+
Kochi Metro Phase II faces delays over land acquisition
RAILWAYS & METRO RAIL

Kochi Metro Phase II faces delays over land acquisition

The Kochi Metro Rail Limited's (KMRL) Phase II expansion, connecting JLN Stadium to Kakkanad, has been delayed due to prolonged land acquisition processes. Revenue authorities have extended the validity of the 11(1) land acquisition notification by six months, delaying the issuance of the 19(1) notification for several key stations. While the 11(1) notification has been issued for stations at Palarivattom, Kakkanad, CSEZ, Chitethukara, and Kinfra, only CSEZ and Chitethukara have moved forward with the 19(1) notification. According to the revenue department's order, the notification's validity has been extended until April 2025 for stations along the 11.2 km route. Construction activities had begun in September, including piling works for the viaduct and CEZ Metro station. KMRL initially projected completion of the project within 20 months and had undertaken preparatory work, including soil tests and topographical surveys, along the route. The proposed line will include new stations at Palarivattom Junction, Palarivattom Bypass, Chembumukku, Vazhakkala, Padamughal, Kakkanad Junction, Cochin SEZ, Chittethukara, KINFRA, and InfoPark. However, disputes over land ownership have caused setbacks, slowing the progress of this critical infrastructure project. (ET)

The Kochi Metro Rail Limited's (KMRL) Phase II expansion, connecting JLN Stadium to Kakkanad, has been delayed due to prolonged land acquisition processes. Revenue authorities have extended the validity of the 11(1) land acquisition notification by six months, delaying the issuance of the 19(1) notification for several key stations. While the 11(1) notification has been issued for stations at Palarivattom, Kakkanad, CSEZ, Chitethukara, and Kinfra, only CSEZ and Chitethukara have moved forward with the 19(1) notification. According to the revenue department's order, the notification's validity has been extended until April 2025 for stations along the 11.2 km route. Construction activities had begun in September, including piling works for the viaduct and CEZ Metro station. KMRL initially projected completion of the project within 20 months and had undertaken preparatory work, including soil tests and topographical surveys, along the route. The proposed line will include new stations at Palarivattom Junction, Palarivattom Bypass, Chembumukku, Vazhakkala, Padamughal, Kakkanad Junction, Cochin SEZ, Chittethukara, KINFRA, and InfoPark. However, disputes over land ownership have caused setbacks, slowing the progress of this critical infrastructure project. (ET)

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App