Saarstahl Rail to Supply Tracks for Bengaluru Suburban Rail Project
RAILWAYS & METRO RAIL

Saarstahl Rail to Supply Tracks for Bengaluru Suburban Rail Project

Rail Infrastructure Development Company Karnataka Limited (K-RIDE) has identified Saarstahl Rail as the lowest bidder for the track supply contract in the Bangalore Suburban Railway Project. The selected contractor will be responsible for supplying 60E1 (UIC 60), 1080 HH Grade rails in accordance with IRS-T-12-2009 standards (including all amendments and correction slips) for two specific sections: Corridor 2, from Baiyappanahalli to Chikkabanavara, and Corridor 4, between Heelalige and Rajankunte.

The tender for this supply contract, which includes a completion deadline of 365 days, was issued by K-RIDE earlier this year. Technical bids were opened on January 31, 2025, with submissions from three companies. Following a technical evaluation on May 29, 2025, Mitsui & Co., Ltd.’s bid was disqualified. Subsequently, financial bids were opened on June 4, 2025, confirming Saarstahl Rail as the lowest bidder.

The Bangalore Suburban Railway Project, currently under construction, spans a total length of 149.348 km and comprises four corridors designed to enhance commuter rail connectivity across the city.

News source: Metro Rail News

Rail Infrastructure Development Company Karnataka Limited (K-RIDE) has identified Saarstahl Rail as the lowest bidder for the track supply contract in the Bangalore Suburban Railway Project. The selected contractor will be responsible for supplying 60E1 (UIC 60), 1080 HH Grade rails in accordance with IRS-T-12-2009 standards (including all amendments and correction slips) for two specific sections: Corridor 2, from Baiyappanahalli to Chikkabanavara, and Corridor 4, between Heelalige and Rajankunte.The tender for this supply contract, which includes a completion deadline of 365 days, was issued by K-RIDE earlier this year. Technical bids were opened on January 31, 2025, with submissions from three companies. Following a technical evaluation on May 29, 2025, Mitsui & Co., Ltd.’s bid was disqualified. Subsequently, financial bids were opened on June 4, 2025, confirming Saarstahl Rail as the lowest bidder.The Bangalore Suburban Railway Project, currently under construction, spans a total length of 149.348 km and comprises four corridors designed to enhance commuter rail connectivity across the city.News source: Metro Rail News

Next Story
Infrastructure Transport

Adani wins Kedarnath ropeway project to cut trek to 36 minutes

Adani Enterprises Ltd (AEL) has secured the contract to build a 12.9-km ropeway connecting Sonprayag with Kedarnath, a project expected to transform the pilgrimage experience. Awarded by National Highways Logistics Management Ltd (NHLML), the project will be executed under the National Ropeways Development Programme – Parvatmala Pariyojana.Currently, pilgrims undertake a gruelling nine-hour trek to Kedarnath. The ropeway will reduce this journey to just 36 minutes and can transport 1,800 passengers per hour in each direction, serving the nearly 20 lakh devotees who visit annually.The Rs 25,0..

Next Story
Infrastructure Transport

Gurugram Rapid Metro to shift from DMRC to GMRL control

The Haryana Mass Rapid Transport Corporation Limited (HMRTC) has begun the process of transferring Gurugram’s Rapid Metro operations from the Delhi Metro Rail Corporation (DMRC) to Gurugram Metro Rail Limited (GMRL). The decision was taken at HMRTC’s 62nd Board meeting, chaired by chief secretary Anurag Rastogi.Committees have been formed to oversee the transition, covering technical, legal, and operational aspects, with definitive timelines being prepared. Until the transfer is complete, the system will be managed jointly by DMRC and GMRL.The Rapid Metro has shown notable performance impr..

Next Story
Infrastructure Transport

Chandigarh Metro cost climbs to Rs 25,000 crore amid delays

The long-awaited Chandigarh Tricity Metro project has seen its estimated cost balloon to nearly Rs 25,000 crore, following delays in approvals by the Union Territory administration. The cost, which stood at Rs 23,263 crore in February 2025, has risen by Rs 1,737 crore in just seven months, according to officials.The matter was raised during the transport standing committee meeting of the Administrator’s Advisory Council, chaired by AAP state president Vijay Pal. A presentation by Rail India Technical and Economic Service (RITES) strongly recommended that the Metro is the most suitable mass r..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?