CERC approves compensation for RSWPL, offset solar duty impact
POWER & RENEWABLE ENERGY

CERC approves compensation for RSWPL, offset solar duty impact

The Central Electricity Regulatory Commission (CERC) has granted approval to ReNew Sun Waves (RSWPL) for compensation, both pre and post the commercial operation date (COD), aimed at mitigating the financial impact of safeguard duty on solar cells/modules and the increased customs duty on solar inverters.

Compensation, to be disbursed at a discounted rate of 9% over a 15-year annuity period, will also cover carrying costs incurred from the date of actual payments to authorities until the issuance of this order.

RSWPL, in response to legislative changes, filed a petition under section 79 of the Electricity Act 2003, seeking approval for a "Change in Law" mechanism to offset financial impacts from safeguard duty on solar cells/modules and increased customs duty on solar inverters.

The company had signed a Power Purchase Agreement (PPA) with Solar Energy Corporation of India (SECI) for a 300 MW solar project in Mandhopura village, Rajasthan.

RSWPL requested remedies following the imposition of safeguard duty on July 29, 2020, and subsequent changes in customs duty on January 6, 2011. The petitioner argued that these events constituted a "Change in Law," justifying compensation to counter increased costs.

Considering the bid date (February 15, 2019), PPA execution (August 13, 2019), and the Scheduled Commercial Operation Date (December 20, 2020), the Commission acknowledged the impact of safeguard duty imposed on July 30, 2020, and new GST rates effective October 1, 2021. These events qualified as a "Change in Law," entitling RSWPL to compensation.

RSWPL contended that the increased costs, resulting from Change in Law events, affected working capital requirements and, consequently, the interest on working capital. The company sought compensation, suggesting an interest rate for carrying costs at 14% per annum or an equivalent rate to the late payment surcharge clause of the PPA.

SECI argued for a 9% interest rate and a 15-year term for loan repayment, while Bihar DISCOMs rejected the interest claim on working capital.

The Commission determined a 9% discount rate and a 15-year annuity period as appropriate for Change in Law compensation. SECI/DISCOMs are liable for monthly annuity payments starting 60 days after this order or claim submission, with late payment surcharge applicable for delays beyond the 60th day.

RSWPL claimed entitlement to carrying costs, opposed by SECI and Bihar DISCOMs. The Commission, citing the PPA and the Supreme Court's Uttar Haryana judgment, ruled in favor of RSWPL's entitlement to compensation (pre- and post-COD), including carrying costs.

The Commission directed contracting parties to reconcile additional expenditure and carrying costs, with DISCOMs obligated to pay SECI reconciled claims, irrespective of DISCOMs' payment to SECI. This decision comes after CERC approved an annual transmission charge of Rs 248.67 million (~$2.98 million) for Apraava Energy's acquisition of Fatehgarh IV Transmission.

The Central Electricity Regulatory Commission (CERC) has granted approval to ReNew Sun Waves (RSWPL) for compensation, both pre and post the commercial operation date (COD), aimed at mitigating the financial impact of safeguard duty on solar cells/modules and the increased customs duty on solar inverters. Compensation, to be disbursed at a discounted rate of 9% over a 15-year annuity period, will also cover carrying costs incurred from the date of actual payments to authorities until the issuance of this order. RSWPL, in response to legislative changes, filed a petition under section 79 of the Electricity Act 2003, seeking approval for a Change in Law mechanism to offset financial impacts from safeguard duty on solar cells/modules and increased customs duty on solar inverters. The company had signed a Power Purchase Agreement (PPA) with Solar Energy Corporation of India (SECI) for a 300 MW solar project in Mandhopura village, Rajasthan. RSWPL requested remedies following the imposition of safeguard duty on July 29, 2020, and subsequent changes in customs duty on January 6, 2011. The petitioner argued that these events constituted a Change in Law, justifying compensation to counter increased costs. Considering the bid date (February 15, 2019), PPA execution (August 13, 2019), and the Scheduled Commercial Operation Date (December 20, 2020), the Commission acknowledged the impact of safeguard duty imposed on July 30, 2020, and new GST rates effective October 1, 2021. These events qualified as a Change in Law, entitling RSWPL to compensation. RSWPL contended that the increased costs, resulting from Change in Law events, affected working capital requirements and, consequently, the interest on working capital. The company sought compensation, suggesting an interest rate for carrying costs at 14% per annum or an equivalent rate to the late payment surcharge clause of the PPA. SECI argued for a 9% interest rate and a 15-year term for loan repayment, while Bihar DISCOMs rejected the interest claim on working capital. The Commission determined a 9% discount rate and a 15-year annuity period as appropriate for Change in Law compensation. SECI/DISCOMs are liable for monthly annuity payments starting 60 days after this order or claim submission, with late payment surcharge applicable for delays beyond the 60th day. RSWPL claimed entitlement to carrying costs, opposed by SECI and Bihar DISCOMs. The Commission, citing the PPA and the Supreme Court's Uttar Haryana judgment, ruled in favor of RSWPL's entitlement to compensation (pre- and post-COD), including carrying costs. The Commission directed contracting parties to reconcile additional expenditure and carrying costs, with DISCOMs obligated to pay SECI reconciled claims, irrespective of DISCOMs' payment to SECI. This decision comes after CERC approved an annual transmission charge of Rs 248.67 million (~$2.98 million) for Apraava Energy's acquisition of Fatehgarh IV Transmission.

Next Story
Infrastructure Urban

World Bank Backs Rs 1.77 Billion Project to Aid Coastal Communities

The World Bank has approved a new programme to support coastal communities in India by conserving ecosystems, reducing plastic pollution and creating jobs for 100,000 people in Tamil Nadu and Karnataka.The $212.64 million (around Rs 1.77 billion) Strengthening Coastal Resilience and the Economy (SHORE) project is part of the $850 million (around Rs 7.08 billion) SHORE programme launched by the World Bank to address challenges faced by coastal populations.India has a coastline stretching over 11,000 km, with one-third vulnerable to erosion and extreme climate events. Approximately 250 million p..

Next Story
Infrastructure Urban

Meghalaya’s Smart City Projects Achieve 78 per cent Progress by July

The Meghalaya government has made significant progress in implementing projects under the Smart City Mission, achieving an overall physical completion of 77.81 per cent as of July this year. Deputy Chief Minister Sniawbhalang Dhar informed the Assembly of this update.VPP legislator Ardent Basaiawmoit raised concerns that the government is focusing primarily on constructing commercial complexes, which he argued is contrary to the mission’s objective of improving living conditions, including education and other sectors.Dhar acknowledged that this may have been the case in the first phase but a..

Next Story
Infrastructure Transport

Mazagon Dock Begins Talks for Rs 9.3 Billion Submarine Project

Mazagon Dock Shipbuilders Ltd on Wednesday (10 September) announced that it has commenced negotiations with the Indian Navy for the long-delayed submarine programme Project P-75(I).The move follows approval from the Ministry of Defence in August, permitting the state-run shipbuilder to begin cost discussions with Germany’s Thyssenkrupp Marine Systems for building six conventional submarines, in a deal valued at nearly Rs 9.3 billion. Sources had earlier informed CNBC-TV18 that the contract is expected to be awarded to Mazagon Dock and Thyssenkrupp about six months after the successful comple..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?