Mega Opportunities coming along Samruddhi Mahamarg
ROADS & HIGHWAYS

Mega Opportunities coming along Samruddhi Mahamarg

As updated on July 29, 2020, almost as much as 40 per cent work of the Samruddhi Mahamarg has been successfully completed and the highway lane from Igatpuri to Nagpur (623 km) will be operational beginning from December 2021. The construction of the remaining 78 km stretch located in Thane is expected to be postponed by three to four months. It has been reported that quite a few portions of the route in Vidarbha, including 10 new towns, and at least one of the 16 stretches of the road will be ready for commercial use by June 2021. Along the Samruddhi Mahamarg, optical fiber web, natural gas pipelines promoting gas-based industries and solar power projects up to around 250-300 MW will be created.

Passing through 10 districts, 26 tehsils, and 390 villages, the gigantic expressway will pave way for the development of around 20 townships and nodes along its way. An eight-phase programme has been set up for the above mentioned by the MSRDC, the organisation responsible for the execution of this project. The first five phases of the same have been completed. It includes geo-referenced mapping, inception, the study of exiting land use and the market demand assessment, drafting a development plan, and preparing the final report. Further, 93 out of 153 structures have been completed in Wardha, 151 out of 199 have been completed in Amravati and 96 out of 209 have been completed in Washim.

Despite the lockdown, the construction work of the expressway continued with special permission from the Central Government. The roadside camps where the workers resided were thoroughly sanitised and their COVID-19 tests were conducted, none being positive. However, the pace of the project had dropped as a fraction of the workers left for their hometowns. It was reported that out of 1,699 structures along the 701-km expressway including bridges, tunnels, and flyovers, 662 were completed and 461 were in progress in March 2020. Three of the eight rails-over-bridges and 31 of the 65 major bridges were under construction. Further, 134 minor bridges have been completed while 45 were in progress.

Furthermore, 8,311 hectares – which are 86 per cent of the total land required for the Samruddhi Mahamaarg – had been acquired in March 2020. The work has been divided among 14 contractors including giant corporations such as Reliance Infrastructure and Larsen & Toubro into 16 packages, with Megha Engineering and Infrastructure and Navayuga Engineering responsible for two of these packages. The total budget allocated for this project is Rs 450 billion. The state government had also provided a compensatory sum of Rs 69.11 billion to those affected by the project.

The Samruddhi expressway was primarily designed with keen precision to ensure a faster, more efficient journey of eight hours only. The expressway is flanked by four lanes on each side. It has a width of 120 m and a central median of 22.5 m. The expressway is expected to feature extensive landscaping, bridge beautification, enhanced street, and tunnel lighting rainwater harvesting and wayside amenities every 40 km. It offers a speed limit of 150 km per hour on flat terrain and 120 km per hour on an incline. The corridor of the Samruddhi Mahamarg is being built from scratch with minimal demolition of existing structures.

Undoubtedly, the project will prove to be a crucial step for the future success of Maharashtra's rural areas.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

As updated on July 29, 2020, almost as much as 40 per cent work of the Samruddhi Mahamarg has been successfully completed and the highway lane from Igatpuri to Nagpur (623 km) will be operational beginning from December 2021. The construction of the remaining 78 km stretch located in Thane is expected to be postponed by three to four months. It has been reported that quite a few portions of the route in Vidarbha, including 10 new towns, and at least one of the 16 stretches of the road will be ready for commercial use by June 2021. Along the Samruddhi Mahamarg, optical fiber web, natural gas pipelines promoting gas-based industries and solar power projects up to around 250-300 MW will be created. Passing through 10 districts, 26 tehsils, and 390 villages, the gigantic expressway will pave way for the development of around 20 townships and nodes along its way. An eight-phase programme has been set up for the above mentioned by the MSRDC, the organisation responsible for the execution of this project. The first five phases of the same have been completed. It includes geo-referenced mapping, inception, the study of exiting land use and the market demand assessment, drafting a development plan, and preparing the final report. Further, 93 out of 153 structures have been completed in Wardha, 151 out of 199 have been completed in Amravati and 96 out of 209 have been completed in Washim. Despite the lockdown, the construction work of the expressway continued with special permission from the Central Government. The roadside camps where the workers resided were thoroughly sanitised and their COVID-19 tests were conducted, none being positive. However, the pace of the project had dropped as a fraction of the workers left for their hometowns. It was reported that out of 1,699 structures along the 701-km expressway including bridges, tunnels, and flyovers, 662 were completed and 461 were in progress in March 2020. Three of the eight rails-over-bridges and 31 of the 65 major bridges were under construction. Further, 134 minor bridges have been completed while 45 were in progress. Furthermore, 8,311 hectares – which are 86 per cent of the total land required for the Samruddhi Mahamaarg – had been acquired in March 2020. The work has been divided among 14 contractors including giant corporations such as Reliance Infrastructure and Larsen & Toubro into 16 packages, with Megha Engineering and Infrastructure and Navayuga Engineering responsible for two of these packages. The total budget allocated for this project is Rs 450 billion. The state government had also provided a compensatory sum of Rs 69.11 billion to those affected by the project. The Samruddhi expressway was primarily designed with keen precision to ensure a faster, more efficient journey of eight hours only. The expressway is flanked by four lanes on each side. It has a width of 120 m and a central median of 22.5 m. The expressway is expected to feature extensive landscaping, bridge beautification, enhanced street, and tunnel lighting rainwater harvesting and wayside amenities every 40 km. It offers a speed limit of 150 km per hour on flat terrain and 120 km per hour on an incline. The corridor of the Samruddhi Mahamarg is being built from scratch with minimal demolition of existing structures. Undoubtedly, the project will prove to be a crucial step for the future success of Maharashtra's rural areas.

Next Story
Real Estate

Manglam Group to Develop Sheraton Hotel in Jaipur

Manglam Group has signed an agreement with Marriott International to develop a Sheraton hotel on the Jaipur–Ajmer Highway in Jaipur. The project will feature 220 keys and is being developed with an investment of around Rs 3.5 billion across more than 300,000 sq ft.The hotel marks Manglam Group’s third collaboration with Marriott International and forms part of its Rs 10 billion hospitality investment roadmap. The agreement was signed by Amrita Gupta, Director, Manglam Group and CEO, Manglam Spa and Resorts, and Rajeev Menon, President, Asia Pacific excluding Greater China, Marriott Interna..

Next Story
Infrastructure Urban

India Warehousing Show 2026 opens at YashoBhoomi

India's warehousing, logistics, and supply chain ecosystem came together as the 15th edition of India Warehousing Show (IWS) 2026 opened at YashoBhoomi, India International Convention & Expo Centre (IICC), Dwarka, New Delhi on June 25 (Thursday). Organised by RX India, the three-day event will run from 25-27 June 2026, bringing together policymakers, industry leaders, technology providers, and supply chain professionals under one roof. It also features a two-day knowledge conference that will run alongside the exhibition. Inaugurated by Pankaj Kumar, Joint Secretary - Logistics, DPIIT..

Next Story
Real Estate

Platinum Corp Launches Bespoke Presidential Suites

Platinum Corp has launched Platinum Stellar: Bespoke Presidential Suites, a luxury residential project on Main Avenue in Santacruz, Mumbai. The project has been positioned as a boutique, design-led development for high-net-worth individuals, business owners and legacy residents from the Bandra-Khar-Santacruz belt.The project has been developed in collaboration with celebrity interior designer Sussanne Khan and follows a design-first approach inspired by Art Deco architecture. It incorporates refined detailing, spacious layouts, premium material palettes and arrival experiences planned to creat..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement