+
Goa and four UTs fail to adhere to renewable purchase obligations
POWER & RENEWABLE ENERGY

Goa and four UTs fail to adhere to renewable purchase obligations

According to the Joint Electricity Regulatory Commission's (JERC's) analysis, besides Andaman & Nicobar Islands and Chandigarh, all other union territories (UT) and Goa have failed to accomplish their solar renewable purchase obligation (RPO) targets for 2020-21.

The information was collected from the electricity departments of Goa, Daman & Diu, Dadra & Nagar Haveli, Andaman & Nicobar Islands, and Chandigarh.

JERC told the media that it had received data on the RPO agreement for FY21 from six union territories and their strategies to reach their targets for FY22.

Goa:

After reviewing the reports, the commission noted that Goa reached its non-solar RPO target for FY20. However, it had a 66.94 MU shortfall in accomplishing its solar RPO targets.

JERC instructed the state to achieve full compliance for solar and non-solar RPO in FY 2021-22. However, because of the impact of Covid-19 and nationwide lockdown, these projects have been delayed.

Puducherry:

JERC noticed that the UT had not achieved its solar and non-solar RPO targets for FY21 and had a backlog of 472.15 MU and 561.37 MU, respectively.

After examining the action plan, JERC directed the electricity department to facilitate the procedure of buying actual power available.

The Commission further underlined the huge backlog. It warned the department that JERC would take appropriate legal action for non-compliance if this proceeded.

Daman & Diu:

The information submitted by the electricity department of Daman & Diu revealed that it had not completed its solar and non-solar RPO target for FY21. Just 36.64 MU of its 311.85 MU solar RPO targets and 192.88 MU of its 436.93 MU non-solar RPO targets were met.

The commission emphasised that the UT has a large backlog at the FY21 end. It also advised the department to get physical renewable energy power in each quarter of 2021-22 to decrease the total shortfall in FY22.

Dadra & Nagar Haveli:

In Dadra & Nagar Haveli, JERC noted there is a 1,319.3 MU shortfall in RPO for FY 2020-21, with backlogs.

The solar RPO target was 577.44 MU, though only 54.90 MU was achieved. Moreover, only 26.28 MU of its 823.04 MU of non-solar RPO target was accomplished.

The Commission examined UT's action plan for FY22 and believed that if the action plan is successfully executed then it could comply with its RPO targets.

Chandigarh:

After reviewing the department’s report, JERC noted that the UT had overachieved its solar RPO target by 33.70 MU for FY21.

But, there was zero compliance for the non-solar RPO target, because of which solar RPO achieved the entire non-solar target of 24.02 MU.

The commission evaluated the action plan proposed by the department and decided that if done successfully, the UT would be able to complete its whole target for FY 2021-22.

Andaman & Nicobar Islands:

The commission cited that even Andaman & Nicobar Islands had also overachieved its solar RPO targets by 3.24 MU. However, there was a non-solar RPO target shortfall of 19.59 MU.

After examining its Action Plan, it has also advised the department to expand its efforts to reach its solar and non-solar RPO targets for FY22.

Lakshadweep:

The Lakshadweep electricity department report revealed that it could not reach its solar and non-solar RPO targets for FY 2020-21 and has a total shortfall of 16.72 MU.

JERC showed disapproval because of the under accomplishment of RPO targets. Furthermore, it directed the department to submit its action plan in a week from the issued date of this order.

In JERC's analysis of RPO targets for FY20, the commission pointed out that only Chandigarh overachieved its RPO target by 2.66 MU.

India aims to accomplish 175 GW of renewable energy by 2022 would be unattainable without the RPO, which has single-handedly made the growth of solar and other renewables since its establishment in 2010.

Image Source


Also read: Maharashtra electricity body rejects plea to offset renewable RPO

Also read: Surplus solar power by Gujarat discoms to be compensated at Rs 2.25/kWh

