Over 670 Road Projects behind schedule, Minister informs Parliament
ROADS & HIGHWAYS

Over 670 Road Projects behind schedule, Minister informs Parliament

According to a statement made by Minister for Road, Transport and Highways, Nitin Gadkari, in the Lok Sabha, there are a total of 1,612 road projects currently under construction across the country, including in Tamil Nadu, as of June 30, 2023. Out of these, 674 projects have experienced delays in their original schedules due to various reasons.

However, Minister Gadkari clarified that not all of the delayed projects are subject to cost escalation. The payment for price escalation is based on the contract conditions, and the actual amount of such escalation and any increase in project cost can only be determined upon the project's actual completion and final settlement of bills.

In cases where the delay can be attributed to the contractor, penalties are imposed, and price escalation is not paid. Therefore, there is no additional cost incurred due to such delays.

To ensure efficient progress, the ministry actively monitors the national highway projects in close collaboration with project implementing agencies, state governments, and contractors/developers. Periodic reviews of the projects are conducted at various levels, and several measures are implemented to enhance the liquidity of funds available to contractors/developers and expedite the project's progress.

According to a statement made by Minister for Road, Transport and Highways, Nitin Gadkari, in the Lok Sabha, there are a total of 1,612 road projects currently under construction across the country, including in Tamil Nadu, as of June 30, 2023. Out of these, 674 projects have experienced delays in their original schedules due to various reasons.However, Minister Gadkari clarified that not all of the delayed projects are subject to cost escalation. The payment for price escalation is based on the contract conditions, and the actual amount of such escalation and any increase in project cost can only be determined upon the project's actual completion and final settlement of bills.In cases where the delay can be attributed to the contractor, penalties are imposed, and price escalation is not paid. Therefore, there is no additional cost incurred due to such delays.To ensure efficient progress, the ministry actively monitors the national highway projects in close collaboration with project implementing agencies, state governments, and contractors/developers. Periodic reviews of the projects are conducted at various levels, and several measures are implemented to enhance the liquidity of funds available to contractors/developers and expedite the project's progress.

Next Story
Real Estate

Omaxe to Develop 450-Acre Township in Indore’s Super Corridor

Omaxe has announced a major expansion in Madhya Pradesh with the acquisition of 450 acres along Indore’s Super Corridor for a modern integrated township. The company will invest Rs 12 billion in the multi-phase project, which is expected to generate Rs 25 billion in revenue over three years.  The development will include residential clusters, commercial and retail zones, schools, healthcare facilities, parks, and green mobility infrastructure. The township aims to support the region’s urban growth and rising infrastructure demand, especially with metro connectivity and major road..

Next Story
Infrastructure Energy

India’s First CBG Plant with Steel Pipeline Integration Launched

CEID Consultants and Engineering has successfully commissioned India’s first Compressed Biogas (CBG) plant integrated via a steel pipeline into a City Gas Distribution (CGD) network. Located in Batala, Gurdaspur (Punjab), the MEPL Bio-energy facility now directly supplies CBG into Gujarat Gas’ grid, eliminating the need for cylinder-based cascade transport and significantly lowering logistics costs. This breakthrough comes after CEID’s earlier deployment of MDPE pipeline offtake at the same plant. The steel pipeline marks a new industry benchmark, enabling continuous, real-time and ..

Next Story
Real Estate

Mittal Builders Plans Landmark Township to Transform Naigaon

Mittal Builders has unveiled a bold urban vision to transform Naigaon into a landmark micro-market in western Mumbai, with plans to unlock 6.5 million sq. ft. of development potential across a 70-acre land parcel. The long-term multi-phase plan has an estimated gross development value (GDV) of over Rs 80 billion. As part of this initiative, Mittal Builders has signed a joint development agreement with The House of Abhinandan Lodha (HoABL) to co-develop a 3 million sq. ft. integrated township, comprising over 4,600 apartments and high-street retail. With a planned investment of Rs 20 billi..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?