+
360 projects report cost overruns of Rs 3.88 tn
PORTS & SHIPPING

360 projects report cost overruns of Rs 3.88 tn

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for June 2019, according to which, out of a total 1,608 projects, more than 360 have shown cost overruns to the tune of Rs 3.88 trillion.

The report states that the original estimated cost of all the projects is approximately Rs 19.18 trillion. Completion cost is now expected to be around Rs 23.05 trillion. This amounts to cost overruns of around 20.23 per cent from the original cost. Additionally, the report included the number of projects that had crossed their deadlines; these amounted to 550. The average time overrun for all 550 projects was reported to be 39.24 months.

Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints because of funding, geographical conditions, labour issues and court cases, among other reasons.

“Project implementation in certain infrastructure sectors continues to remain challenging, with many projects witnessing significant time and cost overruns,” says Shubham Jain, Group Head & Senior Vice-President, Corporate Ratings, ICRA. “As per the recent data available, the aggregate cost overrun for all major ongoing infrastructure projects as a percentage of original cost had increased to over 20 per cent—the highest in about eight years. Two key sectors—railways and power—have contributed to the majority of the cost overruns. This is despite the various reform measures undertaken by the Government. Delays in land acquisition, the difficulty faced in project financing, and increasing cost of land acquisition have been some of the key reasons behind the time and cost overruns.”

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for June 2019, according to which, out of a total 1,608 projects, more than 360 have shown cost overruns to the tune of Rs 3.88 trillion. The report states that the original estimated cost of all the projects is approximately Rs 19.18 trillion. Completion cost is now expected to be around Rs 23.05 trillion. This amounts to cost overruns of around 20.23 per cent from the original cost. Additionally, the report included the number of projects that had crossed their deadlines; these amounted to 550. The average time overrun for all 550 projects was reported to be 39.24 months. Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints because of funding, geographical conditions, labour issues and court cases, among other reasons. “Project implementation in certain infrastructure sectors continues to remain challenging, with many projects witnessing significant time and cost overruns,” says Shubham Jain, Group Head & Senior Vice-President, Corporate Ratings, ICRA. “As per the recent data available, the aggregate cost overrun for all major ongoing infrastructure projects as a percentage of original cost had increased to over 20 per cent—the highest in about eight years. Two key sectors—railways and power—have contributed to the majority of the cost overruns. This is despite the various reform measures undertaken by the Government. Delays in land acquisition, the difficulty faced in project financing, and increasing cost of land acquisition have been some of the key reasons behind the time and cost overruns.”

Next Story
Infrastructure Transport

Kavach 4.0 Commissioned on Delhi–Mumbai and Delhi–Howrah

"Kavach version four has been commissioned on 1,452 route km, covering the high density Delhi–Mumbai and Delhi–Howrah corridors. The rollout included laying 8,570 km of optical fibre, installation of 1,100 telecom towers, deployment of trackside equipment over 6,776 RKm and establishment of 767 station data centres. Trackside implementation has been taken up on 24,427 RKm covering Golden Quadrilateral, Golden Diagonal and High Density Network sections. The programme aims to strengthen signalling and train protection on key routes.Kavach is an indigenously developed automatic train protecti..

Next Story
Infrastructure Transport

Railways Advance Kalyan–Murbad Line And Mumbai Capacity Expansion

"Indian Railways is advancing multiple rail infrastructure projects in Maharashtra, including the sanctioned Kalyan–Murbad new line and sizable investments under the Mumbai Urban Transport Project and the Mumbai–Ahmedabad High Speed Rail project. The Kalyan–Murbad 28 km new line has been sanctioned at Rs 8.36 billion (bn) on a 50:50 cost-sharing basis with the Government of Maharashtra and has been declared a Special Railway Project for land acquisition; proposals covering 214 hectares are at various stages of acquisition. Budgetary outlay for projects falling fully or partly in Maharash..

Next Story
Infrastructure Urban

Parliamentary Panel Flags Funding Gaps in Heavy Industries

"The Department-Related Parliamentary Standing Committee on Industry (Rajya Sabha) presented its 332nd report on the Demands for Grants 2026-27 of the Ministry of Heavy Industries (MHI). Figures converted from crore and lakh are expressed in million (mn). The Budget Estimates 2026-27 for the Ministry stand at Rs 79,399 mn against a projected requirement of Rs 94,843.2 mn, a shortfall of about 16 per cent, with revenue at Rs 79,370.8 mn and capital compressed to Rs 28.2 mn from Rs 5,020 mn.The committee flagged recurring BE-to-RE compression and declining revised estimate utilisation, and calle..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement