Road projects awarded in HAM dried up
ROADS & HIGHWAYS

Road projects awarded in HAM dried up

Awards in HAM assets have significantly dried up, the main reasons being delay in promised land acquisition by NHAI and large lead times in obtaining other regulatory clearances.

Source: Equirus Capital

“Average land acquisition costs have spiked from Rs 9.2 million per hectare in FY14 to Rs 23.8 million per hectare in FY18,” says Vijay Agrawal, Executive Director, Equirus Capital. This has created a lot of funding apprehensions where banks are insisting on releasing funds only after the majority of the land is available. He also points out that developers have submitted aggressive bids for HAM projects and have won many more projects than they can finance. 

Public-sector banks, clearly, are wary of funding new road projects. Lenders are asking developers to show upfront project equity before loan sanction or disbursement. This has delayed financial closure (FC) of HAM projects leading to delays. And, in view of delayed FC, NHAI has slowed down HAM bidding and is focussing on EPC bids.

Devayan Dey, Director-Capital Projects and Infrastructure, PWC, views the reasons for financing challenges as fairly clichéd in terms of poor liquidity, poor capacity or credit worthiness of players, hitches around termination clauses, etc. What’s more important, in his opinion, is to understand what led to such a situation. “These reasons are just intermediary outcomes and not the cause,” he explains. “The root cause can be traced back to procurement norms, especially the qualification criteria not having been reformed for over a decade and being easy to bypass. While land acquisition and clearance issues do persist, the issues are amplified when aspiration versus capacity mismatch remains unchecked by procurement filters. Lack of capacity quickly transforms into delivery issues and lenders started losing confidence.” Lenders are not averse to lending unless the balance sheet and capacity of the borrower do not provide enough confidence. However, it is definitely taking more time.


Looking at projects awarded in the past two years, Rajeshwar Burla, Assistant Vice President & Associate Head-Corporate Ratings, ICRA, says,  “HAM and EPC together accounted for over 95 per cent of total awards with EPC accounting for around 50 per cent followed by HAM at around 45 per cent.” He adds that a majority of the Bharatmala programme is proposed to be executed through the EPC route. So, the current award mix is better in terms of private-sector participation compared to the proposed funding plan. 

“As such, from NHAI’s side, currently there are no funding challenges for HAM projects,” Burla confirms. “But as far as funding challenges for developers (concessionaires for BOT-HAM projects) are concerned, he says, “Overall, there has been improvement in acceptance levels for national highway-HAM projects from lenders. The time taken to achieve FC has reduced considerably – by more than 50 per cent from 430 days in FY2016 to 194 days in FY2018. However, FC-related challenges resurfaced given that many PSU banks are under prompt corrective action.” He adds that, increasingly, for new developers taking high exposure to HAM projects, achieving closure could be even more challenging in the current situation. Given the low equity requirement for HAM, lenders are concerned about the developer’s commitment till the end of the concession period, especially given that some developers have limited experience in the development space – many tier-II developers have won HAM projects.

SHRIYAL SETHUMADHAVAN

Awards in HAM assets have significantly dried up, the main reasons being delay in promised land acquisition by NHAI and large lead times in obtaining other regulatory clearances.Source: Equirus Capital“Average land acquisition costs have spiked from Rs 9.2 million per hectare in FY14 to Rs 23.8 million per hectare in FY18,” says Vijay Agrawal, Executive Director, Equirus Capital. This has created a lot of funding apprehensions where banks are insisting on releasing funds only after the majority of the land is available. He also points out that developers have submitted aggressive bids for HAM projects and have won many more projects than they can finance. Public-sector banks, clearly, are wary of funding new road projects. Lenders are asking developers to show upfront project equity before loan sanction or disbursement. This has delayed financial closure (FC) of HAM projects leading to delays. And, in view of delayed FC, NHAI has slowed down HAM bidding and is focussing on EPC bids.Devayan Dey, Director-Capital Projects and Infrastructure, PWC, views the reasons for financing challenges as fairly clichéd in terms of poor liquidity, poor capacity or credit worthiness of players, hitches around termination clauses, etc. What’s more important, in his opinion, is to understand what led to such a situation. “These reasons are just intermediary outcomes and not the cause,” he explains. “The root cause can be traced back to procurement norms, especially the qualification criteria not having been reformed for over a decade and being easy to bypass. While land acquisition and clearance issues do persist, the issues are amplified when aspiration versus capacity mismatch remains unchecked by procurement filters. Lack of capacity quickly transforms into delivery issues and lenders started losing confidence.” Lenders are not averse to lending unless the balance sheet and capacity of the borrower do not provide enough confidence. However, it is definitely taking more time.Looking at projects awarded in the past two years, Rajeshwar Burla, Assistant Vice President & Associate Head-Corporate Ratings, ICRA, says,  “HAM and EPC together accounted for over 95 per cent of total awards with EPC accounting for around 50 per cent followed by HAM at around 45 per cent.” He adds that a majority of the Bharatmala programme is proposed to be executed through the EPC route. So, the current award mix is better in terms of private-sector participation compared to the proposed funding plan. “As such, from NHAI’s side, currently there are no funding challenges for HAM projects,” Burla confirms. “But as far as funding challenges for developers (concessionaires for BOT-HAM projects) are concerned, he says, “Overall, there has been improvement in acceptance levels for national highway-HAM projects from lenders. The time taken to achieve FC has reduced considerably – by more than 50 per cent from 430 days in FY2016 to 194 days in FY2018. However, FC-related challenges resurfaced given that many PSU banks are under prompt corrective action.” He adds that, increasingly, for new developers taking high exposure to HAM projects, achieving closure could be even more challenging in the current situation. Given the low equity requirement for HAM, lenders are concerned about the developer’s commitment till the end of the concession period, especially given that some developers have limited experience in the development space – many tier-II developers have won HAM projects. SHRIYAL SETHUMADHAVAN

Next Story
Infrastructure Urban

PM GatiShakti Reviews Major Road, Rail and Metro Plans

The Network Planning Group (NPG) under the PM GatiShakti initiative has evaluated multiple infrastructure projects spanning road, rail, and metro systems. The review covered two highway projects by the Ministry of Road Transport and Highways (MoRTH), two railway proposals by the Ministry of Railways, and one metro project under the Ministry of Housing and Urban Affairs (MoHUA). According to the Ministry of Commerce and Industry, the projects were assessed for alignment with PM GatiShakti’s principles of integrated multimodal connectivity, last-mile linkage to economic and social hubs, and t..

Next Story
Real Estate

MahaRERA Fast-Tracks 809 Project Approvals Ahead of Diwali

As Diwali 2025 approaches, the Maharashtra Real Estate Regulatory Authority (MahaRERA) is expediting approvals for new housing projects to ensure compliance with legal, technical, and financial standards before launch. The festive season, especially Dussehra and Diwali, traditionally marks a peak period for real estate launches as developers seek to capitalise on auspicious timings and heightened buyer sentiment. This year, MahaRERA has taken a proactive approach to facilitate timely project approvals ahead of the celebrations. A total of 809 project applications were approved recently, cover..

Next Story
Infrastructure Energy

HFCL Bags Rs 2.8 Billion Export Order for Fibre Cables

Telecom equipment manufacturer HFCL has secured an export order worth USD 32.02 million (around Rs 2.8 billion) for the supply of optical fibre cables to an international client. In a regulatory filing, the company stated that the order was received through its wholly owned overseas subsidiary and is scheduled for execution by December 2026. The contract entails the supply of optical fibre cables customised to the client’s specifications, underscoring HFCL’s strong manufacturing expertise and technological capability in the global telecom infrastructure space. This order further strengt..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?