New Wanpoh Substation Project Extended to June 2027
POWER & RENEWABLE ENERGY

New Wanpoh Substation Project Extended to June 2027

Power Grid Corporation of India (PGCIL) has been granted an 18-month extension for completing the New Wanpoh substation augmentation project in Jammu & Kashmir.
The Central Transmission Utility of India (CTUIL) revised the project’s completion date to 30 June 2027, from the earlier 31 December 2025. The project involves augmenting PGCIL’s 400/220kV New Wanpoh substation with a new 400/220kV, 315 MVA interconnecting transformer (3×105 MVA) and two transformer bays—one each at 400kV and 220kV. The project, estimated at Rs 610 million, was awarded under the regulated tariff mechanism (RTM) on 22 March 2024 with an initial 21-month timeline.
PGCIL cited challenges in awarding the substation extension contract. Despite floating tenders in July 2024 and granting 17 extensions, no bids were received by December 2024. Commissioned in 2014, the New Wanpoh substation is a critical interstate transmission system (ISTS) element, linking the Kashmir Valley to the National Grid and forming part of the Northern Region System Strengthening Scheme – XVI.

Power Grid Corporation of India (PGCIL) has been granted an 18-month extension for completing the New Wanpoh substation augmentation project in Jammu & Kashmir.The Central Transmission Utility of India (CTUIL) revised the project’s completion date to 30 June 2027, from the earlier 31 December 2025. The project involves augmenting PGCIL’s 400/220kV New Wanpoh substation with a new 400/220kV, 315 MVA interconnecting transformer (3×105 MVA) and two transformer bays—one each at 400kV and 220kV. The project, estimated at Rs 610 million, was awarded under the regulated tariff mechanism (RTM) on 22 March 2024 with an initial 21-month timeline.PGCIL cited challenges in awarding the substation extension contract. Despite floating tenders in July 2024 and granting 17 extensions, no bids were received by December 2024. Commissioned in 2014, the New Wanpoh substation is a critical interstate transmission system (ISTS) element, linking the Kashmir Valley to the National Grid and forming part of the Northern Region System Strengthening Scheme – XVI.

Next Story
Infrastructure Energy

Adani Power To Build 2,400 MW Plant in Bihar

Adani Power on Saturday (September 13, 2025) announced plans to set up a 2,400 MW ultra super-critical power plant in Bihar at an investment of $3 billion (around Rs 26.48 billion).The company has signed a 25-year Power Supply Agreement (PSA) with Bihar State Power Generation Company Ltd (BSPGCL) to supply electricity from the project, which will be located at Pirpainti in Bhagalpur district.The PSA follows a Letter of Award issued by BSPGCL to Adani Power on behalf of North Bihar Power Distribution Company Ltd (NBPDCL) and South Bihar Power Distribution Company Ltd (SBPDCL) in August. Adani P..

Next Story
Infrastructure Energy

NTPC Plans Nuclear Power Projects Via JV and Standalone Routes

Power major NTPC is planning to develop nuclear power projects both through joint ventures and on a standalone basis, CMD Gurdeep Singh has said.The company is collaborating with nuclear technology providers and state governments to explore individual nuclear projects, Singh added.Currently, the NTPC Group has an installed capacity of 82,926 MW across 53 NTPC-owned stations and 53 joint venture or subsidiary stations, drawing power from coal, liquid fuel, hydro, and solar sources.In December 2024, Singh had announced NTPC’s ambitious plan to enter the nuclear energy sector, a move expected t..

Next Story
Infrastructure Transport

RVNL Wins $21.6 Million Bhopal Division Traction Substation

Rail Vikas Nigam (RVNL) has been declared the lowest bidder for a $21.6 million traction substation contract awarded by the West Central Railway.The project covers the design, modification, supply, erection, testing, and commissioning of a 220/132kV/2×25kV Scott-connected traction substation, switching posts, Auto-Transformer installations, and Supervisory Control and Data Acquisition (SCADA) systems in the Bina–RTA section of the Bhopal Division. The execution period is set at 540 days.In a regulatory filing, RVNL stated that the order was secured in the ordinary course of business and doe..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?