+
Poringalkuthu project of 24 MW to be operational by April
POWER & RENEWABLE ENERGY

Poringalkuthu project of 24 MW to be operational by April

The Poringalkuthu small hydroelectric project (SHEP), with a capacity of 24 megawatts (MW), is expected to be completed in April, which will help to meet the increased demand for electricity during the summer months.

Civil work associated with the project is now complete.The turbine was tested on Sunday, and the remaining tests will be conducted soon, according to officials from the Kerala State Electricity Board (KSEB). According to the Power Department, the Poringalkuthu SHEP will be the first hydro project of its size to be commissioned in nearly a decade.

The Poringalkuthu SHEP, which will be built in the Chalakkudy basin, received its initial contract in October 2014 and was expected to be completed in 24 months. However, delays in transferring forestland to the contractor, the 2018 and 2019 floods, and the Covid-19 pandemic all hampered the project, forcing the KSEB to extend deadlines multiple times. Poringalkuthu SHEP has a 45.02 million units (mu) annual generation capacity and a project cost of 159.19 crore.

Aside from Poringalkuthu, the 60 MW Pallivasal Extension Scheme, the 40 MW Thottiyar, and the 24 Bhoothathankettu schemes should all be completed by 2022-23 if all goes well. Work on all three projects was pushed back due to a variety of factors.

The KSEB had a total installed capacity of 2,240.22 MW as of March 31, 2021, with hydel projects accounting for 91%, thermal 7.14%, and solar and wind projects accounting for the rest. The KSEB owns 40 hydroelectric generating stations, 17 of which are major.

Four hydroelectric projects with varying capacities, which have been delayed, are expected to be completed in the fiscal year 2022-23, increasing the State's internal power generation capability.

Image Source

Also read: Policy for stalled private hydro projects likely for takeover

The Poringalkuthu small hydroelectric project (SHEP), with a capacity of 24 megawatts (MW), is expected to be completed in April, which will help to meet the increased demand for electricity during the summer months. Civil work associated with the project is now complete.The turbine was tested on Sunday, and the remaining tests will be conducted soon, according to officials from the Kerala State Electricity Board (KSEB). According to the Power Department, the Poringalkuthu SHEP will be the first hydro project of its size to be commissioned in nearly a decade. The Poringalkuthu SHEP, which will be built in the Chalakkudy basin, received its initial contract in October 2014 and was expected to be completed in 24 months. However, delays in transferring forestland to the contractor, the 2018 and 2019 floods, and the Covid-19 pandemic all hampered the project, forcing the KSEB to extend deadlines multiple times. Poringalkuthu SHEP has a 45.02 million units (mu) annual generation capacity and a project cost of 159.19 crore. Aside from Poringalkuthu, the 60 MW Pallivasal Extension Scheme, the 40 MW Thottiyar, and the 24 Bhoothathankettu schemes should all be completed by 2022-23 if all goes well. Work on all three projects was pushed back due to a variety of factors. The KSEB had a total installed capacity of 2,240.22 MW as of March 31, 2021, with hydel projects accounting for 91%, thermal 7.14%, and solar and wind projects accounting for the rest. The KSEB owns 40 hydroelectric generating stations, 17 of which are major. Four hydroelectric projects with varying capacities, which have been delayed, are expected to be completed in the fiscal year 2022-23, increasing the State's internal power generation capability. Image Source Also read: Policy for stalled private hydro projects likely for takeover

Related Stories

Gold Stories

Next Story
Infrastructure Transport

97 Per Cent Of Rongjeng-Mangsang-Adokgre Road Nears Completion

Deputy Chief Minister in-charge of public works Prestone Tynsong said in Shillong on 26 August that 97 per cent physical progress had been achieved on the ongoing Rongjeng-Mangsang-Adokgre road being constructed under the Non-Lapsable Central Pool of Resources (NLCPR). He noted the project was sanctioned in 2017 and that the stipulated time for completion had been 24 months from issue of the final work order. The deputy chief minister informed the assembly that the government had decided to include the remaining work under a World Bank project. In reply to a query from Rongjeng MLA Jim M Sangm..

Next Story
Infrastructure Transport

First TBM Starts Digging Five Point Three Kilometre Tunnel Under SGNP

The Goregaon-Mulund Link Road (GMLR) Phase three (B) project has reached a key milestone as the first tunnel boring machine (TBM) began excavation of the first of two tunnels beneath the Sanjay Gandhi National Park (SGNP). The machine, named Tulsi, started cutting a five point three kilometre bore that will link Dadasaheb Phalke Chitranagari in Goregaon East with Amar Nagar in Mulund West. Officials issued a statement noting the commencement of tunnelling work under the protected green belt. The twin tunnels are being constructed using mechanised tunnelling methods that aim to limit surface di..

Next Story
Infrastructure Transport

UP Approves Two Expressways And Rs 240 bn Infrastructure Push

The Uttar Pradesh Cabinet approved a series of infrastructure and industrial investment proposals totalling Rs 240 billion (Rs 240 bn), including two major expressway projects, a manufacturing and logistics cluster in Sultanpur and incentives for 11 industrial projects across the state. The decisions, taken at a meeting chaired by Chief Minister Yogi Adityanath, underline the state government’s focus on expanding road connectivity around emerging industrial hubs while attracting manufacturing investment to districts beyond major urban centres. The approvals cover both greenfield expressway c..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code