CERC Proposes Stricter Grid Deviation Rules for Renewable Projects
POWER & RENEWABLE ENERGY

CERC Proposes Stricter Grid Deviation Rules for Renewable Projects

The Central Electricity Regulatory Commission (CERC) has proposed amendments to the deviation settlement mechanism (DSM) for wind, solar, and hybrid projects, effective April 2026, in a move aimed at strengthening grid stability.

The regulator has suggested shifting the DSM calculation from available capacity to scheduled generation. From 2026, deviations will be computed using the formula:

Dws% = 100 x [(Actual Injection – Scheduled Generation) / (X% of Available Capacity + (100-X)% of Scheduled Generation)]

CERC has proposed a phased reduction of the ‘x’ value from 100% in 2026 to 0% by 2031, which would increase deviation charges for renewable energy generators over time.

The DSM tolerance bands will also be narrowed—from ±15% to ±10% for wind projects, and from ±10% to ±5% for solar projects.

A Grid-India study across 16 renewable projects showed the tightening could significantly increase deviation incidents. Solar projects may face 3.5–11.1% revenue losses, hybrid projects 2.4–11.8%, while wind projects could see losses as high as 48.2% due to higher variability.

To mitigate such impacts, CERC suggested better forecasting, aggregation of projects, and operational discipline. Additionally, wind and solar projects will not be compensated for over-injections when grid frequency exceeds 50.05 Hz.

The Commission has invited stakeholder comments on the proposal until October 5, 2025.

News source: Mercom India

The Central Electricity Regulatory Commission (CERC) has proposed amendments to the deviation settlement mechanism (DSM) for wind, solar, and hybrid projects, effective April 2026, in a move aimed at strengthening grid stability.The regulator has suggested shifting the DSM calculation from available capacity to scheduled generation. From 2026, deviations will be computed using the formula:Dws% = 100 x [(Actual Injection – Scheduled Generation) / (X% of Available Capacity + (100-X)% of Scheduled Generation)]CERC has proposed a phased reduction of the ‘x’ value from 100% in 2026 to 0% by 2031, which would increase deviation charges for renewable energy generators over time.The DSM tolerance bands will also be narrowed—from ±15% to ±10% for wind projects, and from ±10% to ±5% for solar projects.A Grid-India study across 16 renewable projects showed the tightening could significantly increase deviation incidents. Solar projects may face 3.5–11.1% revenue losses, hybrid projects 2.4–11.8%, while wind projects could see losses as high as 48.2% due to higher variability.To mitigate such impacts, CERC suggested better forecasting, aggregation of projects, and operational discipline. Additionally, wind and solar projects will not be compensated for over-injections when grid frequency exceeds 50.05 Hz.The Commission has invited stakeholder comments on the proposal until October 5, 2025.News source: Mercom India

Next Story
Infrastructure Transport

India Becomes First to Produce Bio-Bitumen for Roads

India has become the first country in the world to commercially produce bio-bitumen for use in road construction, according to Road, Transport and Highways Minister Nitin Gadkari. Bitumen, a black and viscous hydrocarbon derived from crude oil, is a key binding material in road building, and the bio-based alternative is expected to significantly improve the sector’s environmental footprint.Addressing the CSIR Technology Transfer Ceremony in New Delhi, Mr Gadkari congratulated Council of Scientific and Industrial Research on achieving the milestone, noting that the initiative would help curb ..

Next Story
Infrastructure Urban

HILT Policy Seen Boosting Telangana Revenue Sharply

The Hyderabad Industrial Land Transformation (HILT) Policy is expected to generate around Rs 1.08 billion in revenue for the Telangana state exchequer, according to Deputy Chief Minister Bhatti Vikramarka Mallu. Speaking in the Telangana Legislative Assembly, he said the policy would be implemented within a six-month timeframe in a transparent manner, with uniform rules applicable to all stakeholders. Mr Vikramarka noted that without the HILT Policy, the state would have earned only about Rs 1.2 million per acre. Under the new framework, however, revenue is projected to rise sharply to Rs 70 ..

Next Story
Infrastructure Urban

India Post, MoRD Tie Up to Boost Rural Inclusion

The Department of Posts and the Ministry of Rural Development have signed a Memorandum of Understanding to accelerate rural transformation and expand financial, digital and logistics services for Self-Help Groups (SHGs) and rural households across India. The agreement was signed in the presence of Union Minister of Communications and Development of North Eastern Region Jyotiraditya M. Scindia and Union Minister of Rural Development and Agriculture and Farmers’ Welfare Shivraj Singh Chouhan. The collaboration aligns with the government’s “Dak Sewa, Jan Sewa” vision and seeks to repositi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App