Only 46% projects under Smart Cities Mission completed in six years
SMART CITIES

Only 46% projects under Smart Cities Mission completed in six years

Six years post the launch of the Smart Cities Mission (SCM), under which 100 cities from across the country were shortlisted to be developed as smart cities by the centre, only 46% out of around 6,000 projects tendered, have been completed.

The 100 smart cities were supposed to be developed within the five years of the scheme's inception, which is between 2015 and 2020. The completed projects are not yet near the halfway mark one year after the deadline ended.

Out of the 6,017 projects tendered, only 2,781 have been completed until 9 July, 2021, as per the latest data provided by the Ministry of Housing and Urban Development. In other words, only 46% of projects have been completed, ever since the Centre launched the SCM on 25 June, 2015, out of the total tendered projects.

One hundred selected cities under the Smart City Mission were provided with assured electricity supply, adequate water supply, sanitation, including efficient urban mobility and public transport, solid waste management, and affordable housing, especially for the poor and robust IT connectivity and digitalisation.

The selection of 100 "Smart Cities" was completed from January 2016 to June 2018 through four selection rounds. According to the guidelines of Smart Cities Mission, the Centre must provide financial support to the Mission to the extent of Rs 48,000 crore over five years, which is Rs 100 crore on an average per city per year and an equal amount should be provided by the states or urban local bodies.

The government of India has released Rs 23,925.83 crore as the central share to the states, out of which these Smart Cities have utilised Rs 20,410.14 crore, which is around 85%.

Image Source


Also read: Smart Cities Mission: Projects in Visakhapatnam nears completion

Also read: Smart City Mission: Nine projects in Jaipur completed at Rs 142 cr

Also read: Thiruvananthapuram Smart City projects near completion

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

Six years post the launch of the Smart Cities Mission (SCM), under which 100 cities from across the country were shortlisted to be developed as smart cities by the centre, only 46% out of around 6,000 projects tendered, have been completed. The 100 smart cities were supposed to be developed within the five years of the scheme's inception, which is between 2015 and 2020. The completed projects are not yet near the halfway mark one year after the deadline ended. Out of the 6,017 projects tendered, only 2,781 have been completed until 9 July, 2021, as per the latest data provided by the Ministry of Housing and Urban Development. In other words, only 46% of projects have been completed, ever since the Centre launched the SCM on 25 June, 2015, out of the total tendered projects. One hundred selected cities under the Smart City Mission were provided with assured electricity supply, adequate water supply, sanitation, including efficient urban mobility and public transport, solid waste management, and affordable housing, especially for the poor and robust IT connectivity and digitalisation. The selection of 100 Smart Cities was completed from January 2016 to June 2018 through four selection rounds. According to the guidelines of Smart Cities Mission, the Centre must provide financial support to the Mission to the extent of Rs 48,000 crore over five years, which is Rs 100 crore on an average per city per year and an equal amount should be provided by the states or urban local bodies. The government of India has released Rs 23,925.83 crore as the central share to the states, out of which these Smart Cities have utilised Rs 20,410.14 crore, which is around 85%. Image Source Also read: Smart Cities Mission: Projects in Visakhapatnam nears completion Also read: Smart City Mission: Nine projects in Jaipur completed at Rs 142 cr Also read: Thiruvananthapuram Smart City projects near completion

Next Story
Infrastructure Urban

ABS Marine Sees CRISIL Credit Rating Upgrade

ABS Marine Services has secured an upgrade to its long term and short term credit ratings from CRISIL, reflecting improved profitability and revenue growth through long term contracts. CRISIL moved the long term rating from BBB+/Stable to A-/Stable and revised the short term rating from A2 to A2+. The action signals strengthened financial metrics and operational resilience. The company benefited from durable client relationships with firms such as ONGC and Schlumberger. The rating decision followed stronger cash flows and an enlarged bank loan facility, which increased from Rs 3,705 million (m..

Next Story
Infrastructure Transport

Project BRAHMANK Marks 16 Years Of Strategic Roads In Arunachal

Project BRAHMANK is marking 16 years of work to establish strategic road and bridge links across Arunachal Pradesh, maintaining and developing 811 kilometres of roads and nearly 86 bridges that range from small culverts to large steel and arch bridges. These transport links are described as critical for ensuring year-round movement of defence personnel, equipment and essential supplies while improving everyday travel for people in remote villages. The project balances national security requirements with regional development by focusing on reliable access in challenging terrain. Notable enginee..

Next Story
Infrastructure Transport

Longleng CSOs Give One Week Ultimatum Over Two-Lane Highway

Civil society organisations (CSOs) in Longleng district have demanded immediate restoration of the deteriorating Changtongya–Longleng two-lane road and sought a detailed status report on the stalled construction within one week. The demand followed a consultative meeting convened under the Phom Peoples' Council (PPC) to discuss welfare and development concerns. PPC president YB Angam Phom said prolonged non-maintenance had caused hardship to commuters and affected transportation, local commerce and the district's development. The meeting urged authorities to undertake immediate restoration a..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement