KMRC puts construction of corridor on hold, informs High Court
RAILWAYS & METRO RAIL

KMRC puts construction of corridor on hold, informs High Court

The Kolkata Metro Railway Corporation (KMRC) notified the Calcutta High Court that the construction it had undertaken on the East-West Metro corridor had been stopped due to the incident that took place where numerous houses in the central parts of the city were damaged during tunnel-boring work. 

As reported, about five houses had collapsed because of ground settlement from seepage after a water table had been hit by a tunnel boring machine. It is expected that work will commence again after approval from the court. 

Additionally, several buildings in the Bowbazar locality are now showing cracks and have left a large number of people without homes.

The court, hearing a public interest litigation, sought termination of underground drilling in crowded spaces and asked to be brought up to date of all developments in relation to ground settlement and damage done to buildings. 

It is expected that the state government along with the city civic authorities handle the situation effectively and make sure that affected citizens are looked after. 

The Kolkata Metro Railway Corporation (KMRC) notified the Calcutta High Court that the construction it had undertaken on the East-West Metro corridor had been stopped due to the incident that took place where numerous houses in the central parts of the city were damaged during tunnel-boring work. As reported, about five houses had collapsed because of ground settlement from seepage after a water table had been hit by a tunnel boring machine. It is expected that work will commence again after approval from the court. Additionally, several buildings in the Bowbazar locality are now showing cracks and have left a large number of people without homes.The court, hearing a public interest litigation, sought termination of underground drilling in crowded spaces and asked to be brought up to date of all developments in relation to ground settlement and damage done to buildings. It is expected that the state government along with the city civic authorities handle the situation effectively and make sure that affected citizens are looked after. 

Next Story
Infrastructure Energy

Vedanta Aluminium Uses 1.57 bn Units of Green Energy in FY25

Vedanta Aluminium, India’s largest aluminium producer, recently reported consumption of 1.57 billion units of renewable energy in FY25, marking a significant milestone in its 2030 decarbonisation roadmap. The company also achieved an 8.96 per cent reduction in greenhouse gas (GHG) emissions intensity compared to FY21, reinforcing its leadership in India’s low-carbon manufacturing transition. During FY25, Vedanta Aluminium expanded its renewable energy portfolio through long-term power purchase agreements, strengthening its strategy to source nearly 1,500 MW of renewable power over the lon..

Next Story
Real Estate

Oberoi Group to Develop Luxury Resort at Makaibari Tea Estate

EIH Limited, the flagship company of The Oberoi Group, has announced the signing of a management agreement to develop an Oberoi luxury resort at the iconic Makaibari Tea Estate in Darjeeling. The project marks a key milestone in the Group’s long-term strategy of creating distinctive hospitality experiences in rare and environmentally significant locations. Established in 1859, Makaibari is one of the world’s oldest tea estates and is globally recognised for its Himalayan landscape, primary forests and exceptional biodiversity. Spread across 1,236 acres, the estate houses one of the world..

Next Story
Real Estate

GHV Infra Secures Rs 1.09 Bn EPC Order in Jamshedpur

GHV Infra Projects Ltd, a fast-growing EPC company in India’s infrastructure and construction sector, has recently secured a Rs 1.09 billion work order in Jamshedpur, Jharkhand. Awarded by a reputed group entity, the contract covers end-to-end civil construction, mechanical, electrical and plumbing (MEP) systems, along with high-quality finishing works for a large building development. The project will be executed over a 30-month period, with defined benchmarks for quality, safety and timely delivery. The order strengthens GHV Infra’s footprint in Jamshedpur, a key industrial hub known fo..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App