Our team kept challenging itself and achieved significant milestones
The timely completion of such a mega project has been achieved by L&T despite challenges like adverse climatic conditions and the COVID-19 pandemic, which disrupted our global supply chain and availability of workforce. Since inception, the project team kept challenging itself and achieved significant milestones. Starting with the pile foundation works in 2018, the team began the first superstructure concrete span erection works in February 2020.
Tell us about orthotropic steel deck (OSD) technology.
A first-of-its-kind engineering feat in India, OSD span erection works began in January 2022 and about 38 OSD spans (85 to 180 m) were erected within a challenging 15 months, including three non-working months in the monsoon.
To read the full story, CLICK HERE.
- SD Patil
- MTHL Project
- L&T
- global supply chain
- first superstructure concrete
- steel deck technology
- marine construction challenge
- infrastructure
- Logistics
- Severe climatic conditions
- Nava Sheva port
- Navi Mumbai International Airport and Jawaharlal Nehru Port Trust
- India’s longest bridge
- High-strength concrete
- tune mass dampeners
- Nava Sheva port
- Sewri Worli elevated corridor
Please take us through the iconic project’s timeline since inception.The timely completion of such a mega project has been achieved by L&T despite challenges like adverse climatic conditions and the COVID-19 pandemic, which disrupted our global supply chain and availability of workforce. Since inception, the project team kept challenging itself and achieved significant milestones. Starting with the pile foundation works in 2018, the team began the first superstructure concrete span erection works in February 2020.Tell us about orthotropic steel deck (OSD) technology.A first-of-its-kind engineering feat in India, OSD span erection works began in January 2022 and about 38 OSD spans (85 to 180 m) were erected within a challenging 15 months, including three non-working months in the monsoon.To read the full story, CLICK HERE.