CERC approves compensation for RSWPL, offset solar duty impact
POWER & RENEWABLE ENERGY

CERC approves compensation for RSWPL, offset solar duty impact

The Central Electricity Regulatory Commission (CERC) has granted approval to ReNew Sun Waves (RSWPL) for compensation, both pre and post the commercial operation date (COD), aimed at mitigating the financial impact of safeguard duty on solar cells/modules and the increased customs duty on solar inverters.

Compensation, to be disbursed at a discounted rate of 9% over a 15-year annuity period, will also cover carrying costs incurred from the date of actual payments to authorities until the issuance of this order.

RSWPL, in response to legislative changes, filed a petition under section 79 of the Electricity Act 2003, seeking approval for a "Change in Law" mechanism to offset financial impacts from safeguard duty on solar cells/modules and increased customs duty on solar inverters.

The company had signed a Power Purchase Agreement (PPA) with Solar Energy Corporation of India (SECI) for a 300 MW solar project in Mandhopura village, Rajasthan.

RSWPL requested remedies following the imposition of safeguard duty on July 29, 2020, and subsequent changes in customs duty on January 6, 2011. The petitioner argued that these events constituted a "Change in Law," justifying compensation to counter increased costs.

Considering the bid date (February 15, 2019), PPA execution (August 13, 2019), and the Scheduled Commercial Operation Date (December 20, 2020), the Commission acknowledged the impact of safeguard duty imposed on July 30, 2020, and new GST rates effective October 1, 2021. These events qualified as a "Change in Law," entitling RSWPL to compensation.

RSWPL contended that the increased costs, resulting from Change in Law events, affected working capital requirements and, consequently, the interest on working capital. The company sought compensation, suggesting an interest rate for carrying costs at 14% per annum or an equivalent rate to the late payment surcharge clause of the PPA.

SECI argued for a 9% interest rate and a 15-year term for loan repayment, while Bihar DISCOMs rejected the interest claim on working capital.

The Commission determined a 9% discount rate and a 15-year annuity period as appropriate for Change in Law compensation. SECI/DISCOMs are liable for monthly annuity payments starting 60 days after this order or claim submission, with late payment surcharge applicable for delays beyond the 60th day.

RSWPL claimed entitlement to carrying costs, opposed by SECI and Bihar DISCOMs. The Commission, citing the PPA and the Supreme Court's Uttar Haryana judgment, ruled in favor of RSWPL's entitlement to compensation (pre- and post-COD), including carrying costs.

The Commission directed contracting parties to reconcile additional expenditure and carrying costs, with DISCOMs obligated to pay SECI reconciled claims, irrespective of DISCOMs' payment to SECI. This decision comes after CERC approved an annual transmission charge of Rs 248.67 million (~$2.98 million) for Apraava Energy's acquisition of Fatehgarh IV Transmission.

The Central Electricity Regulatory Commission (CERC) has granted approval to ReNew Sun Waves (RSWPL) for compensation, both pre and post the commercial operation date (COD), aimed at mitigating the financial impact of safeguard duty on solar cells/modules and the increased customs duty on solar inverters. Compensation, to be disbursed at a discounted rate of 9% over a 15-year annuity period, will also cover carrying costs incurred from the date of actual payments to authorities until the issuance of this order. RSWPL, in response to legislative changes, filed a petition under section 79 of the Electricity Act 2003, seeking approval for a Change in Law mechanism to offset financial impacts from safeguard duty on solar cells/modules and increased customs duty on solar inverters. The company had signed a Power Purchase Agreement (PPA) with Solar Energy Corporation of India (SECI) for a 300 MW solar project in Mandhopura village, Rajasthan. RSWPL requested remedies following the imposition of safeguard duty on July 29, 2020, and subsequent changes in customs duty on January 6, 2011. The petitioner argued that these events constituted a Change in Law, justifying compensation to counter increased costs. Considering the bid date (February 15, 2019), PPA execution (August 13, 2019), and the Scheduled Commercial Operation Date (December 20, 2020), the Commission acknowledged the impact of safeguard duty imposed on July 30, 2020, and new GST rates effective October 1, 2021. These events qualified as a Change in Law, entitling RSWPL to compensation. RSWPL contended that the increased costs, resulting from Change in Law events, affected working capital requirements and, consequently, the interest on working capital. The company sought compensation, suggesting an interest rate for carrying costs at 14% per annum or an equivalent rate to the late payment surcharge clause of the PPA. SECI argued for a 9% interest rate and a 15-year term for loan repayment, while Bihar DISCOMs rejected the interest claim on working capital. The Commission determined a 9% discount rate and a 15-year annuity period as appropriate for Change in Law compensation. SECI/DISCOMs are liable for monthly annuity payments starting 60 days after this order or claim submission, with late payment surcharge applicable for delays beyond the 60th day. RSWPL claimed entitlement to carrying costs, opposed by SECI and Bihar DISCOMs. The Commission, citing the PPA and the Supreme Court's Uttar Haryana judgment, ruled in favor of RSWPL's entitlement to compensation (pre- and post-COD), including carrying costs. The Commission directed contracting parties to reconcile additional expenditure and carrying costs, with DISCOMs obligated to pay SECI reconciled claims, irrespective of DISCOMs' payment to SECI. This decision comes after CERC approved an annual transmission charge of Rs 248.67 million (~$2.98 million) for Apraava Energy's acquisition of Fatehgarh IV Transmission.

Next Story
Infrastructure Energy

South West Pinnacle Wins Rs 30 Cr Oman Mining Contract

South West Pinnacle Exploration Ltd has secured a Rs 30 crore contract from Minerals Development Oman (MDO) for mining exploration in concession areas 12B and 13.The two-year project will be carried out via Alara Resources LLC, a JV in Oman. MDO, backed by Oman’s investment authorities, focuses on monetising mineral wealth.The contract covers copper, gold, and chromite and highlights South West Pinnacle’s growing footprint in international exploration and mining services. ..

Next Story
Equipment

Godrej GEG Boosts Intralogistics with AI and Green Tech

Godrej Enterprises Group (GEG) is revolutionising warehouse and factory logistics through its Material Handling Equipment and Storage Solutions arms by integrating AI, IoT, and automation.With 20–25% market share and 85% local sourcing, GEG champions Atmanirbhar Bharat and sustainability. The Chennai plant, a green manufacturing leader, uses RoHS-compliant materials and has slashed energy consumption by 60%.GEG serves e-commerce, FMCG, retail, and cold chains with high-performance racking and electric forklifts. Upcoming IoT-enabled forklifts and telematics solutions aim to improve speed, sa..

Next Story
Infrastructure Urban

Amit Shah Inaugurates Key Projects Across Gujarat

Union Home Minister Amit Shah inaugurated and laid the foundation stone for various projects in Gujarat’s Panchmahal district and Ahmedabad.In Godhra, he inaugurated the Center of Excellence building, sports complex, reservoir, and Miyawaki plantation. In Ahmedabad, he unveiled a new cooperative complex in Adaroda village and a primary school in Juwal.These projects, under the Model Co-op Village scheme, aim to boost education, sustainability, and rural development across the state. ..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?