Thane-Bhiwandi Metro Line-5: MMRDA mounts spans over Majiwada Flyover
RAILWAYS & METRO RAIL

Thane-Bhiwandi Metro Line-5: MMRDA mounts spans over Majiwada Flyover

The Mumbai Metropolitan Region Development Authority (MMRDA) has achieved a major milestone in the ongoing Metro Line-5 (Thane-Bhiwandi) project by successfully erecting two critical spans—57.50 meters and 46.00 meters—over the busy Majiwada Flyover using high-capacity cranes (450T and 700T).

The complex operation, which required precise engineering and extensive safety measures, was executed in a densely populated area above a congested roadway. According to MMRDA Metropolitan Commissioner Dr Sanjay Mukherjee, the team completed the task within just five hours during the night, ensuring minimal traffic disruption with the support of local authorities.

The 57.50-meter span between Pier 10 and Pier 11 was lifted using tandem girders weighing 290 MT on Ghodbunder Road, while the 46.00-meter span on the Thane-Bhiwandi Road utilised a super-lift arrangement to account for a 20-meter crane radius. This operation highlights the technical expertise and commitment of the team to completing the project on time.

The Thane-Bhiwandi Metro Line-5 project is being implemented in two phases. Phase-I, covering a 12.7 km stretch with six elevated stations, is 93% complete, with track installation and architectural finishes currently underway. The depot for Line-5 is planned at Kasheli, and preliminary work has commenced. The total cost for Metro Line-5 is estimated at Rs 84.17 billion.

The process of appointing a general consultant for Phase-II between Bhiwandi and Kalyan is in progress, with the appointment of a civil contractor to follow. Once completed, Metro Line-5 will provide interconnectivity with the ongoing Metro Line-4 (Wadala-Kasarvadavli) and the proposed Metro Line-12 (Kalyan-Taloja), along with the existing Central Railway suburban network, significantly enhancing regional connectivity. (freepressjournal)

The Mumbai Metropolitan Region Development Authority (MMRDA) has achieved a major milestone in the ongoing Metro Line-5 (Thane-Bhiwandi) project by successfully erecting two critical spans—57.50 meters and 46.00 meters—over the busy Majiwada Flyover using high-capacity cranes (450T and 700T). The complex operation, which required precise engineering and extensive safety measures, was executed in a densely populated area above a congested roadway. According to MMRDA Metropolitan Commissioner Dr Sanjay Mukherjee, the team completed the task within just five hours during the night, ensuring minimal traffic disruption with the support of local authorities. The 57.50-meter span between Pier 10 and Pier 11 was lifted using tandem girders weighing 290 MT on Ghodbunder Road, while the 46.00-meter span on the Thane-Bhiwandi Road utilised a super-lift arrangement to account for a 20-meter crane radius. This operation highlights the technical expertise and commitment of the team to completing the project on time. The Thane-Bhiwandi Metro Line-5 project is being implemented in two phases. Phase-I, covering a 12.7 km stretch with six elevated stations, is 93% complete, with track installation and architectural finishes currently underway. The depot for Line-5 is planned at Kasheli, and preliminary work has commenced. The total cost for Metro Line-5 is estimated at Rs 84.17 billion. The process of appointing a general consultant for Phase-II between Bhiwandi and Kalyan is in progress, with the appointment of a civil contractor to follow. Once completed, Metro Line-5 will provide interconnectivity with the ongoing Metro Line-4 (Wadala-Kasarvadavli) and the proposed Metro Line-12 (Kalyan-Taloja), along with the existing Central Railway suburban network, significantly enhancing regional connectivity. (freepressjournal)

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->