CERC approves compensation for RSWPL, offset solar duty impact
POWER & RENEWABLE ENERGY

CERC approves compensation for RSWPL, offset solar duty impact

The Central Electricity Regulatory Commission (CERC) has granted approval to ReNew Sun Waves (RSWPL) for compensation, both pre and post the commercial operation date (COD), aimed at mitigating the financial impact of safeguard duty on solar cells/modules and the increased customs duty on solar inverters.

Compensation, to be disbursed at a discounted rate of 9% over a 15-year annuity period, will also cover carrying costs incurred from the date of actual payments to authorities until the issuance of this order.

RSWPL, in response to legislative changes, filed a petition under section 79 of the Electricity Act 2003, seeking approval for a "Change in Law" mechanism to offset financial impacts from safeguard duty on solar cells/modules and increased customs duty on solar inverters.

The company had signed a Power Purchase Agreement (PPA) with Solar Energy Corporation of India (SECI) for a 300 MW solar project in Mandhopura village, Rajasthan.

RSWPL requested remedies following the imposition of safeguard duty on July 29, 2020, and subsequent changes in customs duty on January 6, 2011. The petitioner argued that these events constituted a "Change in Law," justifying compensation to counter increased costs.

Considering the bid date (February 15, 2019), PPA execution (August 13, 2019), and the Scheduled Commercial Operation Date (December 20, 2020), the Commission acknowledged the impact of safeguard duty imposed on July 30, 2020, and new GST rates effective October 1, 2021. These events qualified as a "Change in Law," entitling RSWPL to compensation.

RSWPL contended that the increased costs, resulting from Change in Law events, affected working capital requirements and, consequently, the interest on working capital. The company sought compensation, suggesting an interest rate for carrying costs at 14% per annum or an equivalent rate to the late payment surcharge clause of the PPA.

SECI argued for a 9% interest rate and a 15-year term for loan repayment, while Bihar DISCOMs rejected the interest claim on working capital.

The Commission determined a 9% discount rate and a 15-year annuity period as appropriate for Change in Law compensation. SECI/DISCOMs are liable for monthly annuity payments starting 60 days after this order or claim submission, with late payment surcharge applicable for delays beyond the 60th day.

RSWPL claimed entitlement to carrying costs, opposed by SECI and Bihar DISCOMs. The Commission, citing the PPA and the Supreme Court's Uttar Haryana judgment, ruled in favor of RSWPL's entitlement to compensation (pre- and post-COD), including carrying costs.

The Commission directed contracting parties to reconcile additional expenditure and carrying costs, with DISCOMs obligated to pay SECI reconciled claims, irrespective of DISCOMs' payment to SECI. This decision comes after CERC approved an annual transmission charge of Rs 248.67 million (~$2.98 million) for Apraava Energy's acquisition of Fatehgarh IV Transmission.

The Central Electricity Regulatory Commission (CERC) has granted approval to ReNew Sun Waves (RSWPL) for compensation, both pre and post the commercial operation date (COD), aimed at mitigating the financial impact of safeguard duty on solar cells/modules and the increased customs duty on solar inverters. Compensation, to be disbursed at a discounted rate of 9% over a 15-year annuity period, will also cover carrying costs incurred from the date of actual payments to authorities until the issuance of this order. RSWPL, in response to legislative changes, filed a petition under section 79 of the Electricity Act 2003, seeking approval for a Change in Law mechanism to offset financial impacts from safeguard duty on solar cells/modules and increased customs duty on solar inverters. The company had signed a Power Purchase Agreement (PPA) with Solar Energy Corporation of India (SECI) for a 300 MW solar project in Mandhopura village, Rajasthan. RSWPL requested remedies following the imposition of safeguard duty on July 29, 2020, and subsequent changes in customs duty on January 6, 2011. The petitioner argued that these events constituted a Change in Law, justifying compensation to counter increased costs. Considering the bid date (February 15, 2019), PPA execution (August 13, 2019), and the Scheduled Commercial Operation Date (December 20, 2020), the Commission acknowledged the impact of safeguard duty imposed on July 30, 2020, and new GST rates effective October 1, 2021. These events qualified as a Change in Law, entitling RSWPL to compensation. RSWPL contended that the increased costs, resulting from Change in Law events, affected working capital requirements and, consequently, the interest on working capital. The company sought compensation, suggesting an interest rate for carrying costs at 14% per annum or an equivalent rate to the late payment surcharge clause of the PPA. SECI argued for a 9% interest rate and a 15-year term for loan repayment, while Bihar DISCOMs rejected the interest claim on working capital. The Commission determined a 9% discount rate and a 15-year annuity period as appropriate for Change in Law compensation. SECI/DISCOMs are liable for monthly annuity payments starting 60 days after this order or claim submission, with late payment surcharge applicable for delays beyond the 60th day. RSWPL claimed entitlement to carrying costs, opposed by SECI and Bihar DISCOMs. The Commission, citing the PPA and the Supreme Court's Uttar Haryana judgment, ruled in favor of RSWPL's entitlement to compensation (pre- and post-COD), including carrying costs. The Commission directed contracting parties to reconcile additional expenditure and carrying costs, with DISCOMs obligated to pay SECI reconciled claims, irrespective of DISCOMs' payment to SECI. This decision comes after CERC approved an annual transmission charge of Rs 248.67 million (~$2.98 million) for Apraava Energy's acquisition of Fatehgarh IV Transmission.

Next Story
Equipment

Caterpillar Debuts Three New Cat Excavators at EXCON 2025

Caterpillar Inc., a global leader in construction and mining machinery, strengthened its commitment to India’s infrastructure growth with the debut of three new Cat® hydraulic excavators at EXCON 2025, held from December 9–13 at the Bangalore International Exhibition Centre. The new models—Cat 321, Cat 322 and Cat 324—mark a significant step forward in delivering efficient, digital-ready equipment tailored for India’s evolving construction needs.Designed to support sustainability and productivity on modern jobsites, the machines feature advanced powertrains and intelligent electrohy..

Next Story
Equipment

JK Tyre Expands OTR Lineup with Four New Launches at EXCON 2025

JK Tyre & Industries, one of India’s leading tyre manufacturers, introduced four new Off-the-Road (OTR) tyres at the 13th edition of CII EXCON 2025, South Asia’s largest construction equipment exhibition, underway at the Bangalore International Exhibition Centre. The latest additions strengthen the company’s OTR portfolio and reaffirm its focus on delivering advanced mobility solutions for construction, mining and industrial operations.The new tyres were unveiled by R Mukhopadhyay, Director (R&D), JK Tyre. Among the highlights was the debut of the SKY GRIP, a specialised tyre des..

Next Story
Equipment

ACE, Sanghvi Movers Ink MOU to Boost India-Made Heavy Crane Adoption

Action Construction Equipment (ACE), the world’s largest pick-and-carry crane manufacturer and a leading Indian construction equipment maker, has entered into a strategic Memorandum of Understanding with Sanghvi Movers, Asia’s largest and the world’s fifth-largest crane rental company. The partnership aims to accelerate the deployment of indigenously manufactured heavy slew cranes, particularly truck cranes and crawler cranes, across large-scale infrastructure and industrial projects in India.The alliance aligns strongly with the Government of India’s “Aatmanirbhar Bharat” and “M..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App