According to the Joint Electricity Regulatory Commission's (JERC's) analysis, besides Andaman & Nicobar Islands and Chandigarh, all other union territories (UT) and Goa have failed to accomplish their solar renewable purchase obligation (RPO) targets for 2020-21. The information was collected from the electricity departments of Goa, Daman & Diu, Dadra & Nagar Haveli, Andaman & Nicobar Islands, and Chandigarh. JERC told the media that it had received data on the RPO agreement for FY21 from six union territories and their strategies to reach their targets for FY22. Goa: After reviewing the reports, the commission noted that Goa reached its non-solar RPO target for FY20. However, it had a 66.94 MU shortfall in accomplishing its solar RPO targets. JERC instructed the state to achieve full compliance for solar and non-solar RPO in FY 2021-22. However, because of the impact of Covid-19 and nationwide lockdown, these projects have been delayed. Puducherry: JERC noticed that the UT had not achieved its solar and non-solar RPO targets for FY21 and had a backlog of 472.15 MU and 561.37 MU, respectively. After examining the action plan, JERC directed the electricity department to facilitate the procedure of buying actual power available. The Commission further underlined the huge backlog. It warned the department that JERC would take appropriate legal action for non-compliance if this proceeded. Daman & Diu: The information submitted by the electricity department of Daman & Diu revealed that it had not completed its solar and non-solar RPO target for FY21. Just 36.64 MU of its 311.85 MU solar RPO targets and 192.88 MU of its 436.93 MU non-solar RPO targets were met. The commission emphasised that the UT has a large backlog at the FY21 end. It also advised the department to get physical renewable energy power in each quarter of 2021-22 to decrease the total shortfall in FY22. Dadra & Nagar Haveli: In Dadra & Nagar Haveli, JERC noted there is a 1,319.3 MU shortfall in RPO for FY 2020-21, with backlogs. The solar RPO target was 577.44 MU, though only 54.90 MU was achieved. Moreover, only 26.28 MU of its 823.04 MU of non-solar RPO target was accomplished. The Commission examined UT's action plan for FY22 and believed that if the action plan is successfully executed then it could comply with its RPO targets. Chandigarh: After reviewing the department’s report, JERC noted that the UT had overachieved its solar RPO target by 33.70 MU for FY21. But, there was zero compliance for the non-solar RPO target, because of which solar RPO achieved the entire non-solar target of 24.02 MU. The commission evaluated the action plan proposed by the department and decided that if done successfully, the UT would be able to complete its whole target for FY 2021-22. Andaman & Nicobar Islands: The commission cited that even Andaman & Nicobar Islands had also overachieved its solar RPO targets by 3.24 MU. However, there was a non-solar RPO target shortfall of 19.59 MU. After examining its Action Plan, it has also advised the department to expand its efforts to reach its solar and non-solar RPO targets for FY22. Lakshadweep: The Lakshadweep electricity department report revealed that it could not reach its solar and non-solar RPO targets for FY 2020-21 and has a total shortfall of 16.72 MU. JERC showed disapproval because of the under accomplishment of RPO targets. Furthermore, it directed the department to submit its action plan in a week from the issued date of this order. In JERC's analysis of RPO targets for FY20, the commission pointed out that only Chandigarh overachieved its RPO target by 2.66 MU. India aims to accomplish 175 GW of renewable energy by 2022 would be unattainable without the RPO, which has single-handedly made the growth of solar and other renewables since its establishment in 2010. Image Source Also read: Maharashtra electricity body rejects plea to offset renewable RPO Also read: Surplus solar power by Gujarat discoms to be compensated at Rs 2.25/kWh

Next Story
Real Estate

DLF Returns to Mumbai with Premium Andheri Residential Project

Delhi-NCR based real estate major DLF announced its return to the Mumbai market on 17 July with the launch of its premium residential project, The WestPark, in Andheri. The first phase includes 416 apartments spread across four towers, with two towers launched on the announcement day. The company plans to invest over Rs 8 billion in the project and expects a topline exceeding Rs 20 billion from Phase 1.“We have launched two towers and, given the strong response, plan to unveil the remaining two towers ahead of schedule, within the next few days,” said Aakash Ohri, Joint Managing Director o..

Next Story
Infrastructure Urban

APCRDA Advances Net Zero Goal with IGBC Training for Officials

In a significant stride towards Andhra Pradesh’s Net Zero target by 2040 and the Swarna Andhra 2047 vision, the Andhra Pradesh Capital Region Development Authority (APCRDA), in partnership with the Indian Green Building Council (IGBC), conducted a high-level capacity-building programme for senior officials in Vijayawada on Friday.Held at a city hotel, the session saw the participation of over 50 senior APCRDA officials, including the Engineer-in-Chief, Chief Engineer (H&B), Director (Planning), Director (Environment), and heads of key departments. The training centred on IGBC’s Green B..

Next Story
Infrastructure Energy

Assam Solar Project Halted as Waaree EPC Contract Is Cancelled

Following the Assam government’s withdrawal from its proposed solar project, the Engineering, Procurement, and Construction (EPC) contract awarded to Waaree Renewable has been suspended. Waaree Group’s EPC division informed the stock exchange of this development through a regulatory filing.The Assam solar project was suspended due to funding challenges, which rendered the initiative unviable for the state government. Waaree Renewable Transmission Limited (RTL) explained that the Government of Assam has withdrawn the project’s funding via the Asian Development Bank (ADB) loan. Consequentl..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?