Poringalkuthu project of 24 MW to be operational by April
POWER & RENEWABLE ENERGY

Poringalkuthu project of 24 MW to be operational by April

The Poringalkuthu small hydroelectric project (SHEP), with a capacity of 24 megawatts (MW), is expected to be completed in April, which will help to meet the increased demand for electricity during the summer months.

Civil work associated with the project is now complete.The turbine was tested on Sunday, and the remaining tests will be conducted soon, according to officials from the Kerala State Electricity Board (KSEB). According to the Power Department, the Poringalkuthu SHEP will be the first hydro project of its size to be commissioned in nearly a decade.

The Poringalkuthu SHEP, which will be built in the Chalakkudy basin, received its initial contract in October 2014 and was expected to be completed in 24 months. However, delays in transferring forestland to the contractor, the 2018 and 2019 floods, and the Covid-19 pandemic all hampered the project, forcing the KSEB to extend deadlines multiple times. Poringalkuthu SHEP has a 45.02 million units (mu) annual generation capacity and a project cost of 159.19 crore.

Aside from Poringalkuthu, the 60 MW Pallivasal Extension Scheme, the 40 MW Thottiyar, and the 24 Bhoothathankettu schemes should all be completed by 2022-23 if all goes well. Work on all three projects was pushed back due to a variety of factors.

The KSEB had a total installed capacity of 2,240.22 MW as of March 31, 2021, with hydel projects accounting for 91%, thermal 7.14%, and solar and wind projects accounting for the rest. The KSEB owns 40 hydroelectric generating stations, 17 of which are major.

Four hydroelectric projects with varying capacities, which have been delayed, are expected to be completed in the fiscal year 2022-23, increasing the State's internal power generation capability.

Image Source

Also read: Policy for stalled private hydro projects likely for takeover

The Poringalkuthu small hydroelectric project (SHEP), with a capacity of 24 megawatts (MW), is expected to be completed in April, which will help to meet the increased demand for electricity during the summer months. Civil work associated with the project is now complete.The turbine was tested on Sunday, and the remaining tests will be conducted soon, according to officials from the Kerala State Electricity Board (KSEB). According to the Power Department, the Poringalkuthu SHEP will be the first hydro project of its size to be commissioned in nearly a decade. The Poringalkuthu SHEP, which will be built in the Chalakkudy basin, received its initial contract in October 2014 and was expected to be completed in 24 months. However, delays in transferring forestland to the contractor, the 2018 and 2019 floods, and the Covid-19 pandemic all hampered the project, forcing the KSEB to extend deadlines multiple times. Poringalkuthu SHEP has a 45.02 million units (mu) annual generation capacity and a project cost of 159.19 crore. Aside from Poringalkuthu, the 60 MW Pallivasal Extension Scheme, the 40 MW Thottiyar, and the 24 Bhoothathankettu schemes should all be completed by 2022-23 if all goes well. Work on all three projects was pushed back due to a variety of factors. The KSEB had a total installed capacity of 2,240.22 MW as of March 31, 2021, with hydel projects accounting for 91%, thermal 7.14%, and solar and wind projects accounting for the rest. The KSEB owns 40 hydroelectric generating stations, 17 of which are major. Four hydroelectric projects with varying capacities, which have been delayed, are expected to be completed in the fiscal year 2022-23, increasing the State's internal power generation capability. Image Source Also read: Policy for stalled private hydro projects likely for takeover

Next Story
Infrastructure Urban

Coal Ministry Achieves Milestones under Special Campaign 5.0

The Ministry of Coal and its Public Sector Undertakings (PSUs) have achieved notable milestones under the Special Campaign 5.0, focusing on cleanliness, operational efficiency, and sustainability across the coal sector. During the implementation phase from 2–31 October 2025, over 1,205 sites were cleaned, covering 68,04,087 sq ft, nearing the target of 82,51,511 sq ft. Scrap disposal of 5,813 MT against a target of 8,678 MT generated Rs 228.7 million in revenue. In addition, 1,11,248 physical and 30,331 electronic files were reviewed, with 74,123 weeded out or closed. Key initiatives showc..

Next Story
Infrastructure Energy

Vesting Orders Issued for Three Coal Blocks under Commercial Auctions

The Ministry of Coal’s Nominated Authority has issued vesting orders for three coal blocks under commercial coal block auctions on 23 October 2025. The Coal Mine Development and Production Agreements (CMDPAs) for these mines were earlier signed on 21 August 2025. The three blocks include Rajgamar Dipside (Deavnara), Tangardihi North, and Mahuagarhi. Of these, two are partially explored while one is fully explored, with a combined peak rated capacity of around 1 MTPA and geological reserves of approximately 1,484.41 million tonnes. These mines are expected to generate annual revenue of abou..

Next Story
Infrastructure Urban

TEC, IIT-Hyderabad Partner to Boost 6G and Telecom Standards

The Telecommunication Engineering Centre (TEC), technical arm of the Department of Telecommunications (DoT), has signed a Memorandum of Understanding (MoU) with the Indian Institute of Technology Hyderabad (IIT Hyderabad) for joint research and technical collaboration in advanced telecom technologies and standardisation. The partnership focuses on developing India-specific standards and test frameworks for next-generation networks, including 6G, Artificial Intelligence (AI), and Non-Terrestrial Networks (NTNs). It also aims to enhance India’s participation in international standardisation f..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?