Balance of System tender floated by NTPC for wind project in Gujarat
POWER & RENEWABLE ENERGY

Balance of System tender floated by NTPC for wind project in Gujarat

NTPC Renewable Energy, a wholly owned subsidiary of NTPC invited bids for a 1,000 MW capacity Balance of System (BoS) package of interstate transmission system (ISTS) connected wind power project. Additionally, for three years, the winning bidder will be responsible for the full operation and upkeep of the system. The design, engineering, manufacturing, supply, erection, testing, and commissioning of the wind projects are all included in the scope of work. Additionally, the contractor is in charge of demonstrating the guaranteed performance parameters beginning with the 33kV internal evacuation lines from the unit substation, pooling substation, central monitoring and control station, wind monitoring masts, and external EHV transmission line until the ISTS substation.

The deadline for proposal submissions is February 28, 2023 and opening of bids will also be held on the same day. The bidders must have completed at least one project with a capacity of 10 MW or more at a single location, with a minimum cumulative wind project capacity of 40 MW. Before the bid opening date, the reference project with a capacity of 10 MW or more has to have been in operation for at least a year.

NTPC Renewable Energy, a wholly owned subsidiary of NTPC invited bids for a 1,000 MW capacity Balance of System (BoS) package of interstate transmission system (ISTS) connected wind power project. Additionally, for three years, the winning bidder will be responsible for the full operation and upkeep of the system. The design, engineering, manufacturing, supply, erection, testing, and commissioning of the wind projects are all included in the scope of work. Additionally, the contractor is in charge of demonstrating the guaranteed performance parameters beginning with the 33kV internal evacuation lines from the unit substation, pooling substation, central monitoring and control station, wind monitoring masts, and external EHV transmission line until the ISTS substation. The deadline for proposal submissions is February 28, 2023 and opening of bids will also be held on the same day. The bidders must have completed at least one project with a capacity of 10 MW or more at a single location, with a minimum cumulative wind project capacity of 40 MW. Before the bid opening date, the reference project with a capacity of 10 MW or more has to have been in operation for at least a year.

Next Story
Equipment

Handling concrete better

Efficiently handling the transportation and placement of concrete is essential to help maintain the quality of construction, meet project timelines by minimising downtimes, and reduce costs – by 5 to 15 per cent, according to Sandeep Jain, Director, Arkade Developers. CW explores what the efficient handling of concrete entails.Select wellFirst, a word on choosing the right equipment, such as a mixer with a capacity aligned to the volume required onsite, from Vaibhav Kulkarni, Concrete Expert. “An overly large mixer will increase the idle time (and cost), while one that ..

Next Story
Real Estate

Elevated floors!

Raised access flooring, also called false flooring, is a less common interiors feature than false ceilings, but it has as many uses – if not more.A raised floor is a modular panel installed above the structural floor. The space beneath the raised flooring is typically used to accommodate utilities such as electrical cables, plumbing and HVAC systems. And so, raised flooring is usually associated with buildings with heavy cabling and precise air distribution needs, such as data centres.That said, CW interacted with designers and architects and discovered that false flooring can come in handy ..

Next Story
Infrastructure Urban

The Variation Challenge

A variation or change in scope clause is defined in construction contracts to take care of situations arising from change in the defined scope of work. Such changes may arise due to factors such as additions or deletions in the scope of work, modifications in the type, grade or specifications of materials, alterations in specifications or drawings, and acts or omissions of other contractors. Further, ineffective planning, inadequate investigations or surveys and requests from the employer or those within the project’s area of influence can contribute to changes in the scope of work. Ext..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?