NHAI Tightens Contractor Rules To Boost Highway Projects
ROADS & HIGHWAYS

NHAI Tightens Contractor Rules To Boost Highway Projects

The National Highways Authority of India (NHAI) has strengthened contractor eligibility and compliance norms to enhance execution quality, reduce delays, and lower lifecycle costs of highway projects. The reforms follow concerns over misrepresentation of credentials, unauthorised subcontracting, and weak financial accountability in ongoing projects.
A key clarification addresses the qualification criterion of “Similar Work.” Previously, some bidders cited minor or peripheral works to claim eligibility for large projects. NHAI now specifies that only completed highway projects with all major components comparable to the tendered project will count.
Subcontracting rules have also been tightened. Officials reported instances where concessionaires engaged contractors without prior approval or exceeded limits in EPC, HAM, and BOT projects, undermining quality and timelines. Such deviations will now be classified as “Undesirable Practices” and will attract penalties equivalent to fraudulent behaviour.
Financial compliance has been strengthened with a ban on third-party bid and performance securities. Only guarantees backed directly by the bidder or its approved affiliates will be accepted, improving transparency and enforceability.
The Ministry of Road Transport and Highways stated that these measures are aimed at instilling greater discipline in contract execution and safeguarding the integrity of India’s highway development programme. 

The National Highways Authority of India (NHAI) has strengthened contractor eligibility and compliance norms to enhance execution quality, reduce delays, and lower lifecycle costs of highway projects. The reforms follow concerns over misrepresentation of credentials, unauthorised subcontracting, and weak financial accountability in ongoing projects.A key clarification addresses the qualification criterion of “Similar Work.” Previously, some bidders cited minor or peripheral works to claim eligibility for large projects. NHAI now specifies that only completed highway projects with all major components comparable to the tendered project will count.Subcontracting rules have also been tightened. Officials reported instances where concessionaires engaged contractors without prior approval or exceeded limits in EPC, HAM, and BOT projects, undermining quality and timelines. Such deviations will now be classified as “Undesirable Practices” and will attract penalties equivalent to fraudulent behaviour.Financial compliance has been strengthened with a ban on third-party bid and performance securities. Only guarantees backed directly by the bidder or its approved affiliates will be accepted, improving transparency and enforceability.The Ministry of Road Transport and Highways stated that these measures are aimed at instilling greater discipline in contract execution and safeguarding the integrity of India’s highway development programme. 

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App