Maharashtra Nears Smart Cities Finish, Rs 15.6bn Still Pending
SMART CITIES

Maharashtra Nears Smart Cities Finish, Rs 15.6bn Still Pending

Cities in Maharashtra under the Smart Cities Mission (SCM) are nearing the end of implementation, with over 94 per cent of sanctioned projects completed. However, projects worth more than Rs 15.55 billion remain unfinished, pointing to uneven progress across cities and sectors.

According to official data, Maharashtra’s eight smart cities were allotted 347 projects with a total outlay of Rs 169.8 billion. Of these, 328 projects valued at Rs 154.25 billion have been completed, while 19 projects involving Rs 15.55 billion are still under execution.

Launched in 2014 under Prime Minister Narendra Modi, the Smart Cities Mission aimed to develop 100 cities across India. Maharashtra cities included in the programme were Aurangabad (now Chhatrapati Sambhajinagar), Kalyan-Dombivli, Nagpur, Nashik, Pimpri-Chinchwad, Pune, Solapur and Thane. With the mission concluding on March 31, 2025, there is no budgetary allocation under SCM for the current financial year.

Uneven City-Wise Progress

Pune and Solapur have emerged as full achievers. Pune completed all 55 of its projects, amounting to Rs 33.33 billion, while Solapur finished 49 projects worth Rs 15.87 billion, with no pending works.

Nashik, one of the largest beneficiaries, completed 51 of its 53 projects, accounting for Rs 30.12 billion out of a total allocation of Rs 31.97 billion. Two projects worth Rs 1.85 billion remain under execution.

Chhatrapati Sambhajinagar completed 45 of 47 projects, though pending works still account for Rs 1.45 billion. Thane has two unfinished projects valued at Rs 3.10 billion, while Nagpur has the highest number of pending projects—nine—together worth Rs 2.60 billion.

Kalyan-Dombivli presents a different challenge. While only three projects are pending, their combined value stands at Rs 5.23 billion, making it one of the costliest unfinished portfolios in the State. Pimpri-Chinchwad has a single pending project valued at Rs 1.32 billion.

Sectoral Trends

Sector-wise analysis shows strong completion in social and utility-focused infrastructure. Smart energy, social infrastructure and environment projects have achieved 100 per cent completion, together accounting for over Rs 31.67 billion. Water, sanitation and hygiene projects recorded around 95 per cent completion, while vibrant public spaces and smart governance crossed 97 per cent.

The largest lag is in smart mobility, the biggest sector by value. Although projects worth Rs 55.05 billion have been completed, full closure remains elusive due to delays in road redesign, intelligent transport systems and last-mile connectivity works.

Officials noted that much of the spending under the mission has gone towards addressing basic infrastructure gaps rather than building advanced “smart” urban systems, highlighting the continuing challenge of meeting essential civic needs even under flagship urban programmes.

Cities in Maharashtra under the Smart Cities Mission (SCM) are nearing the end of implementation, with over 94 per cent of sanctioned projects completed. However, projects worth more than Rs 15.55 billion remain unfinished, pointing to uneven progress across cities and sectors. According to official data, Maharashtra’s eight smart cities were allotted 347 projects with a total outlay of Rs 169.8 billion. Of these, 328 projects valued at Rs 154.25 billion have been completed, while 19 projects involving Rs 15.55 billion are still under execution. Launched in 2014 under Prime Minister Narendra Modi, the Smart Cities Mission aimed to develop 100 cities across India. Maharashtra cities included in the programme were Aurangabad (now Chhatrapati Sambhajinagar), Kalyan-Dombivli, Nagpur, Nashik, Pimpri-Chinchwad, Pune, Solapur and Thane. With the mission concluding on March 31, 2025, there is no budgetary allocation under SCM for the current financial year. Uneven City-Wise Progress Pune and Solapur have emerged as full achievers. Pune completed all 55 of its projects, amounting to Rs 33.33 billion, while Solapur finished 49 projects worth Rs 15.87 billion, with no pending works. Nashik, one of the largest beneficiaries, completed 51 of its 53 projects, accounting for Rs 30.12 billion out of a total allocation of Rs 31.97 billion. Two projects worth Rs 1.85 billion remain under execution. Chhatrapati Sambhajinagar completed 45 of 47 projects, though pending works still account for Rs 1.45 billion. Thane has two unfinished projects valued at Rs 3.10 billion, while Nagpur has the highest number of pending projects—nine—together worth Rs 2.60 billion. Kalyan-Dombivli presents a different challenge. While only three projects are pending, their combined value stands at Rs 5.23 billion, making it one of the costliest unfinished portfolios in the State. Pimpri-Chinchwad has a single pending project valued at Rs 1.32 billion. Sectoral Trends Sector-wise analysis shows strong completion in social and utility-focused infrastructure. Smart energy, social infrastructure and environment projects have achieved 100 per cent completion, together accounting for over Rs 31.67 billion. Water, sanitation and hygiene projects recorded around 95 per cent completion, while vibrant public spaces and smart governance crossed 97 per cent. The largest lag is in smart mobility, the biggest sector by value. Although projects worth Rs 55.05 billion have been completed, full closure remains elusive due to delays in road redesign, intelligent transport systems and last-mile connectivity works. Officials noted that much of the spending under the mission has gone towards addressing basic infrastructure gaps rather than building advanced “smart” urban systems, highlighting the continuing challenge of meeting essential civic needs even under flagship urban programmes.

Next Story
Infrastructure Energy

BMW Industries partners with IOCL for PNG supply at Bokaro plant

BMW Industries has entered into a strategic partnership with Indian Oil Corporation (IOCL) for the supply of Piped Natural Gas (PNG), reinforcing its commitment to adopting cleaner and more efficient energy sources for its operations.The agreement was signed at the Eastern Region Pipelines (ERPL) headquarters in Kolkata. The partnership is expected to support the company’s upcoming manufacturing facility in Bokaro by facilitating the use of natural gas as a primary energy source.According to the company, the adoption of PNG will help enhance operational efficiency while also contributing to ..

Next Story
Real Estate

Bombay Realty Secures RERA for Three ICC Tower in South Mumbai

Bombay Realty, the real estate arm of Bombay Dyeing and part of the Wadia Group, has received Real Estate Regulatory Authority (RERA) certification for Three ICC – Wing A, the latest luxury residential tower at Island City Center in Mumbai’s Dadar.The RERA registration marks a key milestone in the development timeline and reinforces the company’s focus on regulatory transparency, timely project delivery, and high construction standards.Following the success of One ICC and Two ICC, the upcoming Three ICC tower represents the next phase of the Island City Center development. The project ai..

Next Story
Infrastructure Energy

Flender launches India’s largest wind gearbox test rig in Walajabad

Flender has inaugurated a 13.5 MW wind turbine gearbox test rig at its Walajabad facility near Chennai, marking the largest installation of its kind in India. The new facility is expected to strengthen the company’s manufacturing and testing capabilities while supporting the growing demands of the wind power sector in both domestic and global markets.The test rig was inaugurated on March 5 in the presence of Andreas Evertz, Group CEO, Flender; Lars Wiegemann, Vice President Wind Gears, Flender; and Vinod Shetty, CEO, Flender India, along with key industry customers and stakeholders.The insta..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement