NHAI Targets Pre-Monsoon Completion of Kuloor Six-Lane Bridge
ROADS & HIGHWAYS

NHAI Targets Pre-Monsoon Completion of Kuloor Six-Lane Bridge

National Highways Authority of India has said it is confident that the long-delayed Kuloor six-lane bridge on National Highway 66 will be completed before the onset of the monsoon this year, provided construction activity is stepped up immediately. Officials warned that any slippage beyond June could push completion back by another year.

The bridge is being constructed across the Phalguni River at Kuloor, between two existing old bridges. The project has been awarded to Pune-based Shinde Developers. Although the work order was issued in April 2021 and completion was originally scheduled for October 2022, the project has faced delays of nearly three years, largely due to financial constraints faced earlier by the contractor.

Officials said work has since resumed, but progress remains slower than required. At present, six pillars have been constructed, with pier cap work underway. Five pier caps have been completed, while work on the sixth is expected to be finished in the coming days.

Once pier cap construction is completed, girder launching will begin. A total of 60 girders have already been manufactured and are currently stored at the Baikampady yard. Girder launching work, which is yet to commence, is expected to take up to four months and has been identified as a critical activity requiring accelerated execution.

The new bridge will have a total width of 41 metres, with a 28-metre-wide main carriageway accommodating six lanes of traffic. A seven-metre-wide service road will also be provided. After the bridge is opened to traffic, the existing old arch bridge will be permanently closed. A new service road and footpath will be developed alongside the old bridge, adjacent to the new structure. Officials said work on the service road can begin only after completion of the main carriageway, as pipeline relocation near the old bridge is required.

Connectivity-wise, the six-lane bridge will link to the highway near the old NMPT lighthouse on the Panambur highway side. On the opposite end, it will connect to the existing flyover through a curved alignment.

Brijesh Chowta recently reviewed the project with NHAI officials and urged them to complete the remaining work within four months. NHAI has directed the contractor to ensure that construction is completed before the monsoon season.

According to the revised schedule, the project is now expected to be completed by May 31, 2026, subject to timely completion of girder launching and associated works.

National Highways Authority of India has said it is confident that the long-delayed Kuloor six-lane bridge on National Highway 66 will be completed before the onset of the monsoon this year, provided construction activity is stepped up immediately. Officials warned that any slippage beyond June could push completion back by another year. The bridge is being constructed across the Phalguni River at Kuloor, between two existing old bridges. The project has been awarded to Pune-based Shinde Developers. Although the work order was issued in April 2021 and completion was originally scheduled for October 2022, the project has faced delays of nearly three years, largely due to financial constraints faced earlier by the contractor. Officials said work has since resumed, but progress remains slower than required. At present, six pillars have been constructed, with pier cap work underway. Five pier caps have been completed, while work on the sixth is expected to be finished in the coming days. Once pier cap construction is completed, girder launching will begin. A total of 60 girders have already been manufactured and are currently stored at the Baikampady yard. Girder launching work, which is yet to commence, is expected to take up to four months and has been identified as a critical activity requiring accelerated execution. The new bridge will have a total width of 41 metres, with a 28-metre-wide main carriageway accommodating six lanes of traffic. A seven-metre-wide service road will also be provided. After the bridge is opened to traffic, the existing old arch bridge will be permanently closed. A new service road and footpath will be developed alongside the old bridge, adjacent to the new structure. Officials said work on the service road can begin only after completion of the main carriageway, as pipeline relocation near the old bridge is required. Connectivity-wise, the six-lane bridge will link to the highway near the old NMPT lighthouse on the Panambur highway side. On the opposite end, it will connect to the existing flyover through a curved alignment. Brijesh Chowta recently reviewed the project with NHAI officials and urged them to complete the remaining work within four months. NHAI has directed the contractor to ensure that construction is completed before the monsoon season. According to the revised schedule, the project is now expected to be completed by May 31, 2026, subject to timely completion of girder launching and associated works.

Next Story
Infrastructure Urban

Implementation Status of Jal Jeevan Mission

Since August 2019 the Government has implemented Jal Jeevan Mission to provide assured potable water through household tap connections in rural India. At the start of the mission only 32.3 million (mn) rural households, representing 16.7 per cent, were reported to have tap water connections. States and union territories have reported that 125.8 mn additional rural households have since been provided with tap connections. As a result, of about 193.6 mn rural households roughly 158.2 mn, or 81.71 per cent, are reported to have tap water supply at home.\n\nThe State, district and village level st..

Next Story
Infrastructure Urban

Jal Jeevan Mission Reaches Eighty One Per Cent Rural Coverage

The Government reported substantial progress under the Jal Jeevan Mission, launched in August 2019 to provide tap water to every rural household. At launch only 32.3 million (mn) rural households had tap connections and states and Union territories reported provision of 125.8 mn additional households by March 2026. Consequently, out of about 193.6 mn rural households around 158.2 mn, or 81.71 per cent, are reported to have tap water at home. The Finance Minister announced extension of the mission until 2028 in the 2025-26 budget speech. The Swachh Bharat Mission Grameen, launched in October 20..

Next Story
Infrastructure Urban

Empowering Local Governance for Sustainable Rural Water Supply

The Ministry of Jal Shakti has aligned the Jal Jeevan Mission (JJM) with the 73rd Amendment to strengthen village level planning and community ownership of water supply. Gram Panchayats, village water and sanitation committees and Pani Samitis are to plan, implement, manage and maintain piped water systems, with gram sabha processes formalising handover and oversight. Implementation support agencies including non government organisations, community based organisations and self help groups have been empanelled to train local committees and promote women participation. Under JJM, the department ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement