Mega Opportunities coming along Samruddhi Mahamarg
ROADS & HIGHWAYS

Mega Opportunities coming along Samruddhi Mahamarg

As updated on July 29, 2020, almost as much as 40 per cent work of the Samruddhi Mahamarg has been successfully completed and the highway lane from Igatpuri to Nagpur (623 km) will be operational beginning from December 2021. The construction of the remaining 78 km stretch located in Thane is expected to be postponed by three to four months. It has been reported that quite a few portions of the route in Vidarbha, including 10 new towns, and at least one of the 16 stretches of the road will be ready for commercial use by June 2021. Along the Samruddhi Mahamarg, optical fiber web, natural gas pipelines promoting gas-based industries and solar power projects up to around 250-300 MW will be created.

Passing through 10 districts, 26 tehsils, and 390 villages, the gigantic expressway will pave way for the development of around 20 townships and nodes along its way. An eight-phase programme has been set up for the above mentioned by the MSRDC, the organisation responsible for the execution of this project. The first five phases of the same have been completed. It includes geo-referenced mapping, inception, the study of exiting land use and the market demand assessment, drafting a development plan, and preparing the final report. Further, 93 out of 153 structures have been completed in Wardha, 151 out of 199 have been completed in Amravati and 96 out of 209 have been completed in Washim.

Despite the lockdown, the construction work of the expressway continued with special permission from the Central Government. The roadside camps where the workers resided were thoroughly sanitised and their COVID-19 tests were conducted, none being positive. However, the pace of the project had dropped as a fraction of the workers left for their hometowns. It was reported that out of 1,699 structures along the 701-km expressway including bridges, tunnels, and flyovers, 662 were completed and 461 were in progress in March 2020. Three of the eight rails-over-bridges and 31 of the 65 major bridges were under construction. Further, 134 minor bridges have been completed while 45 were in progress.

Furthermore, 8,311 hectares – which are 86 per cent of the total land required for the Samruddhi Mahamaarg – had been acquired in March 2020. The work has been divided among 14 contractors including giant corporations such as Reliance Infrastructure and Larsen & Toubro into 16 packages, with Megha Engineering and Infrastructure and Navayuga Engineering responsible for two of these packages. The total budget allocated for this project is Rs 450 billion. The state government had also provided a compensatory sum of Rs 69.11 billion to those affected by the project.

The Samruddhi expressway was primarily designed with keen precision to ensure a faster, more efficient journey of eight hours only. The expressway is flanked by four lanes on each side. It has a width of 120 m and a central median of 22.5 m. The expressway is expected to feature extensive landscaping, bridge beautification, enhanced street, and tunnel lighting rainwater harvesting and wayside amenities every 40 km. It offers a speed limit of 150 km per hour on flat terrain and 120 km per hour on an incline. The corridor of the Samruddhi Mahamarg is being built from scratch with minimal demolition of existing structures.

Undoubtedly, the project will prove to be a crucial step for the future success of Maharashtra's rural areas.

As updated on July 29, 2020, almost as much as 40 per cent work of the Samruddhi Mahamarg has been successfully completed and the highway lane from Igatpuri to Nagpur (623 km) will be operational beginning from December 2021. The construction of the remaining 78 km stretch located in Thane is expected to be postponed by three to four months. It has been reported that quite a few portions of the route in Vidarbha, including 10 new towns, and at least one of the 16 stretches of the road will be ready for commercial use by June 2021. Along the Samruddhi Mahamarg, optical fiber web, natural gas pipelines promoting gas-based industries and solar power projects up to around 250-300 MW will be created. Passing through 10 districts, 26 tehsils, and 390 villages, the gigantic expressway will pave way for the development of around 20 townships and nodes along its way. An eight-phase programme has been set up for the above mentioned by the MSRDC, the organisation responsible for the execution of this project. The first five phases of the same have been completed. It includes geo-referenced mapping, inception, the study of exiting land use and the market demand assessment, drafting a development plan, and preparing the final report. Further, 93 out of 153 structures have been completed in Wardha, 151 out of 199 have been completed in Amravati and 96 out of 209 have been completed in Washim. Despite the lockdown, the construction work of the expressway continued with special permission from the Central Government. The roadside camps where the workers resided were thoroughly sanitised and their COVID-19 tests were conducted, none being positive. However, the pace of the project had dropped as a fraction of the workers left for their hometowns. It was reported that out of 1,699 structures along the 701-km expressway including bridges, tunnels, and flyovers, 662 were completed and 461 were in progress in March 2020. Three of the eight rails-over-bridges and 31 of the 65 major bridges were under construction. Further, 134 minor bridges have been completed while 45 were in progress. Furthermore, 8,311 hectares – which are 86 per cent of the total land required for the Samruddhi Mahamaarg – had been acquired in March 2020. The work has been divided among 14 contractors including giant corporations such as Reliance Infrastructure and Larsen & Toubro into 16 packages, with Megha Engineering and Infrastructure and Navayuga Engineering responsible for two of these packages. The total budget allocated for this project is Rs 450 billion. The state government had also provided a compensatory sum of Rs 69.11 billion to those affected by the project. The Samruddhi expressway was primarily designed with keen precision to ensure a faster, more efficient journey of eight hours only. The expressway is flanked by four lanes on each side. It has a width of 120 m and a central median of 22.5 m. The expressway is expected to feature extensive landscaping, bridge beautification, enhanced street, and tunnel lighting rainwater harvesting and wayside amenities every 40 km. It offers a speed limit of 150 km per hour on flat terrain and 120 km per hour on an incline. The corridor of the Samruddhi Mahamarg is being built from scratch with minimal demolition of existing structures. Undoubtedly, the project will prove to be a crucial step for the future success of Maharashtra's rural areas.

Next Story
Infrastructure Urban

Jyoti Structures FY26 profit rises 56.5%

Jyoti Structures (JSL) recently reported strong financial results for the quarter and year ended 31 March 2026, driven by disciplined execution, cost management and steady progress across its order book.For Q4 FY2025-26, total income rose 44.2 per cent to Rs 2.41 billion from Rs 1.67 billion in Q4 FY2024-25. EBITDA increased 58.6 per cent to Rs 237 million, while EBITDA margin improved by 89 basis points to 9.84 per cent. Profit before tax grew 53.3 per cent to Rs 188.5 million, and net profit rose 51.9 per cent to Rs 181.4 million.For FY2025-26, total income grew 53.1 per cent to Rs 7.72 bill..

Next Story
Infrastructure Energy

Cat BEPU to Power Doppstadt Separator at IFAT 2026

Caterpillar’s Cat Battery Electric Power Unit (BEPU) has been selected by Doppstadt to power its SWS 6 Spiral Shaft Separator, which will be showcased for the first time at IFAT 2026 in Munich, Germany, from 4–7 May.The compact plug-and-play BEPU is designed to replace a diesel engine within the same space, using the same mounting locations and relative machine position. It integrates the battery, motor, inverter, onboard charging, cooling and controls, enabling OEMs to electrify existing chassis platforms without extensive redesign.Caterpillar and Cat dealer Zeppelin Power Systems have be..

Next Story
Infrastructure Urban

VECV sales rise 6.9% in April 2026

VE Commercial Vehicles, a joint venture between Volvo Group and Eicher Motors, recorded sales of 7,318 units in April 2026, compared to 6,846 units in April 2025, registering 6.9 per cent growth. The total included 7,159 units under the Eicher brand and 159 units under the Volvo brand.Eicher branded trucks and buses reported sales of 7,159 units during the month, up 6.6 per cent from 6,717 units in April 2025. In the domestic commercial vehicle market, Eicher sales rose 8.6 per cent to 6,797 units from 6,257 units a year earlier.Exports declined 21.3 per cent, with VECV recording 362 units in ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement