Solar Growth May Slow Beyond FY28 on Awards, Grid Constraints
POWER & RENEWABLE ENERGY

Solar Growth May Slow Beyond FY28 on Awards, Grid Constraints

India’s solar capacity growth could face headwinds beyond FY28 as slower renewable energy project awards, delays in signing power agreements and transmission constraints threaten expansion, according to a report by Yes Securities. Near-term additions remain supported by a construction pipeline exceeding 150 GW and rising rooftop installations, but weaker award activity could affect capacity additions and industry volumes in FY29 and FY30.

Solar capacity additions nearly doubled to 44.61 GW in FY26 from 23.83 GW in FY25. Installations remained strong in the first half of FY27, when 21 GW of solar alternating current capacity was added. However, fresh renewable energy awards fell to 14.7 GW in FY26 from 40.6 GW in FY25, while only 4.7 GW had been awarded in FY27 up to August 10, 2026.

The slowdown has coincided with delays in securing power purchase agreements (PPAs) and power sale agreements (PSAs). About 40 to 45 GW of awarded renewable energy capacity was yet to secure these agreements, creating uncertainty over project execution. Yes Securities said the construction pipeline should support demand for solar modules through FY28, although weaker awards could affect volumes in the following two financial years.

Transmission bottlenecks and rising grid curtailment are adding to sector challenges. Solar power curtailment reached 8,133 gigawatt-hours (GWh) during April-June 2026, with Rajasthan and Gujarat among the states facing difficulties in evacuating renewable power. Curtailment occurs when available electricity cannot be transmitted or absorbed by the grid, limiting delivered power.

Rooftop and agricultural solar programmes continue to support installations and demand for domestic modules. The PM Surya Ghar scheme added 2.4 mn rooftop systems in the first half of FY27, compared with 1.7 mn during the whole of FY26. The PM-Kusum programme is also supporting domestically manufactured modules, while storage-linked tenders are emerging as another demand source, though they could direct more investment towards battery storage.

India’s solar capacity growth could face headwinds beyond FY28 as slower renewable energy project awards, delays in signing power agreements and transmission constraints threaten expansion, according to a report by Yes Securities. Near-term additions remain supported by a construction pipeline exceeding 150 GW and rising rooftop installations, but weaker award activity could affect capacity additions and industry volumes in FY29 and FY30. Solar capacity additions nearly doubled to 44.61 GW in FY26 from 23.83 GW in FY25. Installations remained strong in the first half of FY27, when 21 GW of solar alternating current capacity was added. However, fresh renewable energy awards fell to 14.7 GW in FY26 from 40.6 GW in FY25, while only 4.7 GW had been awarded in FY27 up to August 10, 2026. The slowdown has coincided with delays in securing power purchase agreements (PPAs) and power sale agreements (PSAs). About 40 to 45 GW of awarded renewable energy capacity was yet to secure these agreements, creating uncertainty over project execution. Yes Securities said the construction pipeline should support demand for solar modules through FY28, although weaker awards could affect volumes in the following two financial years. Transmission bottlenecks and rising grid curtailment are adding to sector challenges. Solar power curtailment reached 8,133 gigawatt-hours (GWh) during April-June 2026, with Rajasthan and Gujarat among the states facing difficulties in evacuating renewable power. Curtailment occurs when available electricity cannot be transmitted or absorbed by the grid, limiting delivered power. Rooftop and agricultural solar programmes continue to support installations and demand for domestic modules. The PM Surya Ghar scheme added 2.4 mn rooftop systems in the first half of FY27, compared with 1.7 mn during the whole of FY26. The PM-Kusum programme is also supporting domestically manufactured modules, while storage-linked tenders are emerging as another demand source, though they could direct more investment towards battery storage.

Related Stories

Gold Stories

Next Story
Infrastructure Energy

DMRC Invites Bids for Solar-Linked BESS Power Procurement

Delhi Metro Rail Corporation (DMRC) has invited bids for renewable energy from an Inter-State Transmission System (ISTS)-connected generating plant combining a solar photovoltaic (PV) system with a co-located Battery Energy Storage System (BESS). The procurement will be conducted through competitive bidding followed by an e-reverse auction. The last date for submitting online bids is December 10, 2026, at 3 PM. DMRC will open the technical bids on December 11, 2026, at 3 PM. The opening of financial bids and the e-reverse auction will be scheduled after completion of the technical evaluation. ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code