Only 46% projects under Smart Cities Mission completed in six years
SMART CITIES

Only 46% projects under Smart Cities Mission completed in six years

Six years post the launch of the Smart Cities Mission (SCM), under which 100 cities from across the country were shortlisted to be developed as smart cities by the centre, only 46% out of around 6,000 projects tendered, have been completed.

The 100 smart cities were supposed to be developed within the five years of the scheme's inception, which is between 2015 and 2020. The completed projects are not yet near the halfway mark one year after the deadline ended.

Out of the 6,017 projects tendered, only 2,781 have been completed until 9 July, 2021, as per the latest data provided by the Ministry of Housing and Urban Development. In other words, only 46% of projects have been completed, ever since the Centre launched the SCM on 25 June, 2015, out of the total tendered projects.

One hundred selected cities under the Smart City Mission were provided with assured electricity supply, adequate water supply, sanitation, including efficient urban mobility and public transport, solid waste management, and affordable housing, especially for the poor and robust IT connectivity and digitalisation.

The selection of 100 "Smart Cities" was completed from January 2016 to June 2018 through four selection rounds. According to the guidelines of Smart Cities Mission, the Centre must provide financial support to the Mission to the extent of Rs 48,000 crore over five years, which is Rs 100 crore on an average per city per year and an equal amount should be provided by the states or urban local bodies.

The government of India has released Rs 23,925.83 crore as the central share to the states, out of which these Smart Cities have utilised Rs 20,410.14 crore, which is around 85%.

Image Source


Also read: Smart Cities Mission: Projects in Visakhapatnam nears completion

Also read: Smart City Mission: Nine projects in Jaipur completed at Rs 142 cr

Also read: Thiruvananthapuram Smart City projects near completion

Six years post the launch of the Smart Cities Mission (SCM), under which 100 cities from across the country were shortlisted to be developed as smart cities by the centre, only 46% out of around 6,000 projects tendered, have been completed. The 100 smart cities were supposed to be developed within the five years of the scheme's inception, which is between 2015 and 2020. The completed projects are not yet near the halfway mark one year after the deadline ended. Out of the 6,017 projects tendered, only 2,781 have been completed until 9 July, 2021, as per the latest data provided by the Ministry of Housing and Urban Development. In other words, only 46% of projects have been completed, ever since the Centre launched the SCM on 25 June, 2015, out of the total tendered projects. One hundred selected cities under the Smart City Mission were provided with assured electricity supply, adequate water supply, sanitation, including efficient urban mobility and public transport, solid waste management, and affordable housing, especially for the poor and robust IT connectivity and digitalisation. The selection of 100 Smart Cities was completed from January 2016 to June 2018 through four selection rounds. According to the guidelines of Smart Cities Mission, the Centre must provide financial support to the Mission to the extent of Rs 48,000 crore over five years, which is Rs 100 crore on an average per city per year and an equal amount should be provided by the states or urban local bodies. The government of India has released Rs 23,925.83 crore as the central share to the states, out of which these Smart Cities have utilised Rs 20,410.14 crore, which is around 85%. Image Source Also read: Smart Cities Mission: Projects in Visakhapatnam nears completion Also read: Smart City Mission: Nine projects in Jaipur completed at Rs 142 cr Also read: Thiruvananthapuram Smart City projects near completion

Next Story
Infrastructure Urban

Concord Control Systems Limited Reports ~85% YoY Growth in H1 FY26

Concord Control Systems Limited (BSE: CNCRD | 543619), India’s leading manufacturer of embedded electronic systems and critical electronic solutions, announced its unaudited financial results for the half year ended September 30, 2025.Financial Highlights – H1 FY26 (YoY Comparison)Revenue from Operations rose to ₹815.45 million, up from ₹497.53 million in H1 FY25, marking a 63.90% year-on-year growth.EBITDA increased to ₹217.34 million, compared to ₹142 million in the same period last year.EBITDA Margin stood at 26.65%, compared to 28.54% in H1 FY25, with the decline attributed to ..

Next Story
Infrastructure Urban

Gateway Distriparks Announces Q2 FY25 Results

Gateway Distriparks Limited (GDL), one of India’s leading multimodal logistics providers, announced its financial results for the quarter ended 30 September 2025.For Q2, the company reported total revenue of INR 154.8 crore (H1: INR 316.9 crore), EBITDA of INR 20.56 crore (H1: INR 45.65 crore), PBT of INR –4.23 crore (H1: INR –0.28 crore), and PAT of INR –2.91 crore (H1: INR –0.37 crore). The company stated that these numbers reflect the consolidation of accounts following Snowman Logistics transitioning from an associate company to a subsidiary in December 2024.Commenting on the per..

Next Story
Infrastructure Transport

Last-Mile Connectivity a Prime Focus, Says Ms. Ashwini Bhide,

The IMC Chamber of Commerce and Industry (IMC) hosted a high-impact Managing Committee session today on the theme “Mumbai Metro: Transforming Connectivity and Commuting.” The session featured an insightful address by Ms. Ashwini Bhide, Managing Director, Mumbai Metro Rail Corporation Ltd. (MMRCL), who shared updates on key transport infrastructure developments across Mumbai and the MMR region.Emphasising the city’s critical economic role, Ms. Bhide noted, “Mumbai is the economic powerhouse of Maharashtra, with more than 95% of the region’s population living in urban areas. As Maharas..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement