpose Vehicles (SPVs) formed under the Smart Cities Mission (SCM). This marks a step toward sustaining urban transformation by leveraging institutional capabilities and infrastructure developed over the past decade.Initiated in 2015, the Smart Cities Mission introduced a new era of urban planning in India, with each of the 100 selected cities forming SPVs under the Companies Act, 2013. These entities, jointly owned by state government..

Next Story
Infrastructure Urban

ADB Approves $110 Million Loan to Boost Skills in Gujarat

The Asian Development Bank (ADB) has approved a USD 109.97 million (Rs 9.27 billion) results-based loan to support Gujarat’s efforts to become a global industrial hub by developing a future-ready, skilled workforce.The funding will back the Gujarat skills development programme, led by the Department of Labour, Skill Development and Employment in collaboration with Kaushalya: The Skill University (KSU). The initiative aims to equip the workforce with advanced, industry-aligned skills to meet rising employment demand in high-growth sectors.According to ADB, the programme seeks to strengthen in..

Next Story
Infrastructure Urban

SDAL Tests Rudrastra UAV and Bhargavastra Defence System

Solar Defence and Aerospace Limited (SDAL) has successfully completed a key flight test of its indigenous Hybrid VTOL UAV Rudrastra at the Pokharan Firing Range, aligning with Indian Army performance benchmarks for mission adaptability, high endurance, precision engagement, and vertical take-off and landing (VTOL) capability.The trial marks a notable achievement in India’s Aatmanirbhar Bharat initiative, underscoring advancements in home-grown military technology. The Rudrastra UAV demonstrated a mission radius exceeding 50 km with uninterrupted video relay, a total operational range of over..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?