ACME Solar Commissions 51.87 MW BESS Capacity in Rajasthan
POWER & RENEWABLE ENERGY

ACME Solar Commissions 51.87 MW BESS Capacity in Rajasthan

ACME Solar Holdings has commissioned an additional 51.87 MW of battery energy storage system (BESS) discharge capacity in Rajasthan through its wholly owned subsidiary, ACME Sigma Urja. The commissioning milestones were disclosed on November 20, 2026, for projects at Neemri village in Rawatbhata tehsil, Chittorgarh district.

The first regulatory filing covered 35.81 MW and 148.645 MWh of discharge capacity. The installed capacity of this portion is 35.81 MW and 160.48 MWh. It forms part of a larger 50 MW and 209 MWh BESS linked to the company’s TATA FDRE Power Project, which has an overall installed capacity of 50 MW and 220 MWh.

ACME Solar said only the battery storage component of the TATA FDRE project had been commissioned. The commercial operation date is scheduled for November 22, 2026. The project is supported by a power purchase agreement signed with The Tata Power Company.

In a separate disclosure, ACME Sigma Urja reported the commissioning of an additional 16.06 MW and 69.678 MWh of BESS discharge capacity at the same location. The installed capacity of this portion is 16.06 MW and 75.225 MWh, and it forms part of a 250 MW and 1,069 MWh firm and dispatchable renewable energy project with an overall installed capacity of 250 MW and 1,150 MWh.

Following the latest additions, ACME Sigma Urja’s cumulative commissioned BESS discharge capacity has reached 175.72 MW and 733.939 MWh. Its corresponding installed capacity stands at 175.72 MW and 792.418 MWh. The company said the commercial operation date for the newly commissioned capacity is also scheduled for November 22, 2026. Both filings were made under Regulation 30 of the SEBI Listing Obligations and Disclosure Requirements Regulations, 2015, and signed by Rajesh Sodhi, company secretary and compliance officer.

ACME Solar Holdings has commissioned an additional 51.87 MW of battery energy storage system (BESS) discharge capacity in Rajasthan through its wholly owned subsidiary, ACME Sigma Urja. The commissioning milestones were disclosed on November 20, 2026, for projects at Neemri village in Rawatbhata tehsil, Chittorgarh district. The first regulatory filing covered 35.81 MW and 148.645 MWh of discharge capacity. The installed capacity of this portion is 35.81 MW and 160.48 MWh. It forms part of a larger 50 MW and 209 MWh BESS linked to the company’s TATA FDRE Power Project, which has an overall installed capacity of 50 MW and 220 MWh. ACME Solar said only the battery storage component of the TATA FDRE project had been commissioned. The commercial operation date is scheduled for November 22, 2026. The project is supported by a power purchase agreement signed with The Tata Power Company. In a separate disclosure, ACME Sigma Urja reported the commissioning of an additional 16.06 MW and 69.678 MWh of BESS discharge capacity at the same location. The installed capacity of this portion is 16.06 MW and 75.225 MWh, and it forms part of a 250 MW and 1,069 MWh firm and dispatchable renewable energy project with an overall installed capacity of 250 MW and 1,150 MWh. Following the latest additions, ACME Sigma Urja’s cumulative commissioned BESS discharge capacity has reached 175.72 MW and 733.939 MWh. Its corresponding installed capacity stands at 175.72 MW and 792.418 MWh. The company said the commercial operation date for the newly commissioned capacity is also scheduled for November 22, 2026. Both filings were made under Regulation 30 of the SEBI Listing Obligations and Disclosure Requirements Regulations, 2015, and signed by Rajesh Sodhi, company secretary and compliance officer.

Related Stories

Gold Stories

Next Story
Infrastructure Energy

DMRC Invites Bids for Solar-Linked BESS Power Procurement

Delhi Metro Rail Corporation (DMRC) has invited bids for renewable energy from an Inter-State Transmission System (ISTS)-connected generating plant combining a solar photovoltaic (PV) system with a co-located Battery Energy Storage System (BESS). The procurement will be conducted through competitive bidding followed by an e-reverse auction. The last date for submitting online bids is December 10, 2026, at 3 PM. DMRC will open the technical bids on December 11, 2026, at 3 PM. The opening of financial bids and the e-reverse auction will be scheduled after completion of the technical evaluation. ..

Next Story
Infrastructure Energy

Solar Growth May Slow Beyond FY28 on Awards, Grid Constraints

India’s solar capacity growth could face headwinds beyond FY28 as slower renewable energy project awards, delays in signing power agreements and transmission constraints threaten expansion, according to a report by Yes Securities. Near-term additions remain supported by a construction pipeline exceeding 150 GW and rising rooftop installations, but weaker award activity could affect capacity additions and industry volumes in FY29 and FY30. Solar capacity additions nearly doubled to 44.61 GW in FY26 from 23.83 GW in FY25. Installations remained strong in the first half of FY27, when 21 GW of s..

Next Story
Infrastructure Transport

India’s First High-Speed Rail Service to Begin in 2027

India’s first high-speed rail service will commence in 2027, with the Surat-Vapi section of the Mumbai-Ahmedabad High-Speed Rail corridor scheduled to open first, Railway Minister Ashwini Vaishnaw said. The remaining sections to Mumbai will be opened in phases. Vaishnaw said 456 km of pier work and 371 km of viaduct construction had been completed by September. About 600,000 noise barriers had been installed along a 299 km stretch, while 9,300 overhead equipment masts had been erected across a 206 km viaduct. Four mountain tunnels have been excavated, and 5 km of the 21 km Maharashtra tunnel..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code