Mega Opportunities coming along Samruddhi Mahamarg
ROADS & HIGHWAYS

Mega Opportunities coming along Samruddhi Mahamarg

As updated on July 29, 2020, almost as much as 40 per cent work of the Samruddhi Mahamarg has been successfully completed and the highway lane from Igatpuri to Nagpur (623 km) will be operational beginning from December 2021. The construction of the remaining 78 km stretch located in Thane is expected to be postponed by three to four months. It has been reported that quite a few portions of the route in Vidarbha, including 10 new towns, and at least one of the 16 stretches of the road will be ready for commercial use by June 2021. Along the Samruddhi Mahamarg, optical fiber web, natural gas pipelines promoting gas-based industries and solar power projects up to around 250-300 MW will be created.

Passing through 10 districts, 26 tehsils, and 390 villages, the gigantic expressway will pave way for the development of around 20 townships and nodes along its way. An eight-phase programme has been set up for the above mentioned by the MSRDC, the organisation responsible for the execution of this project. The first five phases of the same have been completed. It includes geo-referenced mapping, inception, the study of exiting land use and the market demand assessment, drafting a development plan, and preparing the final report. Further, 93 out of 153 structures have been completed in Wardha, 151 out of 199 have been completed in Amravati and 96 out of 209 have been completed in Washim.

Despite the lockdown, the construction work of the expressway continued with special permission from the Central Government. The roadside camps where the workers resided were thoroughly sanitised and their COVID-19 tests were conducted, none being positive. However, the pace of the project had dropped as a fraction of the workers left for their hometowns. It was reported that out of 1,699 structures along the 701-km expressway including bridges, tunnels, and flyovers, 662 were completed and 461 were in progress in March 2020. Three of the eight rails-over-bridges and 31 of the 65 major bridges were under construction. Further, 134 minor bridges have been completed while 45 were in progress.

Furthermore, 8,311 hectares – which are 86 per cent of the total land required for the Samruddhi Mahamaarg – had been acquired in March 2020. The work has been divided among 14 contractors including giant corporations such as Reliance Infrastructure and Larsen & Toubro into 16 packages, with Megha Engineering and Infrastructure and Navayuga Engineering responsible for two of these packages. The total budget allocated for this project is Rs 450 billion. The state government had also provided a compensatory sum of Rs 69.11 billion to those affected by the project.

The Samruddhi expressway was primarily designed with keen precision to ensure a faster, more efficient journey of eight hours only. The expressway is flanked by four lanes on each side. It has a width of 120 m and a central median of 22.5 m. The expressway is expected to feature extensive landscaping, bridge beautification, enhanced street, and tunnel lighting rainwater harvesting and wayside amenities every 40 km. It offers a speed limit of 150 km per hour on flat terrain and 120 km per hour on an incline. The corridor of the Samruddhi Mahamarg is being built from scratch with minimal demolition of existing structures.

Undoubtedly, the project will prove to be a crucial step for the future success of Maharashtra's rural areas.

As updated on July 29, 2020, almost as much as 40 per cent work of the Samruddhi Mahamarg has been successfully completed and the highway lane from Igatpuri to Nagpur (623 km) will be operational beginning from December 2021. The construction of the remaining 78 km stretch located in Thane is expected to be postponed by three to four months. It has been reported that quite a few portions of the route in Vidarbha, including 10 new towns, and at least one of the 16 stretches of the road will be ready for commercial use by June 2021. Along the Samruddhi Mahamarg, optical fiber web, natural gas pipelines promoting gas-based industries and solar power projects up to around 250-300 MW will be created. Passing through 10 districts, 26 tehsils, and 390 villages, the gigantic expressway will pave way for the development of around 20 townships and nodes along its way. An eight-phase programme has been set up for the above mentioned by the MSRDC, the organisation responsible for the execution of this project. The first five phases of the same have been completed. It includes geo-referenced mapping, inception, the study of exiting land use and the market demand assessment, drafting a development plan, and preparing the final report. Further, 93 out of 153 structures have been completed in Wardha, 151 out of 199 have been completed in Amravati and 96 out of 209 have been completed in Washim. Despite the lockdown, the construction work of the expressway continued with special permission from the Central Government. The roadside camps where the workers resided were thoroughly sanitised and their COVID-19 tests were conducted, none being positive. However, the pace of the project had dropped as a fraction of the workers left for their hometowns. It was reported that out of 1,699 structures along the 701-km expressway including bridges, tunnels, and flyovers, 662 were completed and 461 were in progress in March 2020. Three of the eight rails-over-bridges and 31 of the 65 major bridges were under construction. Further, 134 minor bridges have been completed while 45 were in progress. Furthermore, 8,311 hectares – which are 86 per cent of the total land required for the Samruddhi Mahamaarg – had been acquired in March 2020. The work has been divided among 14 contractors including giant corporations such as Reliance Infrastructure and Larsen & Toubro into 16 packages, with Megha Engineering and Infrastructure and Navayuga Engineering responsible for two of these packages. The total budget allocated for this project is Rs 450 billion. The state government had also provided a compensatory sum of Rs 69.11 billion to those affected by the project. The Samruddhi expressway was primarily designed with keen precision to ensure a faster, more efficient journey of eight hours only. The expressway is flanked by four lanes on each side. It has a width of 120 m and a central median of 22.5 m. The expressway is expected to feature extensive landscaping, bridge beautification, enhanced street, and tunnel lighting rainwater harvesting and wayside amenities every 40 km. It offers a speed limit of 150 km per hour on flat terrain and 120 km per hour on an incline. The corridor of the Samruddhi Mahamarg is being built from scratch with minimal demolition of existing structures. Undoubtedly, the project will prove to be a crucial step for the future success of Maharashtra's rural areas.

Next Story
Infrastructure Transport

Metro Line 2B Phase 1 to Boost Realty in Mumbai’s Eastern Suburbs

Mumbai’s real estate sector is set for a major boost as Phase 1 of Metro Line 2B, between Mandale and Diamond Garden, nears completion. The Mumbai Metropolitan Region Development Authority (MMRDA) has confirmed that mandatory rectifications are done, and inspections by the Commissioner of Metro Railway Safety (CMRS) have been carried out. The 5.39-km stretch with five stations forms part of the larger DN Nagar–Mandale corridor, designed to ease congestion and improve east–west connectivity. Passenger operations are expected by December 2025, with the full line slated for 2027. ..

Next Story
Resources

WattPower wins Best Inverter award at Global Solar Expo 2025

WattPower, a leading renewable energy solutions provider, has won the award for “Best Inverter in the Utility Segment” at the Global Solar Expo 2025. The recognition underscores the company’s commitment to delivering reliable, high-performance and future-ready solar solutions for large-scale projects. At the forefront of utility-scale solar, WattPower manufactures advanced string inverters that directly feed power into the Indian grid. With robust technology, high-quality components and comprehensive product lifecycle support, its solutions stand among the most sophisticated in the ..

Next Story
Real Estate

Awfis delivers 67,000 sq. ft. innovation hub for eBay in Bengaluru

Awfis Space Solutions, India’s largest flexible workspace provider and the first publicly listed workspace solutions platform, has partnered with eBay to establish a 67,000 sq. ft. innovation hub at Embassy Tech Village, Bengaluru. The mandate covers design, build and management of the new office, which will act as a strategic hub supporting diverse functions and accelerating eBay’s AI-first commerce strategy. The centre will focus on artificial intelligence, engineering, product development and applied research, strengthening eBay’s growth in India. Embassy Tech Village, North Beng..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?